Report No. PID9910 Project Name Indonesia-Energy Project Region East Asia and Pacific Region Sector Electric Power & Other Energy Adjustment Project ID IDPE63913 Borrower(s) GOI W/PARTIAL ONLENDING TO PLN & PGN Implementing Agency Address MOF, MEMR, MIGAS(PERTAMINA), DGEED, PLN AND PGN Ministry of Finance (MOF) Environment Category A Date PID Prepared November 17, 2000 Projected Appraisal Date July 9, 2001 Projected Board Date November 20, 2001 1. Country and Sector Background An underlying analysis of the main sector issues has been carried out in the context of two major sector studies financed by the Bank's own resources: one for the oil and gas (hydrocarbon) sector (which was completed in June 2000 under report number 20512-IND); and one for the electricity sector, which culminated in the Bank, ADB and USAID-supported launch of the Government's Power Sector Restructuring Policy in August 1998. The key issues are as follows.(i) Substantial subsidies for petroleum products and electricity. The energy sector presents one of the biggest challenges to the ability of Indonesia's Government to maintain fiscal sustainability, and consequently, macroeconomics stability. This is because the pricing structure of petroleum products and electricity is significantly distorted, at both the absolute, and relative (see v) levels. The domestic price for a composite barrel (of five major products representing over 97 percent of domestic fuel consumption) was roughly 43 percent of the international price in December 1999 (the amount of subsidy varies depending on the crude oil price and exchange rate). The Government's subsidies for petroleum products (estimated at US$4.9 billion in 1999) are huge by any measure, representing about 5 percent of GDP in 1999, or over 25t of the Government's routine expenditures. The loss in economic efficiency resulting from these subsidies is estimated at about US$780 million. If the subsidies are not removed, the amount that the Government would have to provide between now and the end of 2005 would be about US$24 billion. Furthermore, the subsidies provided to the fuels used for electricity generation mean that the costs faced by the power sector are understated (hence distorting sectoral investment and operating decisions). Even more significant than this indirect subsidy is the direct subsidy provided to the power sector (estimated at US$1 billion in 1999) to meet PLN's cash flow requirements. As a result of the depreciation of the Rupiah, PLN (the State electricity corporation) sells electricity at the equivalent of US3.0-US3.4c per kWh, while it purchases fuel, as well as electricity from independent power producers (see iv), in foreign currency. Consequently PLN's average costs per kWh are about twice as high as its average sale price.As part of the above-referenced sector work, the Bank has already proposed a program for the gradual removal of the fuel subsidies (Annex 4), taking into account the relative distortion of prices, as well as the impact of the program on the poor and on the cost of living. Although price increases will have substantial fiscal benefits, they will also have potentially adverse macroeconomics and social impacts. Consequently, immediate increases to market levels are seen as being unrealistic. Rather, fuel prices should gradually move to market levels over the medium term (i.e., five years), with the eventual goal being full price liberalization. Further, after each major increase, prices need to be periodically adjusted, under an appropriately designed formula (already provided to the Government), to reflect market conditions, and be prorated even while prices are still subsidized.Under the Bank's Second Policy Reform Support Loan (April 26, 1999), the Government made a commitment to implementing plans for the phased removal of both fuel and power subsidies, while protecting the poor and other targeted groups. However, several attempts by the Government during 1998 to mid-2000 to increase the prices of petroleum products (other than aviation fuels), met with strong public resistance. The Government thus deferred a fuel price hike several times, and eventually in September 2000, raised the prices of the five major products by an average of 12%. This increase, although less than that recommended by the Bank, was nonetheless a positive step, particularly as the relative increases (see v) were more or less in line with what the Bank had recommended. Several attempts to increase the power tariff, as required under the tranche-release conditions of ADB's Power Sector Program Loan were also delayed, and only last April the Government was able to increase the tariff by about 30% on average, which at today's exchange rate is the equivalent of USc---per kWh. (ii) Pertamina's dominant role and its inefficiencies in both upstream and downstream hydrocarbon sector operations. Another energy sector issue that has a substantial impact on Indonesia's economy is the problematic role and functions of Pertamina (the State oil, gas and geothermal agency). Key concerns are that: (a) Pertamina's direct operation in the exploration and production of oil and gas in its own concession areas is not efficient; (b) Pertamina acts as the Government's sole agent in supervising the activities of the private companies in the upstream oil and gas sector--thus creating an inherent conflict of interest, since Pertamina competes with the companies it supervises--and this supervisory role focuses more on control than on gaining added value for the Government, consequently contributing to delays and other inefficiencies; and (c) Pertamina enjoys a virtual monopoly over a huge market in downstream activities, a role which is not conducive to efficiency and reliability (with inefficiencies particularly severe in the refining subsector).The Bank in the context of its sector work has recommended that the Government carry out an assessment of the alternatives for reforming Pertamina in a fundamental way, including: (a) forming several full and legally binding subsidiaries, as well as initiating a major divestiture and/or partial privatization program; (b) removing the Foreign Contractors Coordinating and Management Body (BPPKA) from Pertamina and locating it under MEMR (possibly within MIGAS), or as a separate agency; (c) ensuring that Pertamina participates in upstream activities on an equal basis with private companies; and (d) removing Pertamina's monopoly status from downstream activities. With regard to latter, given the size of Indonesia's domestic petroleum market, it can attract international, regional and local investors if the right framework is put in place to make competition realistic and vibrant (see -2 - viii).Although in the last two years a number of changes have been introduced by the Government to gradually liberalize the sector, none have been implemented yet. The Government has in theory opened the refinery sector to private participation, liberalized the market for lubricants, indicated its intention to separate off Pertamina's geothermal operations, and lifted price controls on aviation fuels. However, in practice, there has not been substantive progress in these areas, and some of these policy initiatives are limited in the absence of fundamental changes to the legal framework (e.g., the private sector can build refineries, but cannot supply the major fuels to the domestic market--they can only sell these products to Pertamina). In compliance with an IMF requirement, the Government also appointed international auditors to conduct special audits of Pertamina. (iii) Current structure of the power sector. Given PLN's virtual insolvent state, its huge contractual obligations, its problematic corporate structure and some of the sectoral issues, continuous operation of PLN in its present form is untenable. Although a necessary step, a major increase in tariffs (and/or direct financial support) by the Government, is not in itself sufficient to ensure a sustainable long term solution to the power sector's problems. On the one hand, the Government faces an enormous fiscal burden from PLN (see i and iv), while on the other hand, PLN's own freedom to respond to evolving needs and circumstances is circumscribed by constraints imposed on it by the Government. Consequently, Indonesia needs to move in the same direction as many other countries that are transforming their electricity industries by unbundling vertically-integrated utilities (like PLN), and by moving to a competitive market-based industry structure governed by a independent regulatory framework.The electricity system on Java-Bali is relatively well-developed, and over the medium term can potentially be transformed into a commercially viable and financially independent operation, which in turn would allow the sale of PLN's Java-Bali assets. Operations would be governed by an independent regulatory body, and not by direct Government interference. However, operations outside Java are much less developed and will require stronger Government support for the foreseeable future, thus being more akin to the provision of a social service than the undertaking of a commercial activity.Consequently, the Government's Power Sector Restructuring Policy, launched in August 1998 (based on inputs from the Bank, ADB and USAID), requires the unbundling of PLN geographically, which will allow the distinct separation of PLN's potentially commercial operations in Java-Bali from those operations still requiring direct Government support over the longer term (outside Java-Bali). The Policy envisages the creation of a Regional Electricity Company (REC) comprising all of PLN's assets outside Java-Bali. Subsidies for electricity development outside Java-Bali will be channeled through a Social Electricity Development Fund (SEDF) until such time as those operations become wholly (or partially) commercially viable and financially independent. (However, any subsidies intended to directly support the utilization of electricity or of other fuels by the poor, whether outside Java-Bali or on Java-Bali, will be made explicit and transparent as a distinctly separate line item in the Government's budget). Further, the Policy requires that PLN's operations on Java-Bali be additionally unbundled by function (i.e., generation, transmission and distribution), to allow the transition to a competitive multi-buyer/multi-seller (MBMS) market for operations on Java-Bali, over the medium term (i.e., five years), and in preparation for privatization. As an interim step to full competition, which requires a change in the current legislation, the -3 - Government proposes first establishing a Single Buyer market on Java-Bali. Apart from enacting a new electricity law, another pre-condition of eventually moving to the MBMS market is for the power delivery system on Java-Bali to be sufficiently robust.The Government has taken steps to implement this Power Sector Restructuring Policy, by establishing, under the previous Government (Keppres 139/98), a cross-Ministerial Steering Committee to oversee the corporate and financial restructuring of PLN, as well as to rationalize the private power program (see iv). In parallel, the Minister of Energy and Mineral Resources has established a team to oversee the implementation of the needed legal and regulatory reforms, including the drafting of a new electricity law and implementing regulations. To support the implementation of the Policy, the Bank and ADB have been focusing on complementary areas of restructuring activities. ADB has already provided a program loan (about US$400 million) to the Government to deal with sectoral aspects of the restructuring such as development of legal and regulatory framework and the creation of the Single Buyer and MBMS markets. The Bank on the other hand has been focusing on the corporate and financial restructuring of PLN, by helping the Government and PLN to prepare the detailed design of the implementation plan, as well as by financing the consultancy services required for the actual implementation.(iv) Liabilities associated with Independent Power Producers (IPPs). In addition to PLN's other problems, it faces huge liabilities relating to independent power producers (IPPs). Although Indonesia's IPP program was successful at attracting private capital into the power sector, the contracts provided to the IPPs have resulted in huge real and contingent liabilities for PLN and the Government, as well as potentially excess generation capacity on Java-Bali. (Even before the growth slowdown caused by the crisis, PLN faced the prospect of substantial excess capacity on Java-Bali over the coming years). As a result, the Government is faced with an additional risk factor from the energy sector with regard to maintaining fiscal sustainability. Furthermore, successful implementation of the Government's Power Sector Restructuring Policy is also put at risk until this issue is resolved.The Government signed 26, mainly unsolicited, IPP contracts, which if they were all to be implemented would add about 11,000 MW to the country's installed generation capacity at a total estimated cost of about US$18 billion, or about US$130 billion in "contractual obligation" costs over the next 30 years. These contracts are in the main supported by a Government Letter of Comfort provided by the Ministry of Finance (MOF), and all capacity payments are payable in hard currency (mostly US dollars). Out of this 11,000 MW capacity, about 3090 MW (2895 MW in Java-Bali) have already been completed or are about to be completed shortly. While the tariff varies for each, their average tariff is over US6c per kWh. Since the crisis, PLN has been paying the dollar-denominated invoices of the currently onstream IPPs as if the exchange rate were still at pre-crisis levels, and the Government has announced the postponement, review or cancellation of the planned IPPs. Consequently, there have been several litigation cases, including a ruling by international arbitration tribunal in favor of one of the IPPs. Currently one or two interim agreements have been signed between the Government and the IPPs, but a long term solution is not at hand yet.(v) Distorted energy product pricing structure (especially for natural gas). At the relative level, the disparity between prices of individual petroleum products is large, as is the disparity between the prices of - 4 - natural gas, electricity and substitutable fuels. Electricity prices are further distorted by differences between consumer classes, and between regions, due to the imposition of a Uniform National Tariff. Consequently, the pattern of consumption for energy products is severely distorted, leading to a misallocation of producer and consumer resources.One outcome of this distortion is that the growth of the domestic gas industry has slowed down, whereas its expanded utilization could bring about significant environmental and economic benefits. For instance, the sale price of natural gas to the industrial and commercial sectors is about ------times the subsidized price of high speed diesel oil (Solar), its main competitor. Eliminating this subsidy from Solar would have allowed gas to substitute for around US$----million of Solar during 1999. Further, the structure of gas prices is not economic: the selling price of gas for some users is lower than its economic cost of supply, and for others is just barely sufficient to cover the costs; whereas with respect to its value to the economy, a substantial amount of economic rents (to the Government) are forgone.However, as the table in Annex 4 shows, it is not a straightforward case of simply structuring the gas pricing within an economic framework to reflect the economic cost and value of gas. This is because of the distortions in the prices of other petroleum products for which the gas could substitute. Thus, a rational gas pricing strategy must be developed that will take into account these relative distortions during the transition until the subsidies are gradually removed.(vi) Constraints on the utilization of domestic gas and on expanded private sector participation. In recent years, Indonesia has seen a decline in its net exportable oil, and hence in the associated revenues, because its growing domestic needs for energy have not been met by increased oil production or by substitutes. Development of the domestic gas market would serve to free up additional oil for earning hard currency, and also have significant environmental benefits. But such development is constrained both by the current distortions in the prices of petroleum products, discussed above (see v), and by the lack of an integrated gas transmission and distribution infrastructure. However, since the Government is unable to finance the required infrastructure expansion, there is a particular need for private equity. Increased private sector participation can be achieved in gas transmission through the involvement of strategic investors, and in gas distribution by partial privatization of PGN (the State gas corporation) through a minority initial public offering (IPO).The Government issued a Policy of Natural Gas Development in August 1997, outlining principles of: sector unbundling; introduction and promotion of private sector involvement and competition; deregulated pricing for non-residential consumers; infrastructure and market development; and the eventual establishment of an independent regulatory body. This policy was to be partially implemented through a Keppres for Natural Gas Transmission and Distribution, the latest draft being July 1998, which was also intended to clarify the existing legislative framework and consequently the roles of Pertamina and PGN in the domestic gas sector. However, this has been superseded by the drafting of a new oil and gas law (see viii).(vii) Poor urban air quality. The most serious cause of atmospheric pollution in Jakarta is vehicle emissions resulting from the combustion of petroleum products, with emissions from the industrial sector being the next most significant contributor. Measures of the health damage caused by different pollutants indicate that removal of lead from gasoline, a reduction of the sulfur content in diesel oil, and substitution of oil by - 5 - natural gas through the development of the domestic natural gas industry (see v and vi), could result in substantial health savings. For instance, if the leaded gasoline is phased out, it is estimated that there would be a US$6 billion reduction in environmental damage currently resulting from lead poisoning.Prior to the crisis, under the Government's Blue Sky program, Pertamina had planned to rationalize petroleum product specifications and to phase out leaded gasoline grades through various options such as increasing imports of high octane unleaded gasoline, blending oxygenates such as MTBE into the gasoline pool, and/or increasing the refinery production of high octane blend stocks such as reformate and FCC gasoline. And one of the commitments subscribed to by the Government in its letter of understanding with the IMF is to proceed with plans for the complete removal of lead from gasoline. However, financing either the required refinery modifications, or additional imports of high octane gasoline, has become difficult under the country's current economic circumstance.(viii) Deficiencies in the legislative framework for both the hydrocarbon and power sectors. A number of the above problems stem from, or are reinforced by, the current legislative framework for the energy sector. In the hydrocarbon sector, the existing laws and regulations sanction Pertamina's and PGN's sectoral dominance and allow the Government to interfere with the sector in ways that inhibit efficient sector operation and private sector participation. The Bank had provided significant inputs to the original draft oil and gas law during 1998. This version did not pass, and in any case was substantially modified, to its detriment, at the final stages. The Bank then recommended that the draft law be revised to more closely provide the framework for a competitively-based, market-oriented sector operation, involving less Government interference, and consistent with international industry best practice. However, the draft oil and gas law so far has still not been enacted. In addition, the associated regulations (based on detailed input provided by the Bank), have been reviewed by MIGAS, but are still pending.In the power sector, the competitively-based market operation envisaged for the sector under the Government's Restructuring Policy requires a new legal and regulatory framework. A new electricity law has been drafted, although not yet submitted to Parliament, and as part of the technical assistance associated with ADB's program loan, support will be provided for the development of an autonomous regulatory body with the capability to regulate the power sector.(ix) Institutional requirements for capacity building. All energy sector entities require capacity building to some extent, particularly given the new challenges which they will face during the transition to a more liberalized and market-oriented sector. In particular, the Government requires help to improve public acceptance of the need for fuel and power price rises. There are also a number of other specialized needs for capacity building. For instance, the current Minister of Energy and Mining Resources has expressed interest in establishing a National Energy Policy Office, and has indicated that external support would be required. Further, energy planning/forecasting functions and capabilities are currently spread among many Government agencies, and there are a number of weaknesses in the current approach to developing a cohesive overall energy plan, and supply and demand projections. Also, the draft oil and gas law requires many of Pertamina's roles to be transferred to another agency, in which case such an agency may require significant capacity building to be able to supervise and regulate PSCs, and DGEED needs to be strengthened to deal with new issues arising as a result of the restructuring of the power sector. - 6 - Consequently, sector institutions should be strengthened across the board, particularly where regulatory responsibilities are increased as a result of the reforms. 2. Objectives The objective of the Indonesia Energy Sector Project is to reduce the fiscal burden, and consequently the macroeconomics risks, of the energy sector on the Indonesian economy, while reducing the sector's adverse impact on the environment.This objective will be achieved under the Project through supporting the Government in its efforts to: n gradually phase out subsidies for fuel, by requiring the adoption of an automatic mechanism for the periodic adjustment of fuel prices, by developing effective mechanisms for delivering any targeted subsidies to the poor, and by augmenting the Government's ability to improve public acceptance of the need for fuel price increases and changes;n lay the foundation for a commercially viable, financially independent, and operationally secure and efficient power sector on Java-Bali, as well as allow the introduction of a Java-Bali competitive electricity market, by supporting the implementation of the corporate and financial restructuring of PLN, and by debottlenecking the Java-Bali power delivery system;f manage the subsidies for power development outside Java, by requiring the establishment of a Social Electricity Development Fund (SEDF);ft rationalize the energy product pricing structure (during the period until prices are fully deregulated), by developing, and requiring the implementation of, a rational gas pricing policy;n promote the development of the domestic natural gas industry, in order to free up additional oil for export, by assessing how the gas sector can be restructured and attract increased private sector participation, and by expanding the gas distribution infrastructure on West Java;n increase the domestic use of cleaner fuels, by prioritizing options to phase out lead from gasoline, (as well as through the achievement of the above actions to implement a rational gas pricing policy and expand the gas distribution infrastructure);ft improve capabilities for implementing sector reforms and planning for sector development, by strengthening the institutional capacity of the Ministry of Energy and Mineral Resources (MEMR), the Directorate General of Oil and Gas (MIGAS), and the Directorate General of Electricity and Energy Development (DGEED). 3. Rationale for Bank's Involvement n The past policy dialogue has provided critical support for mapping the reforms needed in the both the gas and, to a larger extent, power sectors. However, despite the above-mentioned commitments by the Government, ongoing Bank involvement is required to ensure implementation of the proposed reforms. For instance, the Government has indicated in its Statement of Development Policy (under the Second Policy Reform Support Loan) that it is looking to the World Bank to take the lead role in providing guidance and support for PLN's corporate and financial restructuring, and to the ADB to take the lead on the related legal and regulatory reforms. Without Bank involvement, it is clear that the desired reforms will not occur, and that the complementary areas addressed by ADB will hence also not be successful.n The Bank has worldwide experience in both hydrocarbon and power sector reform, and it is in a unique position to play a catalytic role in helping Indonesia in the design and implementation of the needed reforms.n The project component relating to the domestic gas sector builds on a solid record of two - 7 - successful prior projects with PGN.n The market-sounding of international gas utilities to determine private sector interest in the downstream gas business in Indonesia has revealed a strong private sector preference for the financial participation of the Bank in the sector, in order to reduce the potential investors' perception of political risks. 4. Description Although the Project is a primarily a sector adjustment operation, the inclusion of physical investment and technical assistance components in addition to the budgetary support component with its associated policy conditions, mean that it is in effect a hybrid operation. Project components will be scoped in more detail during project preparation. However, at this stage, the following components are envisaged.(1) Budgetary Support. The Project will include a relatively large budgetary support component to be released in two tranches. Policy conditions required for first tranche release will relate to: (i) the adoption by the Government of an automatic mechanism for the periodic adjustment of fuel prices; and (ii) the completion of a set of milestones for the initial stages of PLN's corporate and financial restructuring. The appointment of consultants for components (2), (4) and (5) below, as well as the establishment of an adequately staffed Project Implementation Unit (PIU), will also be first tranche release conditions. Policy conditions required for second tranche release will relate to: (i) the completion of a second set of milestones relating to PLN's restructuring, with particular focus on cash flow management, financial restructuring and the initial operation of the Single Buyer market; (ii) the establishment of the Social Electricity Development Fund by the Ministry of Finance; and (iii) the implementation by the Government of appropriate changes in gas prices, relative to other fuels, as determined by the Study performed under component (4) below.(2) Fuel Subsidy Removal Support. The Project will include a technical assistance component to the Ministry of Energy and Mineral Resources (MEMR) that will (a) develop effective mechanisms for delivering any targeted subsidies to the poor, with regard to their use of energy, and (b) augment the Government's ability to improve public acceptance of the need for fuel price increases and changes.(3) PLN Information Technology and System Delivery. The Project will include two investment subcomponents to PLN. The first subcomponent will include financing toward the management and financial information systems required to establish separate transmission, generation and distribution successor companies on Java-Bali which can be made commercially viable and operationally efficient. The development of a masterplan for PLN's information technology requirements will be undertaken as part of the technical assistance for the corporate and financial restructuring of PLN (provided under the Bank's Second Power Transmission and Distribution project), and this masterplan will identify the specific hardware and software requirements to be financed by the Project. The second subcomponent will include transmission, subtransmission, SCADA and any other related investments required on Java-Bali to (a) reduce system delivery constraints, (b) improve the reliability and quality of supply, and (c) allow the day-to-day operation of the Single Buyer, and subsequently MBMS, markets. Since the likely cost of these investments will be substantial, the Bank will be seeking co-financing assistance from possibly JBIC for this subcomponent.(4) Gas Pricing. The Project will include a technical assistance component to MIGAS for a short Study to develop a rational natural gas pricing strategy. The Study's findings and - 8 - recommendations will be used to develop the policy condition on gas pricing for second tranche release of the budgetary support component.(5) Gas Sector Restructuring and Private Participation. The Project will include a technical assistance component to PGN for (a) investigating options for restructuring, unbundling and decentralizing PGN's operations, particularly with a view to separating its transmission and distribution operations, (b) to assist PGN prepare for an IPO, and (c) to seek out a strategic partner for PGN's transmission operations.(6) Gas Distribution. The Project will include an investment component to PGN to expand its gas distribution network in West Java. Prior to the crisis, the Bank had been helping PGN to prepare the West Java Gas Distribution project, and had intended to provide financial support to this project through a proposed loan of US$100 million. The objective of that project was to support the Government's policy of fuel diversification, via expansion of Indonesia's domestic natural gas distribution network, given the economic and environmental benefits of substitution by gas. This objective still remains valid, although in light of the current economic situation, the scope of the physical component, which was to supply natural gas to all industrial and commercial consumers from Cilegon in the west of West Java to Purwakarta in the east, may have to be reviewed. Since it is likely that the Bank's proposed financial contribution will not be sufficient, it is intended that the balance will be co-financed by JBIC. Furthermore, since the major source of gas supply for the new distribution network is expected to come from South Sumatra, PGN is planning to construct a transmission line to transport gas from South Sumatra to West Java using (concessionary) financing from JBIC.(7) Phasing Out Leaded Gasoline. The Project will include a technical assistance component to MIGAS in order to extend the analysis of issues and options for phasing out leaded gasoline and for improving fuel specifications that will be carried out under a PHRD grant as part of project preparation. The nature of the technical assistance will depend on the recommendations of the PHRD-funded study.(8) Capacity Building for MEMR, MIGAS and DGEED. The Project will include a technical assistance component to MEMR, MIGAS and DGEED to improve energy planning, forecasting and policy implementation capabilities, to review the taxation of energy products, and to assist MIGAS in successfully dealing with many of Pertamina's roles, should this be required. (1) Budgetary Support Physical Investments (2) PLN information technology and system delivery (3) PGN gas distribution Technical Assistance (4) Fuel subsidy removal support (5) Gas pricing (6) Gas sector restructuring (7) Phasing out leaded gasoline (8) Capacity Building 5. Financing Total ( US$m) GOVERNMENT 310 IBRD 420 IDA -- Total Project Cost 730 6. Implementation 9 n Implementation period: 4 years.n Executing agencies: (i) Ministry of Finance for the budgetary support component and also for setting up the Social Electricity Development Fund; (ii) PLN for its corporate and financial restructuring as well as for the power sector investment components; (iii) PGN for the gas distribution investment component and the associated TA on restructuring and private sector participation; (iv) MEMR for implementing fuel and power price changes and adjustment mechanism, as well as for the TAs on fuel subsidy removal support and for its capacity building; (v) MIGAS for the TA on gas pricing, for the TA on capacity building and for the TA on phasing out leaded fuels (possibly in coordination with Pertamina); and (vi) DGEED for its capacity building TA.n Onlending: The Government will onlend to PLN and PGN the funds associated with PLN's investment and the gas distribution components. This will be done under Subsidiary Loan Agreements, which would pass on all costs and risks, including foreign exchange risk, incurred by the Government to PLN and PGN.n Monitoring and evaluation arrangements: The Bank will closely supervise progress with policy reforms and with project implementation progress by (a) the establishment of a cross-Ministry Project Implementation Unit (PIU) as a condition of loan effectiveness (i.e., first tranche release condition), (b) the establishment and monitoring of appropriate monitoring and evaluation indicators, (c) reviewing quarterly project progress reports from the PIU and all executing agencies, and (d) undertaking regular field missions.n Disbursement and auditing arrangements: With the exception of the budgetary support component, separate project accounts will be maintained by each of the executing agencies concerned and independently audited by an auditor satisfactory to the Bank. In addition, PLN and PGN would be responsible for submitting to the Bank each year its audited corporate accounts. PLN has been audited by a private auditor (Has Tuanakotta & Mustofa/Deloitte Touche Tohmatsu) while PGN has been audited by the State auditor (Financial and Development Supervisory Board). However, in both instances, accounting standards have been based on those generally accepted in Indonesia. In the event local accounting standards differ from international accounting standards (IAS) in selected accounting treatments, agreement would be sought for the disclosure of the impact of applying IAS on the company's financial position. In addition, as part of the preparation for partial privatization of PGN, agreement would be sought for PGN to be audited by a private auditor acceptable to the Bank. 7. Sustainability The sustainability of the project is dependent on the mitigation of the critical risks below, in particular on minimizing the public reaction to the removal of subsidies for petroleum products and electricity, since a strongly negative reaction might detrimentally impact the stability of the political environment. 8. Lessons learned from past operations in the country/sector It should be pointed out that lessons learned with respect to past experience in Indonesia were gained under an environment characterized by sustained rapid growth and social stability. The situation is now very different and there is no reason to assume that past lessons will necessarily be relevant in the current environment. Nonetheless, the following lessons learned and how the project design will deal with them, are quite relevant. Hybrid Operations and General Project Design n The advantage of a hybrid operation is the potential for increased leverage on - 10 - policy reforms. However, cross conditionalities between policy outcomes and investment components need to be carefully designed. The Project has clear linkages between policy reform outcomes and investment components (see B.3 and D.l).n Complications may occur if there is large co-financing without clearly defined investment components. The Project's investment components, including those being co-financed, will be well prepared/appraised, as if this were a standard sector investment loan.n The speed and size of reforms are to take account of the social and political conditions in the country. A hybrid operation (or APL) will provide an appropriate time frame for the Project (see D.1), and components are specifically included to mitigate the social impact of reforms (see C1.2).n Government has in the past shown flexibility in accepting tough policy conditions, but less commitment to their implementation . The Project design will front-load the conditionalities, and in the process will ensure that some key actions will take place prior to the Board presentation. n Technical assistance needs to focus on organization rather than just on studies or planning. The Project's TA activities will be linked to institutional development and organizational restructuring, instead of simply being isolated individual studies. Appropriate arrangements will be made to ensure follow up actions on the recommendations, in some cases through tranche conditions.Power Sectorn The timetable for unbundling large power utilities needs to be realistic, taking into account various social and political considerations. Project implementation extends over a longer period than a typical sector adjustment operation.n Rural electrification programs must be financially sustainable. The Project requires the establishment of a Social Electricity Fund.Gas Sectorn The pricing of natural gas and the corporate structure of PGN also need to be addressed in order to accelerate the development of the domestic gas industry. The objectives of the previous gas distribution projects in Indonesia were to expand the physical network and enhance efficiency and financial position of the gas distribution company. The Project addresses the sectoral issues as well, such as gas pricing, the restructuring of PGN and the increased participation of the private sector, and the Government's statement of gas sector policy marks a turning point in this regard.n International experience in the gas sector shows that private participation in the sector is often enhanced through establishing a competitive gas market including getting gas to consumers at competitive prices. The pricing reforms under the Project will encourage the evolution of a competitive gas market. General and Project Implementationn Financial covenants need to be relevant and achievable. For instance, a rate of return on revalued assets covenant to measure financial performance is not appropriate for a company like PLN with a very large and lumpy investment program, and in the process of unbundling. This, and particularly the financial and corporate restructuring of PLN, will be reflected in the formulation of project covenants. n Appropriate performance indicators (especially outcome or impact indicators to measure the performance of PLN and PGN) and monitoring are essential. These will be developed during project preparation.n Attention needs to be given to accurate cost estimates and on application of contingencies, as well as to availability of counterpart fundings. Cost estimates (especially those for physical investments) will be based on the latest market prices and future development trends, and firm commitment will be sought from PLN and PGN on availability of counterpart fundings.n Problems arising from dealing with affected people during implementation. Affected people will be involved from the early - 11 - stages of project preparation and throughout implementation, to gain and maintain their support. 9. Program of Targeted Intervention (PTI) N 10. Environment Aspects (including any public consultation) Issues Environmental issues are associated with both the adjustment and investment components of the Project. A key objective of the Project is to reduce the impact of the energy sector's impact on the environment, particularly in regard to improving urban air quality (and reducing greenhouse gas emissions). This is to be achieved through supporting the Government in its efforts to increase the domestic use of cleaner fuels, by prioritizing options to phase out lead from gasoline, as well as by promoting the development of the domestic natural gas industry. These outcomes are supported by policy conditions associated with the adjustment component, as well as by the investment component for gas distribution.There are, however, potentially adverse impacts associated with phasing out leaded gasoline, such as the potentially high benzene and aromatic content of unleaded fuel if specifications are not comprehensively monitored. There may be other positive and negative benefits associated with the policy reforms supported by the Project, and these will be assessed further during project preparation. 11. Contact Point: Task Manager M. Farhandi The World Bank 1818 H Street, NW Washington D.C. 20433 Telephone: 202-458-0478 Fax: 202-522-1648 12. For information on other project related documents contact: The InfoShop The World Bank 1818 H Street, NW Washington, D.C. 20433 Telephone: (202) 458-5454 Fax: (202) 522-1500 Web: http:// www.worldbank.org/infoshop Note: This is information on an evolving project. Certain components may not be necessarily included in the final project. This PID was processed by the InfoShop during the week ending February 2, 2001. - 12 -