ELECTRICITY OF VIETNAM SOUTHERN POWER PROJECT MANAGEMENT BOARD RP82 VOL. 17 PHUOC LONG 220kV SUIiSTATION According to the Decision No.3072/QD-EVN-T October-49'h, 3#02df EVN, the Phuoc Long 220kV substation had been chaiged the nan to Binh Long 220kV substation / Code: 43015 RESETTLEMENT ACTION PLAN 41~~~~~~~~~~~* v~~~~~~~~ 2 /~~~~ October, 2005. TUV QUALITY MANAGEMENT SYSTEM ISO 9001 -.2000 C6NG TY TIJ VAN XAY DING 9IfN 3 ELECTRICITY OF VIETNAM SOUTHERN POWER PROJECT MANAGEMENT BOARD PHUOC LONG 220kV SUBSTATION According to the Decision No.3072/QD-EVN-TD dated October 29th, 2004 of EVN, the Phuoc Long 220kV substation had been changed the name to Binh Long 220kVsubstation Code: 43015 RESETTLEMENT ACTION PLAN Head of Department Duong Thi Thanh Truc Project Director Duong Thi Thanh Truc Member Tran Quang Khai Tran Nguyen Quang Hu HCMC, October 18th 2005 POWER ENGINEERING & CONSULTING COMPANY No.3 VICE DIRECTOR C . TI KHANH BINH October, 2005 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan TABLE OF CONTENTS EXECUTIVE SUMMARY .....................4 1. Initial introduction ..........................................4 2. Scope of project - socio-economic profits of the project ........................................4 3. Total investment - capital source ..........................................4 4. Impacts of the project ......4...................................4 5. Ligibility ..........................................4 6. Resettlement principles...........................R.................................................5 7. Entitlement policy.............................................5 8. Public participation and consultation ................5 9. Complaints and grievances ................6 10. IInstitutional arrangement ................6 11. Schedule...........................6.................6 12. Cost estimate...........................6.................6 13. Monitoring and evaluation ................6 CHAPTERI ...............................................7 INTRODUCTION ...............................................7 1.1. The target of project ...............................................7 1.2. Project description ...............................................7 1.3. Impacts of the project .......7.......................................7 CHAPTER II ...............................................8 MITIGATION MEASURES ..............................................8 2.1. Measures during the design stage ...............................................8 2.2. Measures during the construction stage ...............................................8 2.3. Results of efforts ..............................................8 CHAPTER III ...............................................9 RESETTLEMENT POLICY AND ENTITLEMENT ........................................9 3.1. Legal framework ..............................................9 3.2. Definition and limitation of eligibility .............................................. 11 3.3. Resettlment and compensation principles .............................................. I 1 3.4. The validity of right claiming compensation .............................................. 11 3.5. Compensation policy .............................................. 12 3.6. Impact categories and entitlement policy .............................................. 12 3.7. Subsidy allowances .............................................. 13 CHAPTER IV ..16 PROJECT IMPACT ..16 4.1. Socio-economic surveys .16 4.2. Results of census and socio-economic surveys .16 4.3. Total impacts of the project .17 CHAPTER V ......... 18 INSTITUTIONAL ARRANGEMENT .................................. 18 5.1. Electricity of Vietnam and Southern Power Project Management Board .............. l 8 5.2. Power Engineering & Consultant Company No.3 (PECC3) ................................. 18 5.3. Provincial Compensation Committees .................................. : 18 5.4. Provincial Finance and Price Department and Ministry Of Natural Resource and Environment (MONRE) .18 PECC3 1/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan 5.5. Provincial Compensation Committees ........................... 18 5.6. District People's Committees ........................... 19 5.7. District Compensation Committees ........................... 19 5.8. Commune People's Committees ........................... 19 5.9. Project affected people (PAPS) ........................... 20 5.10. Independent monitoring company ........................... 20 5.11. Organization ........................... 20 CHAPTER VI ..21 IMPLEMENTATION ORGANIZATION . .21 6.1. Establishment of resettlement committees .21 6.2. Select the independent monitoring agency, review unit costs applied in RAP . 21 6.3. Compensations and allowances calculation .21 6.4. Submit to Provincial People's Committees for the compensation schedule and costs' approval ..... 21 6.5. Detailed measurement survey (DMS) .22 6.6. Public announcement .22 6.7. Deadlines of compensation and resettlement .22 6.8. Monitoring .22 6.9. Schedule .22 CHAPTER VII ..24 COSTS AND BUDGET . .24 7.1. Compensation costs .24 7.2. Total cost of RAP .25 CHAPTER VIII ..26 CONSULTATION AND PARTICIPATION . .26 8.1. PuRAPoses .26 8.2. Periods of public consultant .26 CHAPTER IX ..28 COMPLAINTS AND GRIEVANCES . .28 9.1. Procedure of complaints and grievances .28 9.2. Legal guarantees for complaints and grievances .28 CHAPTER X . .29 MONITORING AND EVALUATION . .29 10.1. Internal monitoring .29 10.2. External monitoring .29 PECC3 2/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan ABBREVIATION RAP Resettlement Action Plan PPC Provincial People's Committee PAP Project Affected People PAH Project Affected Household SPPMB Southern Power Project Management Board EVN Electricity of Vietnam PECC3 Power Engineering & Consulting Company No.3 WB :World Bank RCC Resettlement & Compensation Committee VND Viet Nam Dong ROW Right of way TABLES Table 3.1 Subsidy allowances of the project Table 3.2 Entitlement matrix Table 4.1 Total impacts of phan thiet 220 kv substation Table 5.1 Provincial Resettlement Board Personnel of the Project Table 6.1 RAP implementation schedule Table 7.1 Compensation cost of the project Table 7.2 RAP executing cost Table 7.3 Total cost of RAP execution ANNEXES Annex 1 Drawings Annex 2 Form of socio-economic surveys Annex 3 Results of socio-economic surveys Annex 4 Compensation prices Annex 5 Minutes of meeting on public consultation Annex 6 Images of public consultation meeting Annex 7 Agreement document of Local PPC on RAP PECC3 3/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan EXECUTIVE SUMMARY 1. INITIAL INTRODUCTION The Phuoc Long 220kV substation is proposed to be built on a farming land cultivating perennial trees (includes: cashew, pepper and other fruit trees) which belongs to the Gruop No.4, Thanh Tuan hamlet, Thanh Luong commune, Binh Long district, Binh Phuoc province. The investor of the project is Southern Power Project Management Board, oh behalf of Electricity of Vietnam with total invested cost is 148,473,973,448 VND. The capital source is from the remaining budget of "System Efficiency Improvement, Equitization and Renewable" (SEIER) project, the credit 3680-VN of WB. 2. SCOPE OF PROJECT - SOCIO-ECONOMIC PROFITS OF THE PROJECT The puRAPoses of Phuoc Long 220/110kV substation project are: - Concentrate and distribute the electricity capacity from Hydropower plants such as Thac Mo, Can Don and Srok Phumieng to the Southern main economic area in order to exploit effectually the output capacity of electrical sources. - Resisting overcharged for the existing 110kV transmission line and also the constructing power network of the area. - Enhancing the capacity of providing electricity and increasing the reliability and safety in power supplying for 110kV power network that can satisfy the increasing demand of additional charge of Binh Phuoc province and surrounding areas in period 2006-20 10. - Decreasing capacity and electrical energy loss of the 110kV power network of the area and increasing the electrical quality. 3. TOTAL INVESTMENT - CAPITAL SOURCE - Investor: Southern Power Project Management Board (SPPMB) - Electricity of Vietnam (EVN) - Management agency: Southem Power Project Management Board (SPPMB) - Investing capital: 148,473,973,448 VND - Capital source: From the remaining budget of "System Efficiency Improvement, Equitization and Renewable" project, credit 3680-VN, borrowing from World Bank. 4. IMPACTS OF THE PROJECT There will be a total of 5 affected households. These households will be only impacted on agricultural land cultivating perennial trees, includes: Permanent acquisition land : total of the permanent acquired land for the substation is 24,220 m2 and tower foundation is 743 m2 - Temporary impacts: the damage of trees, crops around construction areas of tower foundation and substation or the temporary roads for construction activities. Total of affected land in ROW of the connecting line is 5,297 m2 5. ELIGIBILITY The cut-off day is proposed to be set on January 3 lt, 2004. Project affected households (PAHs) are all households, institutions or organizations owning, renting or using land (with or without legal paper) that are affected by this project. All above households have right to be compensated for lost properties when they are in the inventory list or they can prove that they owned, rented, or used these properties before the cut-off day. Households having incomes affected by this project are applied similarly. PECC3 4/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan Households encroach into the project affected area after the cut-off day will not be compensated. 6. RESETTLEMENT PRINCIPLES The capital resource of this project is from the remaining budget of SEIER project, credit No.3680- VN of WB. The policies applied in RAP of the SEIER project were approved by Viet Nam Government and cleared by WB. So, the resettlement principles applied in this project followed the principles in RAP of the SEIER project and obeyed Vietnamese laws and World Bank policy on involuntary resettlement (OP 4.12). 1. Resettlement and compensation programs must be designed so as to allow the improvement or at least the maintenance of living standards of PAPs as before the project. 2. Both resettlement and land acquisition must be minimized as much as possible. 3. Resettlement distance must be minimized in case compensation is land-for land type. 4. Cash compensation for houses or structures shall be paid at the substitution cost; cash compensation for crops shall be paid at the market-price. 5. Resettlement period must be minimized and the cash of compensation should be provided to PAPs before the beginning of the construction activities affecting them, no site clearing if the full compensation have not been done yet. 6. All of PAPs who have houses and/or parcels located in the project area before the cut-off date are entitled receiving compensation according to their lost properties and/or incomes. 7. ENTITLEMENT POLICY The resettlement principles applied in this project followed the principles in RAP of the main project and obeyed Vietnamese laws and World Bank policy on involuntary resettlement (OP 4.12). The policies were approved by Viet Nam Government and cleared by WB. Affected land area less than 25% total area and other losses are compensated in cash at the costs that were submitted by RCC to local PPC for approval. Affected land area more than 25% total area is compensated by the same quality and area or cash according to PAPs' option. The compensation costs for this project will be based on the compensation costs that were submitted by the RCC to the PPC for approval. Compensation is at approved costs for land, houses and perennial trees and at market prices for annual crops. The cost estimated for this RAP is based on the official price frames of Provincial People's Committees according to: - The Decree No. 20/2003/QD-UB dated March, 18th 2003 of Binh Phuoc Provincial People's Committees on "Promulgation of compensation policy for land and compensation costs for houses, crops, structures in Binh Phuoc province" - Regulations of Decree No.87-CP of GOV and Circular No.145 of Ministry of Finance. All the compensation unit costs will be re-checked at the beginning of RAP implementation by the Resettlement and Compensation committees (RCC) and, if necessary, they will be adjusted to meet the costs that were submitted by the RCC to the PPC foe approval and be approved by the Chairman of Local People Committee based on the proposal of the Local Finance and Price Department. Besides of compensation for damage, the affected households also will be received allowances and subsidies according to regulation of Decree 197. The allowances and subsidies are noted in Compensation Policy of the province. 8. PUBLIC PARTICIPATION AND CONSULTATION This RAP is developed in close consultation with local authorities of Binh Phuoc province and PAP~s in order to maximize their participation in Resettlement Action Planning and implementing and the socio-economic benefits of PAPs to the project. The consultation with PAPs in disseminating PECC3 5/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan information and getting their feedback will reduce contradiction and avoid delays in project implementation. Local authorities and PAPs were consulted on line alignments, resettlement policy, RAP implementation, grievance mechanism, and monitoring and evaluation on the restoration of PAPs' livelihoods after the project implementation 9. COMPLAINTS AND GRIEVANCES During the project implementation, PAP's complaints will be dealt with according to the Complain and Denounce Law of Vietnam and will be treated and guided fairly by related agencies. No addition fee will be paid for their complaints. The complaints mechanism is instructed in chapter VIII of this RAP. 10. INSTITUTIONAL ARRANGEMENT EVN and SPPMB are responsible for all of operations of the project including RAP implementation. SPPMB will be helped and closely cooperated by People's Committees of Binh Phuoc province and local relevant institutions. 11. IMPLEMENTATION SCHEDULE - Establish compensation committees, select an independent monitoring agency, calculate compensation unit costs, consult from community would be carried out within one month as from the beginning of project's implementation. - Compensation will be conducted after 3 months as from Provincial People's Committees has approved compensation cost and implementation schedule. - Receiving, dealing with complaints and grievances as from Provincial People's Committees approved compensation cost until project completion. - Monitoring will be carried out during project implementation. 12. COST ESTIMATING Total compensation costs are estimated about 806,175,000 VND, estimated cost for RAP implementation is about 183,808,750 VND. Total estimated cost for the resettlement program is about 1,143,431,231 VND. 13. MONITORING AND EVALUATION The implementation of RAP shall be constantly supervised and monitored by SPPMB. Moreover, an independent consulting agency will be entrusted with independent monitoring tasks. The independent monitoring agency selected by SPPMB will sign a contract just after RAP approval and will begin supervision and monitoring activities from the beginning of the RAP implementation phase. PECC3 6/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER I INTRODUCTION 1.1. THE TARGET OF PROJECT - Concentrate and distribute the electricity capacity from Hydropower plants such as Thac Mo, Can Don and Srok Phumieng to the Southern main economic area in order to exploit effectually the output capacity of electrical sources. - Resisting overcharged for the existing 110kV transmission line and also the constructing power network of the area. - Enhancing the capacity of providing electricity and increasing the reliability and safety in power supplying for 110kV power network that can satisfy the increasing demand of additional charge of Binh Phuoc province and surrounding areas in period 2006-2010. - Decreasing capacity and electrical energy loss of the 110kV power network of the area and increasing the electrical quality. 1.2. PROJECT DESCRIPTION Total area of the Phuoc Long 220kV substation is 24,220 m2 including the area of substation and access road. The substation locates on the Group No4, Thanh Tuan hamlet, Thanh Luong commune, Binh Long district, Binh Phuoc province. Substation size: - Model: semi-outdoor, frequently watched. - Voltages: 220/110/22kV - Output capacity: 2xl25MVA 110kV connecting route: connect from the Ham Thuan - Phuoc Long 110Kv transmission line, Thac Mo - Tay Ninh 110kV double circuit transmission line and Srokphummieng - Loc Ninh 11 OkV transmission line to the Phuoc Long 220kV substation. 1.3. IMPACTS OF THE PROJECT Main impacts of the Phuoc Long 220 kV substation include: - Permanent land acquisition at substation site, access road - Temporary impacts in construction phase due to material transport According to results of socio-economic survey, the project does not intersect any ethnic minorities or historical and cultural monuments. Basing on the investigation of Power Investigation and Construction Division (PECC3), the total of 2 2 the permanent acquired land area is 24,963 m (for substation is 24,220 m , pole foundations of connecting route is 743 mi2), temporary acquired land area for connecting route is 5,297 M2. The acquired land is perennial tree cultivated land. The project takes no impact on houses, residential land and other kinds of land. PECC3 7/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER II MITIGATION MEASURES 2.1. MEASURES DURING THE DESIGN STAGE Many efforts are carried out to minimize the adverse impacts at the FS as well as the design stage, such as: In this phase, in order to minimize the project's impacts, the substation position is selected to meet the below requirements: - Locations of the subprojects (substation, access road, line direction) is as near as possible to the existing national grid to minimize length of connecting tap, so, minimize land acquisition and losses; - Location of the project is nearby transportation roads; - The site chosen for the substation must agrees with the overall socio-economic planning program of the local, concurrently minimize the impacts on the environment. - Selection based on consultations with, agreement of local authorities, local people. There are 3 alternatives for the substation location, and the alternative No.2 is selected because this alternative only impacts on agricultural land, without impact on houses of inhabitants. 2.2. MEASURES DURING THE CONSTRUCTION STAGE In the construction stage, the construction organizing method and schedule will be used and optimized to comply with the current regulation of construction works and to minimize the negative impacts: - The temporary roads serving for construction are considered carefully (should go through vacant areas) in order to minimize the impacts and compensation. - Camps for workers in the construction period will be located on the favourable area, nearby headquarter of communes. 2.3. RESULTS OF EFFORTS The impacts of the project are shown as follows: - Permanent acquired land area that must be compensated is 24,963 m2 and the temporary acquired land is 5,297 m2. 100% of this land is agriculture land which is cultivating perennial trees and other fruit trees. - Among 5 PAHs, there are 3 PAHs will be acquired more than 25% of its area. - No impact on pagodas, temples, places of historical interest, natural reserved areas, - No impact on the community ethnic minorities. PECC3 8/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER III RESETTLEMENT POLICY AND ENTITLEMENT 3.1. LEGAL FRAMEWORK The capital source of this project is from the remaining budget of the SEIER project, credit CR3680- VN of WB financial resources. The resettlement policies applied in this project follow current Vietnamese laws on "Compensation and Resettlement" and the guideline of World Bank on involuntary resettlement (OP4.12). 3.1.1. Related laws, decrees and regulations 1. The Land Law of Vietnam dated July 14th, 1993. Amendment dated November 26th, 2003. 2. The Government Decree N 197/2004/ND-CP dated December 3rd, 2004 on compensation for the damage when the State recover land for national defense, security, national interests and public interests; 3. The Government Decree No.181/2004/ND-CP dated October 29th, 2004 on the instruction for The Land Law 2003. 4. The Government Decree No.188/2004/ND-CP dated November 16th, 2004 on the method the determining of the land price and frame price for types of land. 5. The Circular No. 114/2004/TT-BTC dated November 26th, 2004 of the Ministry of Finance, on the instruction for Decree No.188/2004/ND-CP of the Government on the method the determining of the land price and frame price for types of land. 6. Tlhe Circular No.116/2004/TT-BTC dated November 26th, 2004 of the Ministry of Finance, on the instruction for Decree No.197/2004/ND-CP dated December 3 h, 2004 of the Government on compensation, support and resettlement when the State recover land. 7. The Government Decree No 54/1999/ND-CP dated July 8th, 1999 on the protection of the high voltage network and the Circular No.07/2001/TT-BCN dated Sep. 1it 2001 8. The Government Decree No. 118/2004iND-CP dated May 10th, 2004 on adjustment and ,h amendment of some items of the Decree No.54/1999/ ND-CP dated July 8' , 1999 on the protection of the high voltage network. 9. Circular 07/2001/TT-BCN of Department of Industry dated September 01st, 2001 on implementation guiding for some technical item stipulated in Government Decree No.54/1999/ND-CP dated July 08th, 1999 on safety protection of high voltage electrical network. 10. Circular No 106/2002/TTLT/BTC-BCN dated Nov 22nd, 2002 of Ministry of Industry on the compensation and subsidy costs for high voltage power network project. l1. The Decree No. 20/2003/QD-UB dated March, 18th 2003 of Binh Phuoc Provincial People's Committees on "Promulgation of compensation policy for land and compensation costs for houses, crops, structures in Binh Phuoc province" In order to carry out RAP according to OP 4.12 of the World Bank, some law provisions and decrees/circulars of Vietnam that not ensure the compensation according to the approved price or stipulating the provisions that not apply the compensation right and life recovery for the households who have not got valid documents in owning land will be dispensed from the applying by the Vietnam Government based on the approval of RAP policies of the SEIER project, credit 3680-VN. 3.1.2. OP 4.12 guideline of the World Bank According to the Guidelines of World Bank in Involuntary Resettlement Policy, project affected persons (PAPs) will be ensured improving or maintaining the living standards as before having the project. In order to agree with OP 4.12 of the World Bank, all of PAPs that are listed will be PECC3 9/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan project. In order to agree with OP 4.12 of the World Bank, all of PAPs that are listed will be compensated for lost properties. Only persons who settle at the site affected by the project after the statistical cut-off date are not compensated. Too, in order to agree with OP 4.12 of the World Bank, houses, structures, trees will be compensated according to substitution cost and farm produces, short-day crops will be compensated according to market costs. 3.1.3. Essential elimination In order to implement RAP according to OP 4.12 of the World Bank, some provisions of the law or regulation of Vietnam that not ensure the compensation according to the approved price or stipulate the provisions that not apply the compensation right for the affected households that not have valid documents in owning land will be dispensed from the applying. The provisions will be eliminated including: (i) Damage compensated right - Decree 197/CP Article 6 of Decree 197/CP (people that not be compensated for the loss of land) stipulate "People that is recovered land that not having one of conditions stipulated at Article 8 of this decree or offend against the plan that have been approved and promulgated at land using time or offend against security corridor of work; people that occupied land illegally will not be compensated for the lost land. In case of needing support, the province people's committee will considered at each specific case. Article 17 of Decree 197/CP (The principle of compensation for lost property), section 2, stipulate "Owner of the property that locate in illegal land as stipulated at Article 7 of this decree will be considered to support at each specific case by province people's committee". In order to ensure meeting the fundamental principles of RAP, the waivers of applying Article 7 and Article 17 of Decree 197/CP (to allow the households having illegal land as above to be compensated) were approved by Vietnam Government and cleared by WB for RAP of the SEIER project, credit 3680-VN. (ii) The land price for calculating compensation According to the regulation of the Vietnamese Government, the compensation price is calculated based on Decree 87/CP, 197/CP, 17/1998/ND-CP and Decision 20/2003/QD-UB of Binh Phuoc Provincial Poeple's Committee and the actual prices of lands in the local. The unit price for land compensation will be submitted to PPC for approval base on the proposal of the local Finance and Price Department or the RCC, and be ensured to equalize to substitution cost. (iii) Compensation principle - Decree 197/CP Article 19 of Decree 197/CP stipulates the compensation solutions for house, structure in different legal situations. In order to ensure meeting the fundamental principles of RAP, waivers of applying Article 19 and Article 20 of Decree 197/CP (in order to allow the households having affected house and structure to be compensated) were approved by Vietnam Government and cleared by WB for RAP of the SEIER project, credit 3680-VN. (iv) Support policy for the people hiring house that is owned by the Government - Decree 197/CP Article 21 of Decree 197/CP and Article 7 of Decision 4755/QD-UB-QLDT stipulate "PAPs are using the houses that be owned by the Government and located in the recovered scope if do not want to continue hiring Government's houses will be entitled to compensation at a rate equal 60% of the cost of the rented house and 60% of the cost of land". The waivers were approved by Viet Nam Government and cleared by World Band (for RAP of the SEIER project, credit CR3680-VN). The related PPCs will issue the official letter for their agreement in implementing the policies set forth in RAP. PECC3 0/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan 3.2. DEFINITION AND LIMITATION OF ELIGIBILITY The cut-off day is proposed to be set on January 315', 2004. Project Affected Person (PAP) are all individuals, firms or institution with or without land registration papers who owned, rented or used land, properties and business which are affected by the project: All PAPs will be enztitled to full compensation for their respective losses as long as they are included in the PAP intvenztory list or can prove that they used the affected itenms before the cut-off day. The samle applies to PAPs whose incomes are affected by the project. The cut-off date of this RAP has been fixed at the day of the inventory, DMS completion and will be proclaimed by local authorities. Encroachers who settled into the proposed affected areas after the cut-off date will have no entitlement to compensation and resettlement. They will be required to demolish their structures and cut the trees or harvest the crops for land clearance to the project. In case necessary, they will be forced to remove out the proposed project area. Nevertheless, they do not have to pay any fine or sanction. 3.3. RESETTLMENT AND COMPENSATION PRINCIPLES These principles obey the Vietnamese laws and World Bank policy on involuntary resettlement. Vietnamese legislation and World Bank directives have been adapted to fit the specific condition of the project as define below: - Resettlement and compensation programs must be designed so as to allow the improvement or at least the maintenance PAP's living standards as before executing the project. - Both resettlement and land acquisition must be minimized as much as possible. - Resettlement distance must be minimized in case compensation is land-for land type. - Cash compensation for houses/or structures shall be paid at the substitution cost; cash compensation for farm produce shall be paid at the market-price. - Resettlement period must be minimized and the cash of compensation should be provided to PAPs before the beginning of the construction activities affecting them, no land clearance if the full compensation has not been done yet. - All of PAPs having houses and land located in the project area before the cut-off date are entitled receiving compensation for their lost properties and/or income. - Resettlement and compensation plan should be carried out with consultation of PAP and approval by local authorities. - Resettlement and compensation plan must provide adequate institutional arrangement to warrant effectively and timely the proper implementation and monitoring. - Financial and technical resources for the resettlement and compensation should be available whenever required. - The living standards and income in the new sites should be maintained or improved more than before having the project. - The regulations in this RAP will be enforceable as an official legal document after be approved by the Government of Vietnam. 3.4. THE VALIDITY OF RIGHT CLAIMING COMPENSATION Legal PAPs are all of the affected households and organizations in the list (with or without legal paper of using land) or they can prove owning, hiring or using land and properties relating to land before the cut-off date of statistic. PECC3 11/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan In addition, legal PAPs are the households and organizations that having affected profession and/or business and income by the project due to temporary or endless recovery of land or different properties too. 3.5. COMPENSATION POLICY - Compensation for losses of farm products will be provided at the market prices. Compensation for houses, structures, trees, and other assets will be provided at the costs that were approved by the PPC. - Compensation for land losses less than 25% of total land PAP holding will be paid at the appvoved cost for lost land area and all other losses in cash. - Compensation for land losses equal or more than 25% of total land PAP holding will be provided in terms of land at the equivalent area and quality or in cash depending on PAP's choice. - Compensation price will be defined according to tariffs established by the provinces and based on the Decree 87-CP and the Circular 145 of the Ministry of Finance. - Due to the time from preparation to project execution can extend so the estimated price could unsuitable to market price or approved price at the time executing project. Therefore all of prices will be checked again and adjusted if necessary when beginning RAP implementation. Detail survey report will be carried out as soon as begin the project execution by resettlement committee. Independent monitoring agency, Province Finance Department will assess price list at the executing time. - Compensation for crop will be paid in cash at the market rates and be calculated on productivity average of the last 3 years (on Circular 145 of Ministry of Finance). - Compensation for land, houses and trees will be paid in cash at the approved price. 3.6. IMPACT CATEGORIES AND ENTITLEMENT POLICY By the nature of the project as described above and based on the surveys on the PAPs, the impacted categories could be classified as below: 3.6.1. Temporary impact: All of households have land, crops, trees or structures locating in ROW of the connecting route or in the temporary service roads. Category 1: The households have trees, crops, which are damaged temporarily by the project during the construction period due to material transport or pulling electric wire. 3.6.2. Permanent Impact: The households have land and properties that will be recovered permanently for the tower foundations, the substation area, and the permanent roads for construction and maintenance of the project. All of households have houses (totally or partially of house area) or structure, or trees located in corridor of transmission line, which need to be removed, demolished, or cut. Category 2: The households have -house or structure which are partially dismantled and the dismantled portion will not affect to the safety of the entire house or structure and will be rebuilt in adjacent areas of the same owner. Impact on clearing away for residential areas will be temporary and it can be reused for restricted puRAPoses. * Category 3: The households have house or structure which is partially or totally dismantled (and the dismantled portion more than 25% house area or lower than 25% but unsafe for house structure), still having land for rebuilt. PECC3 12/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan Category 4: The households have house or structure which are partially or totally dismantled, (and the dismantled portion more than 25% house area or lower than 25% but unsafe for house structure), but does not have spare residential land for reconstructing house. Category 5: The households have agricultural land which will be acquired permanently by the project including the construction of tower foundations, substation and permanent roads for manager and maintenance of the project. Category 6: The households have the job or other services are affected by the project. Basing on the investigation and compensation standards, the classification table on compensation standards is prepared as table 3.2. 3.7. SUBSIDY ALLOWANCES Besides the direct compensation for the losses, PAPs also entitled to subsidies/allowances as stipulated in the Decree No.197 of GOV. These allowances are as below: 3.7.1. Subsidy for house moving (transport allowance) (Article 27, Decree No.197) This allowance is for PAPs who are totally impacted on houses and have to be move to new sites or reorganize to the remaining residential areas. PAHs which have to move their houses to new places will be entitled to an allowance of 3,000,000VND. 3.7.2. Relocation Subsidy for Resettlement (Article 28, Decree No.197) This subsidy allowance is a food allowance for PAPs who are totally impacted on house and therefore have to reconstruct for their new houses. Each member of PAH will be subsidized 30kg of rice (equivalent) /person/month in six months. 3.7.3. Timely Movement Incentive (Article 26, Decree No.22) PAHs, who relocate on timely manner, will get a bonus of 3,000,OO0VND/household (maximum 5,000,000 VND/ household) 3.7.4. Rehabilitation Allowance (Article 29, Decree No.197) For PAHs which are permanent affected from 50% to 70% of productive land or incomes, 2 labour will be entitled to the allowance for each PAH; PAHs are more than 70% of productive land or incomes, all people in labour age will be entitled to the allowance of 1 ,000,OOOVND/person. Table 3.1: SUBSIDY ALLOWANCES OF THE PROJECT No Type of allowance Number of allowanced persons/ households 1 Transportation allowance (households) 0 2 Rehabilitation allowance (persons) 0 3 Allowance for difficulties of changing occupation (persons) 12 4 Timely movement incentive (households) 0 PECC3 13/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan Table 3.2: ENTITLEMENT MATRIX TYPE TYPE OF LOSS APPLICATION DEFINITION OF COMPENSATION POLICY IMPLEMENTARY MEASURES STANDARD Temporary acquisition All of PAPs The households with or Cash compensation for: - Compensation for the affected trees will be at the of lands, trees, crops in without land registration The affected trees based on the type and prices approved by PPC. the corridor of paper or able to prove age - Compensation is executed before clearing away at I transmission line occupancy or using The crops based on the crop type and least I month. lands prior to cut-off average productivity of the last 3 years. - Information on compensation must be announced date are listed. The quantity of crop will be calculation widely. __________________ in temporary encroachment time. Partial dismantled Households The households with or Cash compensation for the directly House/structure losing less than without land/house affected rooms plus the walls based on (impact less than 25% 25% of their registration paper are type of house. 2 and no cause unsafe for house and relative listed. Not compensating for land. remaining structures) residential land with spare land for area. reconstruction. Partial or total Households The households with or - Cash compensation for the directly -Project Manager Board and local authorities dismantled losing more or without land/house affected area at the approved price and determine and ensure the compensation price to be house/structure (impact less than 25% of registration paper are dismantled spending. calculated at approved price not including salvaged more or less than 25% their house but listed. - Compensating for affected land materials and dismantled costs. 3 but can cause unsafe can cause unsafe - Relocation allowance of 30kg of rice - Households receiving compensation will for the remaining for the remaining per person per month in 6 months. reconstruct their house themselves. structure) with spare structure... - Transport allowance. - Compensation will be executed before clearing land for reconstruction. - Allowance of timely movement away at least 3 months. incentive. Partial or total The households The households with or PAPs can choose one of the followings: - House or structure is dismantled partly or retained dismantled lose partly of their without legal paper of -Cash compensation for the affected land by Article 8 of Decree 54/1999/ND-CP. house/structure, no house or structure owning land and house and houses/structures based on the - Consultancy in choice for the households. Project spare land for and the remaining are listed house/structures types. Manager Board and local authorities determine and reconstruction. land outside the -House and land compensation in ensure the compensation price to be calculated at corridor of resettlement areas. approved price. 4 transmission line -Land and cash compensation for - PAPs receiving compensation will dismantle and is not large affected house or structure. reconstruct their house themselves in case of cash enough for the And: compensation or moving themselves to resettlement reconstruction of - Relocation allowance of 30kg of rice area. a house per person per month in 6 months. - Compensation will be executed before clearing equivalent to the - Transport allowance. away at least 3 months lost one. - Allowance of timely movement ________________________ ___________________ incentive. PECC3 14/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan TYPE TYPE OF LOSS APPLICATION DEFINITION OF COMPENSATION POLICY IMPLEMENTARY MEASURES STANDARD Permanent acquisition The households The households with or The households lost agricultural - Consultancy in choice for the households. Project of land for tower have land to be without legal paper of forestry land: Manager Board and local authorities determine and foundations and recovered using land are listed a. Land loss less than 25% of their total ensure the compensation price to be calculated at substation. permanently for area: Cash compensation for lost area. approved price. tower or b. Land loss more than 25% of their total substation area: Land compensation for lost area if foundations: remaining land still economic value and a. Land loss less land compensation for total area if than 25% of their remaining land no more economic value. Consultancy in choice for PAPs. 5 total area Cash compensation for properties related b. Land loss more to land. than 25% of their The households lost resident land: total area - If remaining land is enough for living (>60m2 if at towns and > I 00m2 if at rural areas): Cash compensation for lost area and related properties. - If remaining land not enough for living: PAP can choose to be compensated by cash or land for total area and related properties. Affecting to job and All PAPs (a)Temporary impact Compensation for lost income will be executed other services Compensation for lost income in the before clearing away at least I month. 6 affected time. Consultancy in choice for the households. (b) Permanent impact Preparing outline of restoration program in the Grant for restoration phase executing RAP. PECC3 15/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER IV PROJECT IMPACT 4.1. SOCIO-ECONOMIC SURVEYS Socio-economic survey was carried out by PECC3 in April, May 2004. This section aims at providing basic data about socio - economic characteristics of the project area. These data are based on surveying of PAHs having land in ROW and the substation area. The survey information is on income sources, income, socio-economic situation; impact of resettlement on living standard and income. A lot of information was obtained. Some households could not point out the concrete income source and their revenue. However with 100% of PAPs included in the survey, socio-economic survey on PAPs also aims at identifying characteristics of affected area, assessing the development of population, houses, socio-economic, average income, health care, education, etc... 4.1.1 Population The substation locates on relative flat area, mainly is agriculture land used to cultivate perennial trees such as cashew, pepper and other fruit trees. This area having scattered resident with mean population density is 184 persons/km2. The characteristics of affected households: - The average number of persons per household is 5.4, a bit higher than that of the whole country (4.97). Among which, the biggest household has 8 persons. - Young people (from 0 to 17 years old) present 33.3%. - The productive age group and old people accounts for 66.7%. 4.1.2. Income Sources of income: the main source of incomes of PAHs is from agriculture activities. Almost PAPs live by agriculture, a little is handicraft and wage-earner. The average monthly income of PAHs is 3,600,000 VND/month, among which PAH has highest income is 5,000,000 VND/month and the lowest is 2,400,000 VND. The living standard of PAHs is in average level, 100% PAHs are connected to the power network, having motorbikes and televisions. 4.1.3. Education Almost PAPs have secondary education level (make up 80% of the total PAPs), 20% of PAPs have primary education level, no PAP has high-school or university level of education. 4.2. RESULTS OF CENSUS AND SOCIO-ECONOMIC SURVEYS The survey results are shown as follows: - There will be a total of 5 affected households (27 persons), all affected households will be impacted on agricultural land. There are no households will be affected on houses or other structures. - Among 5 PAHs, there are 3 PAHs will be acquired more than 25% of its area. However, these PAHs choose to be compensated for the affected land in cash. - There is no impact on natural preserving zones, vestiges, pagodas, sensitive areas and ethnic minorities. - Total affected land area by the project is 24,963 m2 permanent acquired land and needs to be compensated, this area is for constructing foundation of the substation. The temporary acquired land for ROW is 5,297 m2 in area. PECC3 16/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan 4.3. TOTAL IMPACTS OF THE PROJECT Table 4.1 TOTAL IMPACTS Of PHUOC LONG 220 KV SUBSTATION Affected land Houses Affected tree & crop Kind Land area Affected houses Perennial tree Annual Crop Permanent Temporary Kind Number Area Kind Number Kind Area (m2) (in2) l (m2) (class) (item) (mi) (m2) 1. Substation 1 0 Cashew 915 Residential 0 0 2 0 Pepper 290 Agriculture 24,220 0 3 0 Longan 30 Forestry 0 0 4 0 Gum tree 300 2. Connecting route Temporary Residential 0 0 Agriculture 743 5,297 Forestry 0 0 Total 24,963 5,297 PECC3 17/29 Electricity of Vietnam Phuoc Long 220 kVl Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER V INSTITUTIONAL ARRANGEMENT 5.1. ELECTRICITY OF VIETNAM (EVN) AND SOUTHERN POWER PROJECT MANAGEMENT BOARD (SPPMB) EVN is the project's investor, grants authority to SPPMB to plan and carry out all aspects of project, including RAP implementation. For direct works on the ground, SPPMB will be helped and closely coordinated by People's Committees of Binh Phuoc province and local relevant institutions. Department of Technology, Science, Environment and Telecommunication, belongs to EVN, is in charge of guiding and supervising the implementation of RAP for the project. 5.2. POWER ENGINEERING & CONSULTANT COMPANY NO.3 (PECC3) PECC3 was assigned to carry out the census, inventory survey and prepare RAP cooperating with SPPMB to organize the public consultation for the project. 5.3. PROVINCIAL COMPENSATION COMMITTEES - Approving RAP and directly dividing the responsibility to their relevant institutions in RAP implementation. - Approving unit prices of compensation, allowances and establishing appraising committees, compensation committees at all different administrative levels - Approving documents of revoking and transferring land for compensation in the area of province. - Redressing complaints and grievances 5.4. PROVINCIAL FINANCE AND PRICE DEPARTMENT AND DEPARTMENT OF NATURAL RESOURCE AND ENVIRONMENT (DONRE) Provincial Finance and Price Department is responsible for researching and promulgating compensation price then offers to Provincial People's Committee for approving. At the beginning of the RAP's implementation, Finance and Price Department co-operates with Construction Department, DONRE, Agricultural and Rural Development Department, People's Committee of districts and the independent supervising organization in order to evaluate the applied unit prices in RAP and offer to Provincial People's Committees for the adjustment if it is necessary to make sure that the compensation unit costs are at the approved price at the time of the compensation payment. 5.5. PROVINCIAL COMPENSATION COMMITTEES The provincial compensation committees are mainly responsible for: - Helping district compensation committees in preparing the detail plan of compensation and resettlement. - Checking all inventories of impacts of the project and the detailed implementation plans of compensation and resettlement submitted by District Compensation Committees. - Resolving the complaints if the compensation is not satisfied at district level. Provincial compensation committee will include the representatives of: + Finance and Price Department + Construction Department + Department of Natural Resource and Environment PECC3 18/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan + Chairman of people's committees of district and commune + Representatives of Project Management Board 5.6. DISTRICT PEOPLE'S COMMITTEES District People's Committees are responsible for guiding the compensation and activities of resettlement of districts, including: - Guiding the relevant institutions for implementing the impact investigation, public consultation, information dissemination on the resettlement policies and RAP implementation. - Establishing the District Compensation Committees. - Resolving the complaints or queries of PAPs at the district level 5.7. DISTRICT COMPENSATION COMMITTEES These institutions are mainly responsible for implementing RAP in district area. District compensation committee includes experienced officers in the investigation and gathering information. The District compensation committee is responsible for: - Organizing the survey team to carry out the detail measurement survey (DMS) for affected houses and properties; finalizing DMS and entitlement form for each PAP. - Checking compensation unit prices used in RAP, proposing to adjust the unit prices in conformation with market prices/approved costs (if it is necessary). - Cooperating with SPPMB, organizing meetings with PAPs, local authorities and popularizing entitlement forms to PAPs. - Basing on policies and approved processes of RAP, preparing detailed implementation plans (quarterly, semi annual, annual plans) and together with SPPMB paying the compensation money to PAPs in a timely manner. - Settling complaints and grievances of PAPs, resolving any difficulties during the project implementation, and pointing out solutions for the outstanding issues to Provincial Compensation Committees and Developers. - District Compensation Committees will be headed by Vice-Chairman of District. The District Compensation Committee includes representatives of: - Finance and Price Department. - Land Department - Industry Department - Affected communes. - PAPs 5.8. COMMUNE PEOPLE'S COMMITTEES Commune People 's Committees are responsible for: - Supplying information for investigation and statistic works and contributing to census and inventory surveys. - Co-operating with District Compensation Committees to organize public meetings, information dissemination, paying the compensation money and allowance to PAPs. - Transferring all feedbacks of PAPs to District Compensation Committees, resolving complaints at the communal level and proposing solutions for the outstanding problems (if any). PECC3 19/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan - Supporting local inhabitants to overcome all troubles during the construction period and assisting PAPs in repairing of affected houses. - Arranging land for land in case PAPs ask for compensation by the way of changing land by land. 5.9. PROJECT AFFECTED PEOPLE (PAPS) PAPs are responsible for carefully checking on their lost properties and respective entitlements and clearing land in a timely manner after receiving full entitlements 5.10. INDEPENDENT MONITORING COMPANY Monitoring all of the establishment and resettlement aspects, supplying SPPMB with reports about the rate of progressing, the quantity and quality of execution activities. 5.11. ORGANIZATION Table 5.1: Provincial Resettlement Board Personnel of the Project District Resettlement Board No Member of Unit Number of Work duration staff 1 PPC 1 haft month Part time 2 Department of Finance and 1 haft month Part time Price 3 Project Management Board 2 2 months Part time 4 DOSTE 1 haft month Part time District's Finance and Price 1 haft month Part time Department 6 District's Industry Department I haft month Part time District's Land Survey 1 Deatmn haft month Part time Department District's Agriculture and 8 Rural Development 1 haft month Part time Department 9 District People's committee 2 haft month Part time 10 Commune People's committee 1 1 months Part time 1 Land Survey Department of 2 2months Part time Commune 12 Representative of PAPs 2 2 months Part time Total 16 11 months Part time PECC3 20/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER VI IMPLEMENTATION ORGANIZATION RAP's implementation activities will be processed immediately after receiving government and World Bank's approval. The following organizations and institutions will be involved in the preparation and implementation of the compensation and Resettlement Action Plans for the project: - Provincial People's Committees of Binh Phuoc. - Electricity of Vietnam (EVN) - Southern Power Project Management Board (SPPMB) - Power Engineering & Consulting Company No.3 (PECC3) - Finance and Price Department - Department of Natural Resource and Environment - Construction Department - People's Committees of District and Commune - Land Survey Department of District and Commune - Resettlement Committees of District and Commune - Representatives of PAPs RAP's implementation including: 6.1 ESTABLISHMENT OF RESETTLEMENT COMMITTEES As soon as the project is approved, Compensation Committee will be established by the People's Committees of provinces and districts. 6.2 SELECT THE INDEPENDENT MONITORING AGENCY AND REVIEW UNIT COSTS APPLIED IN RAP At the early time of RAP implementation, SPPMB will select the qualified institutions for this task. The independent monitoring agency will review the RAP implementation and the unit costs applied in RAP, recommend for modifying if it is necessary 6.3 COMPENSATIONS AND ALLOWANCES CALCULATION At the beginning of the RAP implementation, Finance and Price Department co-operates with Construction Department, DONRE, Agricultural and Rural Development Department, People's Committee of districts and the independent supervising organization in order to evaluate the applied unit prices in RAP. 6.4 SUBMIT TO PROVINCIAL PEOPLE'S COMMITTEES FOR THE COMPENSATION SCHEDULE AND COSTS' APPROVAL The schedule as well as compensation unit costs, allowances and their adjustment (if it is necessary to make sure that the compensation unit costs are at the approved prices at the time of the compensation payment) will be submitted to Provincial People's Committees for the approval by the Provincial RCC. After approved, that costs and allowances will be applied and announced to PAPs in that province. PECC3 21/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southern Power Project Management Board Resettlement Action Plan 6.5 DETAILED MEASUREMENT SURVEY (DMS) SPPMB and Resettlement Committees will carry out DMS and finalize for their entitlements. The final result of DMS and entitlements will be disseminated to PAPs by communal authorities. SPPMB and RCs will also clearly inform PAPs on the adjustment for compensation unit costs. 6.6 PUBLIC ANNOUNCEMENT Just after the project approval, PAPs will be fully informed about the project, their rights and the specific policies of this RAP including eligibility provisions, entitlement policies, types and rates of compensation and allowance, adjusted compensation costs (if any), results of DMS, schedules, complaint and grievance rights and mechanism. Such information will be also delivered to the PAPs by SPPMB via meetings and documents leaved at Commune People's Committees or other places that are informed to each PAPs. Resettlement pamphlets will also be disseminated to each PAPs. 6.7 DEADLINES OF COMPENSATION AND RESETTLEMENT - The compensation money for one-part damaged houses will be paid at least three months before starting the constructive execution. - The house repairing allowance will be paid together with the compensation money for the one- part damaged house. - The moving allowance will be paid at least six months but in just one time. - The compensation money for affected land areas and crops will be paid at least one month before starting constructive execution. - Affected land tenure households will be clearly cleaned up the required area at least one month before starting constructive execution. - The affected part of resettlement-households will be removed at least one month before starting constructive execution. In case of not complying, proper organizations will have rights to remove and the allowance for removing will be withdrawn. * 6.8 MONITORING This task will be done by SPPMB and the independent monitoring agency through out the whole period of the RAP implementation 6.9 SCHEDULE One of provisions of this RAP is that RAP should be done in accordance with proposed basic principles. All RAP activities must be satisfactorily completed before World Bank gives a no objection for award of contract for the projects. Any changes to the RAP after WB clearance will require review by the WB Office in Hanoi before commencement of construction. This means that construction works must be logically followed and not preceded the execution of RAP program. In other words, in case of retards in RAP execution, the delay will be reflected in construction works. The proposed schedule for RAP implementation is shown in table 6.1 PECC3 22/29 Electricity of Vietnam Phuoc Long 220 kV Substation Project Southem Power Project Management Board Resettlement Action Plan Table 6.1: RAP IMPLEMENTATION SCHEDULE 2004 2005 2006 No Items 2 344 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 0 12 1 Establish the provincial RCC and select the independent monitoring agency 2 Carry out the DMS 3 Calculate and adjust compensation unit costs 4 Public consultation and participation Te Provincial People's Committee 5 approves compensation costs and schedules 6 Proclaim schedules, the DMS results and compensation unit costs. 7 Compensation payment 8 Land clearance Receive and resolve complaints and 9 grevances ---- ---- ----- 10 Monitorng activities - I - - - T - I- PECC3 23/29 Electricity of Vietnam Phuoc Long 220kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER VII COSTS AND BUDGET 7.1. COMPENSATION COSTS The compensation costs for houses, land and trees/crops are calculated based on the Decree No. 20/2003/QD-UB of Binh Phuoc Province and reality land prices in the local. These costs will be reviewed and adjusted by RCC and approved by Binh Phuoc PC at the beginning of RAP implementation to ensure that PAPs will be compensated at the approved costs for land, houses, trees, crops according to this RAP policy. 7.1.1 Compensation for Land According to Article 8 of Decree 1 97/CP stipulates that the compensation costs of revoked land shall be determined on the basis of local land prices that is issued according to the revisions of the Government multiplied by a coefficient "K" in order to guarantee the compatibility of compensation with the profitability and the price of transfer land use right in the locality. 7.1.2. Compensation for Houses According to article 18 of Decree 197/CP stipulates that house will be compensated from 1% to 100% of the new house value. In this RAP, compensation for house is calculated at 100% value of the new one. 7.1.3. Compensation for Annual Crops According to article 24 of Decree 197/CP guides that compensation for annual crops are calculated based on the average yields of the latest 3 years multiply with the market price at the calculation time. 7.1.4. Compensation for Trees and Fruit-Trees According to article 24 of Decree 197/CP guides that trees will be compensated at the real price at the time of land acquisition (fruit-tree will be compensated by the real price in the time of revoking land, trees will be compensated for the remaining harvests). 7.1.5. Compensation for other Properties Properties such as electric meters, telephone reinstall, graves, wells, tombs, etc... will be compensated at the approved costs In order to comply the project's resettlement policies, at the time of RAP implementation, the relevant departments under the PPCs and the Independent Monitoring Agency will carry out the survey on the approved costs for land, houses, trees and market prices for crops in the local area. Adjusting the compensation unit costs will be done by PPCs (if necessary) to ensure that the compensation costs for land, houses, trees are at the approved costs and the compensation costs for crops are at the market prices The cost estimate for RAP is shown in Table 7.1: PECC3 24/29 Electricity of Vietnam Phuoc Long 220kV Substation Project Southern Power Project Management Board Resettlement Action Plan Table 7.1. COMPENSATION COST OF THE PROJECT Unit price Total No Items Unit Quantity VND VND A Compensating House/Structure 0 B Land Compensation 624,075,000 1 Agriculture land m2 24,963 25,000 624,075,000 C Compensation for perennial trees 170,100,000 1 Cashew Amount 915 120,000 109,800,000 2 Pepper Amount 290 120,000 34,800,000 3 Longan Amount 30 150,000 4,500,000 4 Gum tree Amount 300 70,000 21,000,000 D Compensation for others 0 E Allowances 12,000,000 1 Rehabilitation Persons 0 720,000 0 2 Occupation changing Persons 12 1,000,000 12,000,000 Total (A+B+C+D+E) 806,175,000 7.2. TOTAL COST OF RAP Total cost estimated RAP is 1,143,431,231 VND. This included compensation cost and the cost for compensating work. The Calculating Cost Table for compensation activities is shown in Table 7.3 Table 7.2 RAP EXECUTING COST Unit price Total No. Item Unit Quantity VND VND 1 Survey land Substation 3,500,000 3,500,000 2 Plant landmark Substation 10,000,000 10,000,000 3 Cost for PR report 80,000,000 4 Independent monitoring Cost 50,000,000 5 Cost for RCC 5% compensation cost 40,308,750 Total l 183,808,750 Table 7.3 TOTAL COST OF RAP EXECUTION No. Item Formula Total A Compensation Cost table 7.1 806,175,000 B Executing cost table 7.2 183,808,750 l C Escalation 5% x (A+B) 49,499,188 D Contingency(*) 10% x (A+B+C) 103,948,294 Total 1,143,431,231 (*) In experience, there are many variations during the period of the project implementation, the contingency should be accounted at 10% PECC3 25/29 Electricity of Vietnam Phuoc Long 220kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER IX COMPLAINTS AND GRIEVANCES Since the entire resettlement and rehabilitation program is being carried out with the participation of the PAHs, it is expected that no grievance issue will be raised. However, to ensure that the PAHs have avenues for redressing their grievances related to any aspect of compensation and resettlement, detailed procedures of redresses of grievances have been established for the project. The objective is to respond to the complaints of the PAHs speedily and in a transparent manner. The mechanism is designed to be easy, transparent and fair. PAH's complaints and grievances will be dealt with according to customary procedures and according to Vietnamese law. PAH's complaints will be treated fairly and must be facilitated with assistance as they plead their cases. In addition, no fee shall be levied on them and in case legal supports are necessary, this shall be given to them free of charge. 9.1. PROCEDURE OF COMPLAINTS AND GRIEVANCES The sequence of complaints and grievances including: 1) Step 1: If there is any aspect of the resettlement and rehabilitation program from a PAP, it will be sent to Commune People's Committee. Commune People's Committee will transfer their contents to SPPMB and cooperate with SPPMB to resolve it through direct negotiation within 15 days from the day received complaints and grievances. 2) Step 2: If PAP is not satisfied with the decision in step 1, the complaints shall be brought and solved at related District authorities with the cooperation of SPPMB within 15 days from the date of the receipt of the decision in step 1. 3) Step 3: If the step 2 also fails, complaints will be transferred to provincial authorities. Fifteen-day period is limit time of resolving. 4) Finally, if the PAP is still dissatisfied with the decision, he/she can appeal to the Provincial/District People's Court (DPC) in accordance with the "Civil Procedure Act" within 15 days of receiving the decision of the SPPMB without being charged. DPC decision will be a legal basis for compensation. 9.2. LEGAL GUARANTEES FOR COMPLAINTS AND GRIEVANCES In order to make sure that SPPMB consider PAH's complaints and a fair settlement of litigation cases, negotiations will be observed by PAH's witnesses. Further, PAHs have rights to ask the helping of their selected representatives PECC3 28/29 Electricity of Vietnam Phuoc Long 220kV Substation Project Southern Power Project Management Board Resettlement Action Plan CHAPTER X MONITORING AND EVALUATION RAP shall be constantly supervised and monitored by SPPMB in cooperation with local People's Committees. The WB OP 4.12 on Involuntary Resettlement recommends that independent activities are carried out. An independent monitoring agency will be entrusted with external monitoring tasks. The interested institutions have to submit their technical and financial proposals to SPPMB for review and then to WB for its concurrence. The chosen external monitoring institution shall be contracted by the SPPMB immediately after RAP approval and shall begin supervision and monitoring activities from the beginning of the implementation phase. Terms of Reference for independent monitoring will be prepared by SPPMB and then submit to WB for its concurrence 10.1. INTERNAL MONITORING Internal supervision and monitoring include: a. Monitoring the investigation of population and social economy situation and inventorying the PAP's damages, status, occupation and living condition and supervising the compensation, resettlement and rehabilitation of PAP in the term agreed by the PAP. b. Monitoring whether the implementation of resettlement and compensation tasks are cared out as provided in this RAP. c. Monitoring the availability and quality of replacement land. d. Monitoring the timely and sufficient deployment of resettlement and compensation funds for this RAP. e. Investigate and fairly assess each case of complaint and grievance. f. Internal monitoring agencies will prepare a quarterly report detailing the progress of RAP implementation. Such a report should be made available to appropriate Government authorities, WB and external monitoring agencies. 10.2. EXTERNAL MONITORING Beside evaluation the quarterly reports produced by internal monitors and conduct the same thing of investigation assigned to internal monitoring, the external monitoring agency will be responsible for following activities: a. Review and evaluate the inventoried results and entitlements determination. Check unit costs of compensation applied in RAP, to see if they are still at the approved costs and market prices at the time of RAP implementation and recommend to SPPMB for adjusting if necessary. b. Evaluation of socio-economic impacts of this project on the PAPs. c. Supervision of the implementation of RAP to achieve the objectives of the RAP in particular "to improve or at least maintain the incomes and living conditions of the PAP after the resettlement". d. Putting forward the amendments for the implementation of RAP so as to achieve the objectives of this RAP. e. Offering suggestions on how improve RAP programs f. Closely monitoring compensation activities and be prepared to give informed evaluation of complaints and grievances cases. g. Write working reports to be submitted to SPPMB and WB. PECC3 29/29 APPENDIXES APPENDIX 1 DRAWINGS I LAND USE WITHIN PROJECT SIT TAN D - PHUOC LONG 220KV TANSASSION L AND PR UOC LONG 22V UBSTATION / WIN r 1e DVNG DT IZU WC DV S faN DAY v TAN - Lo C /NG vA BiN A 0 > 1_____ 220KV TRANSMISSION LINE / 0110G DAY 220KV LIlllll Forest / Ring BCVv d ;- > ,0~~~~~~~~~~~~~~~~~~~~~1 _-, 5 O ~~~220KV SUBSTATION / TRAM 220KV | Agricultural land / 0at Nong Nghiep - - - National Boundary I Ranh Gidi Quo6c Gia -- Mangrove Forest / Rdng Ngap Man oc h a oyP* 6fs\Ro~~-Ht Province Boundary / Ranh Gidi Tlnh - . Contour Line / flhfdng Dong Mdc hU _ CGC (PuH - - Distric Boundary / Ranh Gidi Huyen Chne Kn S nh < 1 ~~~~~~~~~~~~~~~~~~~~~~~~~~~Traffic Road / Oifdng Giao ThOng Hr ltnh \ / (XutmiChinh g > inhtuy TanFb (ffi-'' \* w \ P ) t \ L^ngAi* Sttin h N < 1ttt/ k / TTmng ' / \W Ph 1. _ _ _ _ _ _A. I i i i i i i I I APPENDIX 2 SAMPLE OF SOCIO-ECONOMIC INVENTORY QUESTIONNAIRE FOR INVENTORY OF LOSSES Code: ............................... Name of respondent: .............................................................................................................................. Address: .............................................................................................................................. Street: .............................................................................................................................. Hamlet: .............................................................................................................................. Commune/Ward: .............................................................................................................................. District: .............................................................................................................................. Province: .............................................................................................................................. 1. INFORMATION OF HOUSEHOLD o* Age Ethnic Residential No Name in full i Education** registration (0 grUpstatus** Adult member 1 2 4 5 Under 17 years old Total members of family .. Total adult members .+ Total members under 17 years old ........ () Relationship to owner: 1. Husband/wife 2. Father/Mother 3. Children 4. Grandchild 5. Grandparent 6. Others (*) Education: 1. Analphabetic 2. Can read and write 3. Primary school 4. Secondary school 5. High school 6. University graduate 7. Intermediate school/Vocational school Ethnic minority households: Attending school Primary school Secondary school High school University Male Female Male Female Male Female Male Female (***) Residential registration status: 1. Pennanent residential registration 2. Temporary residential registration 3. Temporary absence 4. No residential registration 1.1. Occupation and average monthly income of family members Income per month No Name Occupation* Total Regular Other sources 1 2 3 4 Totalfamily income (*) Occupation 1. Wage-earner 7. Unstable occupation 2. Retirement 8. Other occupation 3. Handicraft 9. Housewife 4. Farmer 10. Schooling/training 5. Aquaculture/fishing 11. Unemployed 6. Business 12. Eligibility for especial assistance The family is in the income group: High 0 Above medium 0 Medium 0 Low El (In relation with average income ofprovince) 1.2 Average expenses of household (VND) Monthly expenses Total Other expenses Total * Food * Festivals * Electricity * Funerals/weddings * Water * Purchasing household appliance * Rent house * Repairs of house * Education * Repairs of motorbike/ motor boat * Transport Others * Clothes * Medical * Taxes, fees * Others 1.3 In case the household relocates a new place, number of members: 1. Be lost one's job El 2. Be decreased income D 3. Unknow El 1.4 Use of the house 1. Use for living E 2. Use for business E 3. Partly living and partly business 0 4. for rent E 5. Vacant D 6. Others El 1.5 Household comforts and appliances in possession 1. Toilets [1 2. Kitchen El 3. Water connection from network a Water Meter D 4. Electricity E Electricity Meter El 5. Motorbike El 6. Motor-boat E 7. Bicycle El 8. Television El 9. Fridge D 10. Washing-machine El 11. Electronic produce E 12. Telephone E 13. Others 1.6 Does the household have any disabled member? Yes El No El 1.7 If 'Yes' to 1.6, please ascertain the type of disability disabled level No Name Age Type of disability Male Female ~~~~Totally Partially Mild Male Female 1. Blind 2. Hearing impairs 3. Mentally retarded =___ _____________ ______ 4. Orthopaedically I ~~~~handicaped 5. Others 1.8 Does the household have any elderly member? 1. Yes 0 2. No [1 If "yes", please give details about age, physical condition, dependency status etc. 1.9 According to you, what are the special needs of the elderly and disable persons? (Example: medical care, mobility, food, social ...) 1.10 Health of household 1. Water disease (diarrhea, dysentery ...) 0 2. Respiration (bronchitis ... ) 0 3. Internal disease (cardiac, liver ...) [1 4. Skin disease 0 1.11 Religion 1. Buddhism 0 2. Catholicism 0 3. Others 0 2. INFORMATION ON AFFECTED ASSETS 2.1. Residential land Land for housing and land for business Unit: m2 Existing residential land Legal status Affected residential land X Land for housing Land for business i r ~~~~~With Without With Without > S ~~~~~ownership ownership ownership ownership I- 0 0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Related papers to residential land: ....... ................................................... ....... ................................................... ....... ................................................... * In case without ownership, please write specifically state of rent, state of temporary residence, . and monthly expense for rent. 2.2. Cultivated land Unit: m2 Legal status Items Existing area Affected area With Without Temporary use ownership ownership Paddy field Crops land Industrial trees land Garden Forest Pond Other Related papers to cultivated land: .................................................................................................................. .................................................................................................................. .................................................................................................................. .................................... * 2.3. Affected perennial trees and annual trees Affected perennial trees and fruit trees State of State of Type of trees Amount (tree) cutting Type of trees Amount (tree) development (year) (year) * Eucalyptus * Longan * China-tree * Durian * Bamboo * Pepper * Mango * Cashew * Orange * Coffee * Palm * Jack * Star apple * Plum * Coconut . * * Rambutan * Affected annual trees Amount State of cutting Amount ~State of Type of trees (tree) ( c utting Amoeu development (crop/year)~ ~ ~ ~ ~~(ro/yar * Paddy * Maize * Sugar-cane * Pineapple * Bean * Other * Cassava . .............. .... ............ 2.4 House Construction Existing house Affected house permit Type of Total T otal house Total Total house Typse ofOwned Encroached house construction house urfacire Yes No land land land r lan (M2) (2 plot (M2) plot(m2 ______ ~~~~~~~~~~~~~(MI) M ) 2 class 2 d class 3rd class 4th class Temporary Related papers to house: .................................................................................................................. .................................................................................................................. .................................................................................................................. ...................................... * * In case without ownership, please write specifically state of rent, state of temporary residence, ... and monthly expense for rent house. 2.5. Other structures Items Measurement Estimated price Related papers * Kitchen * Toilet * Cattle cages * Cistern * Well ; Yard * Electricity supply system Items Measurement Estimated price Related papers * Water supply system * Bridge, sewer * Entrance * Church/shrine * Graves * Others 3. INFORMATION ON COMPENSATION AND RESETTLEMENT 3.1 Willingness for resettlement 1. Yes E 2. No El If 'No', what are your suggestions? .................................................................................................................. .................................................................................................................. .................................................................................................................. .................................................................................................................. .................................................................................................................. ............................................. Apart from this house and this plot of residential land, does the household have any other house or other land in commune/district/province? 1. Yes [1 2. No E If 'Yes', please give details about address, area, type of house/land .................................................................................................................. .................................................................................................................. .................................................................................................................. ........................... 3.2 What form of compensation for land would you perfer? 1. Land for lost land 11 2. Cash for lost land C1 3.3 What form of compensation for house and other losses would you perfer? 1. Provide materials and labour for construction of house at self-selected location 2. Cash for structures for self-relocation 3. Independent house settled by the proj ect 4. Other options ............................. ............................................................................ ...................................................................................................... 3.4 What form of restoration for income would you prefer? 1. Financial assistance [ 2. Allocate a plot El 3. Assistance in employment seeking a 4. Assistance for training Cl 5. Training for appropriate new skill a 6. Assistance in credit for restoration of business E 7. Other proposals ...................................................................................................... 3.5 What form of resettlement would you prefer? (Please record in order ofpreference: 1, 2, 3... in the blank space) 1. Land is compensated at the replacement cost, trees/crops are compensated at the market price. E 2. Resettle on the remaining of your land C1 3. Adequate technical infrastructures (road, electricity supply system, water supply system, ...) at new site El 4. Adequate social infrastructure (school, market, ...) at new site C l 5. Easy to open business at new site D 6. Good community at new site O 7. Good environment quality at new site El 8. Got a house in resettlement area without incurring debt El 9. Training and employment El 10. Additional suggestions, if any .... ... ... ... ... .... ... ... ... ... ... ....................................................... Date . Month ... Year. Interviewer (Sign and write one 'sfull name) APPENDIX 3 RESULT OF SOCIO - ECONOMIC INVENTORY Table 1: INFORMATION OF HOUSEHOLD No of Residential Income per Mouth in Education registration Occupation month Impacted in household status case of No Head of 1des 00Average relocated No household Adress > c 1- expenses 1,2 * ~~~~~~~ a.E o.E'~~~~~~ Opio ,2o -41 -4 4-4- I. Thanh Luong commune, Binh Long district, Binh Phuoc province 1 Buii Van Phuc Thanh Tuan hamlet, T.Luong comm. 4 4 3 1 4 3,000,000 1,000,000 4,750,000 1 2 Nguyen Van Nang Thanh Tuan hamlet, T.Luong comm. 6 1 4 1 1,3,4 3,500,000 600,000 3,750,000 1 3 Pham Van Si Thanh Tuan hamlet, T.Luong comm. 2 1 4 2 4 2,100,000 300,000 1,600,000 3 4 Pham Van Phii Thanh Tuan hamlet, T.Luong comm. 2 2 4 1 1,4 1,900,000 500,000 1,860,000 2 5 Nguyen Van DAn Thanh Tuan hamlet, T.Luong comm. 4 1 4 1 4 5,000,000 0o 4,620,000 3 TABLE 2: HOUSEHOLD COMFORTS AND APPLIANCES IN POSSESSION, HEALTHY STATUS Disable Use of the house Comforts and persons Elderly Health of Religion No Head of household appliances in (No (0); If member household (Option from 1 (Option form 1 to possession "Yes", (Yes (1), No . t 4 5) (Option from 1 to 13) option form (0)) (Option from1 to o ) I. Thanh Luong commune, Binh Long district, Binh Phuoc province I Bui VAn Phuc | 1 1,3,4 0 0 0 0 2 | Nguyen Van Nang | 1 1,3,4 0 1 0 0 3 Pham VAn Si 1 1,4 0 0 0 0 4 | Pham VAn Phii 1 1,3,4 1 1 0 0 4 A 5 NguyenVanDin 1 1,3,4 0 1 0 0 TABLE 3: AFFECTED LAND _ Existing Affected Ownership residential land residential land Existing cultivated land (mi2) Affected cultivated land (m 2) status residntia land_ _residential ___land_ (Yes, No) No OWNER'S NAME , z ., O c - V 2 Nguyen Va Nang 400 6 400 C6 0 0 0 13000 0 0 0 500 0C Pham~~~~~~~~l MaS 40 Q.)0 C 0 100 0 0 0 0 60 0C 4 ~ ~ ~ C Pha VaPh 400~ C6~ 0, 0~ 0 20 0 0 0 0 0C 14 0 0 d 0.4 U ~~~~~~~~~~P-s u I. Thanh Luong commune, Binh Long district, Binh Phuoc province 1 BWi Vgn Ph?ic 400 C6 300 C6 25000 0 0 9000 0 3500 0 0 0 0 4500 2000 C6 2 Nguy6n VAnNdng 400 C6 400 C6 0 0 0 13000 0 0 0 0 0 0 5500 0 C6 3 PhamnVdn SY 400 C6 400 C6 0 0 0 13000 0 0 0 0 0 0 4600 0 C6 4 Pham V5nPhii 400 C6 0 0 10 0 0 7200 10 10 0 0 0 10 80 0 C6 5 Nguyen Van Dan 400 C6 400 0 0 0 0 12500 0 0 0 0 0 0 2200 0 C6 TABLE 4: AFFECTED HOUSE Class Construction Existing house Affected house of permit house No Owner (1, 2, Encroached Total house house Total house Total house (1, 2, Owned land E T h construction surface T h construction 3, 4, (Yes, No) (M) land land plot area land plot surface area Temp) kn 2 i2 2 i2 i2 1. Thanh Luong commune, Binh Long district, Binh Phuoc province I~~~~~~~~~~~~~~~~~~~~~~~ I BuiiVanPhuic 4 C6 400 145 0 84 0 2 Nguyen Van Nang 4 kh6ng 400 90 0 90 0 3 Pham VAn Si Tam kh6ng 400 35 0 35 0 4 Pham Van Phu Tam kh6ng 400 45 0 0 0 5 Nguyen Van Dan 3 kh6ng 400 90 0 90 0 TABLE 5: HOUSEHOLD IMPACTED ON CROPS Paddy Cassava Manioc Maize Sugar-cane Bean Others No NAME 3 o '4 4 _ E I. Thanh Luong commune, Binh Long district, Binh Phuoc province 1 BMEiVanPhdc 1000 1 0 0 0 0 0 0 0 0 0 0 0 0 2 Nguyen Van Nang 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 Pham VanSI 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 Pham VAnPhu 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 NguyenVanDan O 0 0 0 O 0 0 0 0 0 0 0 0 0 Cn -r W N) z -~~ 0 z z c ~< W 0 3 N n z N n mont(re) tz o o 0 0 0 w Amount (tree) P o o 0 0 0 S. State of cutting C _ - - - (year) CD .I O N' O Amnount (tree) R 01 X 01 m X State of cutting Q _ _ (year) _ m: o o 0 0 0' ~ Amount (tree) _ n State of cutting q C o 0 0 0 0 (year) z CD o) CD ^ o Amount (tree) (*) 0 State of cutting Z (year) - 0 0 O O Amount (tree) m 04 0 C4 Cn W State of cutting CD (year) c o o o Co0 Amount (tree) m m State of cutting (year) z D 0 0 0 0 Amount (tree) t- State of cutting u m (year) > o cD C 0 0 Amount (tree) t o o o , o oState of cutting m (year) CD ~~~~~~Amount (tree) tT ~~. ~~State of cutting z z (year) 0 ~~~~~~Amount (tree) " CD 0D 0D 0 0 State of cuttin 9 (year) APPENDIX 4 COMPENSATION UNIT COST BINH PHUIOC PEOPLE'S COMMITTEE SOCIAL REPUBLIC OF VIETNAM Independence - Freedom - Happiness No. 20/2003/QD-UB Binh Phtr&c, March 18'h 2003 DECISION OF BINH PHUfOC PEOPLE'S COMMITTEE On unit price of compensation for land, house, structure construction and crops within Binh Phu6c territory BINH PHIU(IC PEOPLE'S COMMITTEE - Base on the legislation of People's Council and People's Committee organization (modified) which was approved by the ninth National Assembly on June 2 It, 1994 - Base on the legislation of Land dated July 14th, 1993 and the Decree No. 04/2000/ND-CP dated February 11th on the modified legislation and adding some clauses of land legislation - Base on the Decree No. 203/HDBT dated December 21'h 1982 of Ministerial Council (Government) on regulations for road protection. - Base on the Decree No. 87/CP dated August 17th, 1994 of the Government on Land unit prices. - Base on the Decree No. 22/1998/ND-CP dated April 24th,1998 of the Government on land compensation that serve for the Nation benefit and national defence and security - Base on the Decree No. 54/1999/ND-CP dated July 8th, 1999 of the Government on Protection of Safety for high voltage networks - Base on the Decree No.172/1999/ND-CP dated December 7th, 1999 of the Government on implementation details of the Ordinance of protection road traffic structures. - Base on the Decree No.38/2000/ND-CP dated August 23th, 2000 of the Government on money of land use - Base on the Circular No.145/1998/TT-BTC dated November 4th 1998 of Ministry of Finance on implementation instruction of the Decree No.22/1998/ND-CP - Base on the Circular No.106/2002/TTLT/BTC-BCN dated November 22th, 2002 of the Ministry of Finance and the Ministry of Industry on compensation instruction, assistance for construction of high voltage networks - Base on the Decision No.51/QD-UB dated Feburary 11th, 1991 of Song Be People's Committee on the regulations for corridor of road safety on Song Be Province; the Decision No.416/QD-UB dated November 6th 1991 of Song Be People's Committee (former) on the changes of regulations for corridor of road safety on Section 743 and 741; the Decision No.860/QD-UB dated July 16th, 1993 on the regulations of chli s6o lo gi6i cac trnc durong in DOng Xoai town, DOng PhM district - Base on the Decision No.25/1998/QD-UB dated March 10th, 1998 of Provincial People's Committee on the regulations for road safety; The Decsion No.1 16/1998/QD-UB dated September 29th 1998 of the Provincial People's Committee on adjusting and adding for the regulations for road safety according to the decision No.25/1998/QD-UB dated March 10th, 1998 of the Provincial People's Committee - Base on the Decision No.52/1999/QD-UB dated March 25'h 1999 of the Provincial People's Committee on the promulgation of process for compensation alterations as the Government withdraw land according to the Decree No.22/1998/ND-CP - Base on the Decision No.35/2002/QD-UB dated July 26h 2002 of the Provincial People's Committee on the promulgation of average price unit for civil and industry project on Binh Phuoc Province - Base on the Decision No.37/2002/QD-UB dated July 26th 2002 of the Provincial People's Committee on the promulgation of Methods to define construction areas, floor areas, areas of used land, level of houses, residual for affected houses. - According to the Proposal of Department of Finance - Price at the Statement No.49/TCVG dated January 21 th, 2003 DECIDE Clause 1: Enclose with this Decision the Unit price of compensation for land and houses, structure and crops on province to base on: - Caculating proverty value as land transfer - Compensation for loss of land that serve for the nation benefit and national defence and security according to the Dcree to No.22/1998/ND-CP dated April 24th, 1998 of the Government Clause 2: Base on the activities of each project, Compensation Council depend on market price units for each the period of time are the cost of land tranfer, the cost of land invesment (including house, structures, trees) and the added polycies at current regulations to form compensation plan for each project. This compensation plans will be appraised by Department of Finance - Price, approved by Provincial People's Committee which demonstrate to implement the activities of compensation and clearance for the project. - For project's capital by the budget of district and town which follows the approved class of compensation at Decision No.662/QD-UB dated April 23th 2002 of Provincial People's Committee, Compensation Council of District and Town to report People's Committee of District and Town approve the cost of compensation which follows agreed price unit by Provincial People's Committee. Department of Finance - Price will receive 01 copy to follow after aprroved cost of compensation. - For project implemented inventory, compensation by the separated price unit and policy will not apply this Decision - For projects which still have not the policy and the compensation plan and have not inventory status will apply this Decision Clause 3: This Decision will replace Decision No.13/1999/QD-UB dated January 29th 1999 and Decision No3O/2001/QD-UB dated April 26th 2001 of Provicial People's Committee. The regulations of Decision No.52/1999/QD-UB dated March 25th 1999 of Provicial People's Committee which conflict to this Decision will detroyed Clause 4: Base on this Decision will be conducted this Decision on April 015 2003 by: The Chief of the People's Council Secretariat and the Chief of the Provincial People's Committee Secretariat, Director of Department of Finance and Price, Director of Land Survey, Director of Department of Construction, Director of Department of Argiculture and Rural Development, Director of Department of Transportation, Director of Department of Justice, Provicial State treasury, Director of ax Bureau, People's Committee of district and town and Leaders of related units CLIc phtcng an gi Li boi tIILdng- PhLt d!&ic guti cho S6 Tl chinnh - V2It Ngia tl-ham clinh, trinh UBND t'nh phe (Iuyevl lm cctn Cif de" thuLc hien c6ng tLic boi [hLfdn- giai ph6mng nit bang cho dL rn Cd1. Do'i vdi cac dtr an c6 nLguon voin do ngan sach huyen, thi xI CLu tLr theo plhan cap phe duyet, boi thlfdng tai Quyet dinh so 62/QE)-UB ngay 23/4/2002 cu'a UBND tinh, Hoi dong boi thu'dng huyen, thi xa trinlh UBND huyen, thi xa phe duyet chi phi boui thiidng theo chii7i trtrong chinh .saich giai diroc UBND tlnh chap thuan. Sau khi phe duyet ket qua th-am dinh, g,i' cho Sa Tai chinh- Vat giai 01 ban de^ theo doi. 3D6i vdi caic dii an cla trien khai thu'c hien kie'm ke, boi chiing co chinh sadch, ddn gia boi thtf&ng rierig kh6ng 5p dung Quyet dinlh nay. DOi vdi nhfung dLr an chtra c6 chfnh sach va phtfong an gia boi thLOng, chu'a thu'c hien trien khai kiem ke hien trang thi ap dung thutc hie.n theo *Quyet dinh nay. Di4u 3: Quyet dinh nay thay the Quyet dinh so' 1 3/i 999/QD-UB ng?iy 29/0i/1999 va. Quyet dinh .sc 30/2()011QE)-UB ng,ay 26/4/2001 cua UBND - tinh. Cac n6i dung quy dinh tai Quyet dinh so 52/1999/QE)-UB ngiYy ?5,/3!I 999 cua UB3ND ti'nh trai v6'i quy dinh tai Quyet dinn tnaiy dii.c bal hi. Die'u 4: Cac 6ng (ba) Chanh Vdn phonc, UBND tinh, Giam d'c Si Tai cninh - Vat gia, Si E)ia chinh, Sci Xay diing, Sci Nong nghiep va Phatr tri~n nina thon, SG' Giao thing Van tai, Si TLr phap, Kho bac Nsha nu'CC rinh, Cuc Thuc., BND cac huyen, thi xai va Thu trpidng cac nbanh cc Lim ciualh chiu traich rnhiemn thi hainh Quyet dith nAiy kc nir ogciy 01/4/200(3!./ TMV. UY BAN NHAN D)AN TTiW N'ich nhanh Q t Cfn yTICH - TTTJ TT 77 VD ?,j'*VD - CT PCT. ID i ' !z - ' _-_- K~~~~~~~~~~~~.. >,,Ps _,_________________ _ j. -'*_ C I 'FTI NN H3 I N P H 1-fJi C )$^c LIap - T11 do - Ha nh p[litC QUY DINH Ve chfinh sach boi thMdng da't va don gia boi thWmng nhA cia, vat kie'n truc, hoa mAu tren dia ban tinh (Ban hanh kel thleo Quyit dintlk so ^- /2003/JQD- UB ngeiy /1 / 0 ? /2003 cia UBND tZnh) CHIJONG I CHINH SACH BOI THU'dNG Dieu 1: DO'i tu'Ang va pham vi ap dung: 1. DEi t`clng: LA tat ca' cac to^ chf!c, ho gia dinh, ca nhan tr'c tiep quLan Iy s' dung dat, chu s6 h'uu cac tai san c6 tren dlt, nay NhA ntrdc thu hoi dat ce quy hoach si dung dat theo quyet dinh cua UBND t7nh hoac NhA ntc kh6ng thu hoi dat d do"i vOi dat nam trong hanh lang bao ve an toTa cCia d-rOng day dien cao ap ma bi han che' khha ning s'r dlngn 2. Pham vi boi thutdng thiit hai: Pham vi boi thLkng thiet hai bao gom: Boi thirdng thiet hai ve dat (dat dlu dieu kien quy dinh boi thtdfng; doi vdi dit nam trong hanh lang bao ve an toan cu'a du'dng day dien cao ap chi' boi thLidng phan datd d6n dae xay durn, tram dit n, tru co,t va day tie'p dt ) vA tAi san tren dt (dloi v0i nhA, c6ng trinh xay dlng , cay trong tren dat d' dieu kie n quy dinh b-i thutdng), tro cap ddi song, di chuyen, di ddi va di chuyen dung ke hoach theo quy dinh. 3. Pham vi khong boi thOdng thiet hai: - Da't, nhA cCa, vat kien truc, ciy trong tren d't do sang nhucng, lan chiem xay du'ng trdi phep phat sinh sau thdi direm quy hoach chung i du 'Lo'c cap c6 tham quyen phe duvet (hoac thngr ba,o b7ang van ban cua caD c6 th.'rM quyen v' quy hoach). - Dr kh6nL du' dieu kien boi )hI'dn t h Q dm ban o K nhmC i i ti ,an h n hLu rtren /d t nay1). t1-0 llZ CLtV CU th+ nhliLf su L: - DL^t s2 dung tO' ngaiy v20/1/1982 trd ve trifdc: H-'inh iana bao ve du'Ong bo i& c tinh tO' tim dLr6na I0 L IO rnoi ben. - DE't sC dung tO' ngiay 21/12/1982 den ngiy 10/2/1991: FP{nh lang bao ve du'dng bo d roc xac dinh theo Nghi dinh so' 203/HDBT n,gOy 21/12/1982 cua Ho,i dong B6 trut8ng (nay 1i Chfnh phu). - DEt su dung trt ngay 11/2/1991 den ng0y 9/3/1998: H-Hanh lang bao ve cdLrfng bo ducoc xac dinh theo cic Quyet dinh sau: Quyet dinh so' 51/QD-UB ng0y 11/2/1991 cua UBND tinh S6ng'B6 (cu) ve viec quy dinh hanh lang bao ve dWring b6 tren dia ban tinh Song Be. + Quy&t dinh so 416/QE)-UB ngay 6/11/1991 cuia UBND tinh S6ng Be (cu) ve viec thay doi qui dinh hanh lang bao ve dordng bo tren DT 743 va DT 741. + Quye't dinh so' 860/QED-UB ngay 16/7/1993 cua UBND tinh S6ng Be (cu) ve viec qui dinh chi so' lo gioi cac truc dci8ng trong thi tran Do`n- Xoai hLiyen Do6ng Phil (n6i o thi xa E)Dng Xoai, cldung QL14 va durdng EDT741). - DEt siY dung tO' ng0y 10/3/1998 de'n nay: Hanh lang bao ve dIr.ng b6 cltuoc xac dinh theo cac Quyet dinh sau: - Quvyt dinhi so 25/199S/QD-UTB ngay 10/033/1998 (ua UBND iir h v+ vitec 'o;an -anh citr ci1nrih oa'te vir , a`'kjn- nO + Quvyt dinh so I 116/1998/QD-UB ngay 29/9/1998 LI a UBNJD Linh ve vi.e dieu chInh, bo sung quy dinh bao ve, ddng bo, . - E'io vdi khu vuLc n6i 6 thi tran, thi xa tuy theo th('i diem ph6 duyet quy hoach do'i vdi thi tran, thi xa hanh lang bao ve dirdng bo cdtfc tinh bang chI gidi xay dun,ng tai thdi dierm quy hoach 1 gi-i theo quyet dinh phe duyet quy hoach. Rieng doi vdi khu vuc n,i 6 thi xa D6ng Xoai hanh lang bao ve dtidng b6 dcdc tinh dclfoc tinh bang chi gidi xay dilng tai thdi diem quy hoach 1l gidi theo cac Quyet dinh so' 860/QD-UB ngay 16/7/1993 cu-a UBND tinh S6ng Be (cu) ve vie,c qui dinh chi so' 16 gidi cac truc du'dng trong thi tran Do-ng Xoai huyen D6)ng PhO, Quyet dinh s6' 1061/QED-UB ngay 3/7/1.997 cua UBND tinh ve viec ph6 duyet quy hoach chung xdy du,rng thi xa Dong Xoai, Quyet dinh so' 3055/QD-UB ngay 5/12/2000 cua UBND tinh ve viec ban hanh quv dinh ve chi gici du'dng do, chi -idi xay dun l tam nlliln glao lo, bo" tri he tho'ng ha tang k7 rhut cua he thong JuLngd n6i 6 rhi -K. E)ong, Xoai ti7nh B3inh P hRbc. CN>QSDED). 1.1.3. Tru'dng hop d.t chula c6 ai3lv chl'ng nhan quvun Li v dung li nhuna aud dieu kien bo'i thLudng tai muc 2. l khoan 2 dieu 3 qui dMnh nr,v i nha va c6ng trinh phu phuc vu sinh hoat thi di?n tich dct th6o cut duOc xSc dinh la dien tich dat c6 nha 6, bep, san, gieng nu'dc, nha tam, nha ve sinh chuo-ng trai chan nu6i -la suc, ga cam, ndi de thiuc 1n ala s'ic, -ia cam, nol .e7 chat do't, noi de^ 6 t6 nhiLng kh6ng vuijt qua 300 m)/ho do6i vdi dat do thi hoac 400 m2/hM doi vdi dclt khu dan ctu n6ng th6n. Phan dien tich dat con lai vutdt han miic dutdc tinh Ia dat n6ng nghiep, dct lam nghiep (tuy theo muc dich siY dung ). Trltrng hop nAy chu suf dung dat phai c6 du' 02 dieu kien .sau: a. SiIt dung dclt lien tuc, o6n dinh kh6ng tranh cha'p tif tructc ngay 15/10/1993 de'n ngAy kiem ke hien trang. b. C6 nhA 6 dtfoc xay du'ng tit trLf6'c ngay 15/10/1993, khong bi lap bien ban vi pham hAnh chinh trong xay d'ng. - 1.1.4. Tru'dng hOp dct chu'a c6 giay chung nhan quyen s.? dung dat, nhutng da hoan thAnh thu tuc xin siY dunng d^t nhtu durtc cp c6 tham quiyen cho phep chuyen muc dich sff dung da't tO' d^t c6 muc dich sir dung cii dht n6iig- 1arn nghiep thAinh dat 6 v3. 1l hoLn thAnh viec d6ng Lu chuy'en mLuc dich 5,1 dung, Iat. Dien tIfch boi thLreng cfft 6t dltfcu xaic dinh ic d.in tich dAirt thui'c tr' dti d6n- thue' chuv e'n muc di 'h sft dung dlat niht.fn,, khr.n crd 3r 0 m doi vdi dirt do) thi, Thoanc qua 400 mr2 d0oi v\i dat k,hu d an cut nrng thonr 1 1. 5. Trutdng hop cdt dd c6 giay chin,g nhan quyen su dung d1^t nhufng trong qua trinh do dac giai thu'a c6 su,' chenh l, ch ve dien tich dcrt so v6i gia'y 'C~~~~~~~~~~I chd'ng nrhn quyen sut ding dcat th' phan dien tich dat thuic te chenh k ch so. vdi gia'y chung nhan quyen sL' dung dclt drtdc xac di,nh nhu' sau a. TrLrdng'hJp dien tich cdat dlo dac giai thua In hon die,n tich dart Thi tren giaiy churng nhan quyen sut dung dclt dutoc xut ly nhut sau: - Neu giay chunng nhan quyen sOt dung dat IA dat tho cut, thi dien tich dat tho cut dtrcc tinh theo giay CNQSDD nhi'ng kh6ng qua 400 mi. Phan dien tich cdlt vutr1t so vdi giady CNQSDD thi tdufoc tinh la dat n6ng nghiep, lam nghiep (tuy theo muc dich sO dung dcat) - >eu giayv CNQSDD c6 ca dart tho cuf va dat n6ng, lam nghiep thi dien tich cdit tho cut (hoac cdit n6na, lam nghiep) dutoc xdc dinh nhu sau: + TrLfdng hop giay CNQSDD ghi ro di-n tich dirt tho cLu lh die, n :ch di't tho6 cut dutoc xac dinh theo Jdi&^m 1. 1. 1. muc 1. 1 khoa: n I dieu 3 quv *Jm h nAv. PhAin ehen ;ich aLit con ta- boi Ihutdn2 theo i," lit mnrJ ng t ep. >m nchie p (`Cy then) mruc dch JU Jung cOne to.i-dt' chi t10i'm 'ui N\27) S DDE '.1. Dtab tilt ,hui d N' c xemn xot h)i ti u'o)n' DEar thu hoi d&c xem xet boi rhu'dn- la M: K mI tron, -dc d-iK kLin sau cliy: 2.1.1. CL6 C iay CNQSDD theo quy dinh cua phap luat ve dMft tai. 2.1.2. C6 Quyet dinh giao Mit cua co quan .Nha nu'dc co tha"m quyen theo quy clinh cua phap luat ve dt dai. 2.1.3. C6 giCy td chuyen nhtfqng quyen sif dung dct (QSD dMt) theo quy clinh cu]a phap luat ve dat dai. 2.1.4. C6 giay td thanh 1I, h6a gia, mnua nha thu6c sa h2uu Nha nLr'c cuing vdi xac nhan QSD dat theo dung quy dinh cuia phap Luat, hoac quyet dinh giao nha 6, cap nhA a agan lien vdidt 6 thu6c sa h'u Nha nukic c'u'a ccr quan Nha ntrdc c6 tham quyen. 2.1.5. Ba.n an c6 hieu lItfc thi hanh cua Toa an nhan dan ve viec Liai quyet tranh cha`p nh~ a gan lien vdi QSD dt hoac Quyet dinh ctlia cd quan co tha'm quyen ve giai quy6t tranh chap datdai i d c6 hieu lLc php lIluit. 2.1.6. Tr L,.ng hTp khUn.g c6 cac gif'y tW qul dinh tai 'iam 2 1., 2.1.2, 2.1i ,, 72j 4 vd .1 5 ,nuc 9. I Rlobn 2 dP~ iyt lc thil il'0f bi thlu .'6i M5it 4i,<,c ~ u ~ai co ca o'" - u -i m 1'b h '6 1Li t c t-?-t '-7 .'.1" .ltih L'i ulLi Ci C( ItcC ,',a jeZ hts ,t'L. Wim.i't d urqc f [thu L iri ,Ol i !a d. Mi s lt dun" i 1n inlh trri.dc nii L5v 1 5/10f93 'ng-iy Lu,at datt dai ICa *fi c6 hiu .lrc thi hanh) thuoc mot trong cac trnr8ng hop sau: a. Dat Md slr dung on dinh tru'dc ngay 08/1/1988 (ngay cong bo Ludt dt dai) ducLjc UBND xa, phu'dng, thi tran xac nhan (tai thdi die'm scf dung dat khong vi pham quy hoach du'clc cap c6 tham quyen phe duyet va da c6ng bo, hoac kh6ng vi pham hanh lang bao ve c6ng trinh, khong a1n chiem Mit trai phep). b. Du'oc co quan NhU nu`dc c6 tha'm quyen giao dat suf du-nc trong qua trinh thu,c hie,n chinh sach Mit dai cu'a Nha nu.Ac VNDCCH, Chlinh pUi CMLTCHMNVN va Nha nOrdc CHXHCNVN ma ng'dLi d'toc giao dt v n tiep tuc sit9 dung Mtdt tMi d&en ngay bi thu hoi. c. C6 giay td hop Ie do cd quan c6 tham quyen thuoc chl eM ec c`ap cho ngfOi si.t dung da (bao gaom: ba.nr khoKn clien tho ho.c trich luc, trich sao, bairn dO dien [hS, ban d phan chiet thi'a, chfinMg Lhi dcan rnMi tit :hurc, dan2 tich sanc tCIn tai Ph6ng truttng khe, Tv dien "a, >ThaTrh cb, rna marc;i Ml v6 n silt dun on dinh l,e1i tue khnu ct-ran1h C( `.lP tkhic CItcC ctC Gei e`Gi > Mi bi thLi ho nIC I=,hTlh '/vU tii cl inh cho t'hal vIULC. 2.2. ca t thu h6i kh6ng dli(uc xem xet boi thL6;ng: D&t thu hoi khong cltfc xen xYt boi thtOng la dt thuLo6c mot Eronc cac tru,dng hop sau: - Da't kh6ng c6 mot trong cac diVu kien quy dinh de b0i thu'tng tai muc 2.1 khoan 2 dieu 3 thi kh6ng duoc b6i thurdng. - Dt s!( dung tr ng;,y 15/10/1993 tr6 ve sau kh6ng c6 giay hop 1l, hop phip thi kh6ng dltoc boi thu'dng (kc ca cac trutdng hop dtrc UBND x, phu'6ng, thi tran xa c nhan). - Da't nam trong, hanh lang bao ve dOng b6 theo qui dinh ci7'a phap luat ve dat dai thi khong dtOfc b0i thtf(ng khl bi thu hoi dcfft. - Dt dM du'oc Nha nLrdc quy hoach dcloc ccip c6 thtam quyen phe duyet va dq cnong bo', neu dan tur a^n chie m trai ph6p thi kh6ng dtroc boi thufntM khi bi thu hoi dcat. - E)at cti'a cclc doanh nghiep, c6ng ty dcl du'Oc co quan co thL'irn quyen giao dat nhtfiig khong nop tien sii dung dL^ft hoac in6p tidn .CS dLun rit bring ngan saich Nhat nucdc thi khngn- boi .hu'(ang hiaet hai ve lt. C-h; iroc boi th16dng, thiet hai chi pli dii diau ttu vTcl dt neu tien t cl kh6ng thuoc ng2rn sach N.hA nufdc. - DEt co Quyet dinh cho thue, dat tam giao sit dung, dXt dau thau kh6ng du'c b6i thtnang thiet hai ve- dt nhu'ng dicfc boi thtrdng, chi phi dc dau ttr vao dt cu'a ngurdi bi thu hoi drt (neu tien d6 kh6ng thuoc ngan sach Nha nu'dc). - Trong trrdng hop can thiet xet thay can ho tro thi UBND tlnnh se xem xet quyet clinh d0i vdi tEfng trLdng hop cu the . 3.M "Ic boi thO:ng thiet hai: 3. 1. E)oi vdi dat ndna nghVtp, lIm nghi&p, dat co mat nudc nu6i trong thuv -an: Boi thuldn, I OC)-/c iOn o-ia. 3.2. Di v,'di 'lit tho Cii: .3C i'c boi :h[tukLn chc Ll Jin> noLt .,au: n.2. . Boi rPuonn c V ,; i Jlfl '`l iOng hi1c p 2QO 'ca u-aiy ti LVI' i i h t Li c ti rDl -.1 _.i . 2a.1 .i. -i.t, F d l' . 2.9 Ll . k:ho, 2r i, |' ( J t 1 9 i Ll 3 . D(U^SN GIA PO O H THUCNG ' I4 1 iE ' 'i ' Die u 4 D In giS boi thiMng da't Cdn cii vdao th(si diem trien khai thu-c hien chL. an, clon gia boi thS;ng, clat c6 Quy6t dinh rieng cho tTfnhg dut an. Dieu 5: Do;n gia boi thut8nc thiet hai nha, vat kien truc, c8ng trinh tren dat 1/ Don gid b6i thuifna nha 8, vit kien thuc, c6ng trinh- phu dLu'oc xc clinh theo ket cau, vat lieu su]r dung, cU the: 1.1. Nha cap II: 1.1.1. Nha cap II A: - Qui m6: 1 tret I lau tr6 len, c6 ph6ng sinh hoat chung 8 tiung tang, co ph6nc, ve sinh chung vdi trang thiet bi cao ca'p 8 tiu'ng tang va c6 tiu 01 ph6ng ve sinh ring, trd Ien c7utdc bo tri 8 m6t hoac cdc phong ngu:. Dien thcUh mat tien chie'm Imn hon hoac bang 50% dien tich tu'eing bao che, c6 h tho'ng die chie'u sng, ii hoat va ca'p thoct ni-Mc. K6t c'du: "M6ng, c6t, kIdi ng T,h t6ng cot tLnep (Bt ci-u 1- an LiL BTCT, tudc'ng xay gach; mcii BTCT tren c6 dan chcI nhiet ihoad 1hD ingi, tole de cdch nhiet, cho"ng tha'm va tao dang ki'n trdSc; nen va san I;t gach men cao cap; tuong c7A, cday sAn sOn nudc; mat tien op cla granit cao cap hoac o"p cdc loai tuocng cudtong; c ta kinh khung nh6m, sat hoac g6 nhnm 1; Ian can, cau thang bang Inox (hoac go c6 gio tri tJ. ng I-u)Dng). - Don gia: 2.000.000 d6ong/m2 xay dtmng. 1.1.2. NhA c II B: - Qui m6: 1 tret I k^u tr8 len, c6 phong sinh hoat chungr & tiifng tang va c6 phong ve sinh chung v6i trang thie't bic cao ca'p 8 tiltng tang. Dien tich mat tien chim lAin hon hoac bang 50% dien tich ttf6ng- bao che, co he tho'ng dien chie'u sAng, sinh hoat, va ca'p thoadt nLt'dc. - Ket cau: M6ng, cat, khung BTCT chiu VLne; san lau BTCT; ntcdng xlv gach; mdi BTCT trcn cod dan cach nhiet hoadc l na-oi. tole di cach nhiet, chona tham vAa .a dang kin n truc; nen vJ. n IS, gach men ao cAp; -'dnl ii. dLA, , an son mLtLc: malt tir n0) % cach men c-a c c; cia ink n n.rp s,t hoac zi nahim ILan can. --all :hn bn Inc? CC ()CL?C , i,a [T _ Cit r:n I l n c,T},iSpl I. 2. IN h capr III A: - Qui m6: 1 tret I lau tro 1'n, c6 phbng sinh hoat chun, tCrnd Ving,c6 he thong c iin chie'u sang, sinh hoat va cap thoat nu'dc. - Ket cau: M6na, cot, khunog BTCT chiu IuLc; sAn Iau BTCT; w6dng xaLy gach; mai BTCT; nen va san lat gCach men; tLOng dA, day san sdn nmf&c; mrn tien op gach men; cua kinh khung nh6m, sa-t hoac go; Ian can, cau thaong bancg Inox (hoAc go co gia tri tniong clurong). - Don gia: 1.500.000 dong/m2 xay dung. 1.2.2. NhA cap III B: - Qui m6 : I tret I lau trc len, c6 he thong dien chie'u sangr, sinh hoat va ca'p thoat ntr6c. - Ket cau: M6ng, cot, khung BTCT chiu luc; .san lau BTCT; tidncg xay gach; mai lcp ng6i hoac tole; nen vA sAn Iat gach men; trung da, clAy sAn son ntrdc; mat tien op gach men; cura kiinh khung nh6m, sat hoac go; Ian can, cau thang baing Inox hoac go c6 gia tii tuoncng diong; tran tarm nhua hoac van ep. - DOn gia: 1.300.000 dong/m' xA'y d'flng. 1.2.3. Nha ca^D III C: - Qui m6: 1 tret 1 a^u trc len, c6 he thong dien chieu sang, sinh hoat va cap thoat n1rLc. - Ket cau: M6ng, c6t, khnng BTCT chiu lu'c; san in BTCT; rong xay gach; mai lop tole hoac fibro xi mAng; nen va san tat gach men; ttfdng, dci, dAy san qu6t v6i; chra kinh khung sat hoac g6; lan can, cau thang, ban(g Inox hoac sro c6 gia' tri tLcrn' dtoncg; tran cdc loai. - Don -ia: 1.100.000 dong/m2 xay dnn.. 1.3. NhA cap IV 1.3.1. NhA ca'p IVA - Qui m6: Loai [ret hoac c6 dLc a 0 - Ke cani: NIo6ig, cot BTCT; xudOng gach; m,ai ng6i hoac tole; mat t-in citc se no; nen 2ach bdna hoac Gnch men: tEran cac loai; nrbinL, cy se no scn n.rci; 4p lit mat tmn hio c to cis) Lh c inh khu n, ( ho.c L {-c,6 ni i -I t n t dN7 . - - -o ~&: t E riTi c ln(ng 1 - ~~~~~-m r srj ~~~~~~~~~~t4'~~~~~~~( (-I---)fl ~~~~~~~~~~~~~~ V 1~~~~ - 1 1 .e (J' ii "ch -;' LI I LI ~ ~ ~ u LI III Lcd v. can nha dlfoc x,ic dnMh tlheo Qu&'t dinh so' 377/2002'/QD-UB n-civ 26/7/2002 cua UBND tinh ve viec batn hanh quy dinh ve phurong phap xac dinh dien tich xay du'ng, dien tich san, dien tich scr dung; cap nha; gia tri c6n lai ca can nha. - Gia tri con lai do^i vdi nha tron, muc 1. 1, rnuc 1.2 du'oc tinh theo gi.a tri c6n lai th rc te` nhtrng kh6ng thap hon 60%. Do"i vdi nha muc 1.3, 1.4 va 1.5 dtuic tinh bang 100%. - Cac loai nha trong muc 1.1 neu nen dat thi trtr 150.000 dc/m Caic loai nha trong muc 1.2 va diem 1.3.1, 1.3.2 muc 1.3 d tren neu nen dat thi trU 90.000 dong/m' suf dung do'i vdi nen gach men va 70.000 dong/nm stf dung doi vdi nen gach bong. Cac loai nha trong diem 1.3.3 muc 1.3, muc 1.4 va muc 1.5 6 tren ne'u nen dat thi tr f 40.000 d6ng/m2 sLf dung. - Chenh lech gilfa nen gach men via nen gach xi mrng (hoac nen xi mang, gach tau) Ia 30.000 do6ng/m . - Cac loai nha tronc, diem 1.2.2, 1.2.3 muc 1.2 va muc 1.3 f tren neu kh6ng c6 la phong thi trOr 50.000 dong/m2 s.r dung - Tru'dng hop chieu cao tu'dng tinlh tO' mat nen (san) de'n day da thha'p nhat dufdi 2,7 met hoac nha c6 m6ng, cot lam bang gach o6ng doi vdi n h c a'p 4, nlhO ban kie'l co; chnieu cao .;tung thap nh.nar dudi I , 6 met aoi vdi nha ram thi don gia boi thuon,g tinh bang 80% don gia bAi thurdng theo cap rihi tu'ong - TrLonc hoip nha, c6ng trinh kh6ng t6 mat tLfdnT xung quanh thi don gia boi thLrdng dudoc tinlh bang 85% dOn gia b6i thL'dng theo ca'p nha tu'ong cmng. - D6'i vdi gac go xOay dtrng trong nha tai cac muc 1.3 va 1.4 dOn gia gac D6 dU'oc tinh 150.000 d6ng/m2 sur dung. Phan dien tich nha chinh tinh theo ddn gia cap nha tu'ong tmngc - Doi vdi nha tien che khung sat trbn, keo sat, mai tole,-vach tole. nen xi mang don gia tinh nhu' nha tam loai 2. TrLdng hop kh6ng c6 vach t,nh theo don giad nha tam loai 3. 1.6. D6n gia b6i thd6on2 calc c6n2 trinh phu - Ao dio tinh .hoi 1Jdng ?11(in rL'j co, kh6nz tinh nn3n ci2p) i0.000 d,ng/m- - Bd kR dOt (Cp duana ao h65 kh6n- c.in JAo saL, chi' lam bo k,;): 7.500 don /m- - S^an i, lang, xi m 40.(000O cInIT'.-I - SI I b e to n 2 f lin -i !3T .di .................. in x cm . z{I i lrr.t; ' , '') _(K ! r)(! :, ! . ,70 // .) ))000 dOll c, m S }n b. L6 n 03 ri; 10 -~~.000 JOrm'in - -~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~n o rndile 3w >) rj') F,r z,i - - 5 Ghi ciCh - Chuong trai chadi nuoi, nhKi tam, nha ' eMh neu k(h6ng lot ne` thi trl'r 40.OOdongI/m - Gia tri cac cong trinh phu diidc tinh 100%. - DE)i vdi be' ( ho) xay ,,ach c6 ket cau don cian klh6ng dung cho nhu cau sinh hoat mrn dung cho muc dich khcri nhu' nu6i ca, con gid tinh banng 80% mdc boi thtldng quy dinh. - Do6i vdi ao dao: Ngoai phan xac dinh don gia boi thLudng theo kho'i lu'ong du'oc tinh boi thuidng them dithen tich c6 rna.t ntfrdc nu6i trong thuy san . - Trudng hop nha tam, nha ve sinh xay dutng trong nha a, nha bep... da xac dinh theo don gid boi thrnMng nha, kh6ng tinh boi thuOcng them phan dien tich nay. - Don gid bMi thtrdng dien ke, dien thoai a tren ap dung cho cac ho bi riai toa trang hoac dien tich dt con lai du'ti 40 m2 d i vdi dat d6 thi va du'i 100 m2 doi vdi dat khu dan ci. n6ng th6n. Tru'dng hop dien ke phu aan sau dien ke chinh kh6no xAc dinh boi thutdng. - Tru'dng hop sau khi giai toa dien tich dat con lai tu 40 m 2 tr6 Ien d6i x'di dat d6 thi v) tdf 100 m tr6 len doi vdi diit khu dan cu' n6ng th6n. Don riaI dien ke, die cn thoai dt.oc tinh nhu' sau: dien ke chinh 300.000 dong/cai; dien thoai 50.000 dong/cai . Truo6ng hop ho6 ga, ham tmu hoai c6 ket ca'u nhu gieng dao thi don- cgi bMi thuLdng dtfoc xac dinh nhu' dcn gid boi thidsng giengdcao. - E6)i vdi cac c6ng trinh ky thuat ha tang can lien vdi dat giai toa (dcl du' dieu kien b6i thudn(g tai muc 2.1 khoan 2 dieu 3 quy dinh nay) thi boi thuodng thiet hai bThg cgi tri xay dung mdi. - Cac trudng hop don le kh6ng co don gid boli thu`dng trong Bang quy dinh nay thi H6i dong kiem ke boi thodng tien hanh dinh gid boi thudTng (lap bang, thuyet minh xac dinh ro co so dinh gia', cac yeu t6 cau thanh nen don gia boi rhLdrng) gCui S6 Tai chinh - Vat Lia th`am dinh trinh UBND tinh ph& duvye. 2. Doi voi nha bi giai toa m6t phan ( nha naim tren du'`ng ranh g1ioi khu gia i toa) 2.1. DSEi vdi nha bi (iai roa m5tr phan nhuna phan dien tich ccln lai bi -nlh ho.;nc ket cau hoac dien tich con Ii rho kh6nzg d ng dcc ( PhLin dien richn con iai eko theo nioi coc GPIB,N. Ne>U nha. con, ir`,nh il duvnc tren . ~ ~ ~ ~ ~ - . . mCi'c b6i du? ng quy jtiui' tu'Ong Lr11lg theo don -ici c16i v ci c,ne trlin h '`tv dOn> hop phLIp. 4. Do'i vdi nha , cong trinh nam trong hanh lang giai toa bao ve lu'6iLdicn 4.1. DEoi vdi nha a, cong trinh nam trong hanh lang giai toa bao ve ludi dien khong phai di chuye-n ra khoi hanh lang bao ve neu dam bao cac dieu kien sau: a! Lam bang vat lieu khong chay. b/ Ket cau kim loai phai no'i dat theo tieu-chuan hien hanh. c/ Khoang cach thanng dng tu' day dan a trong trang thai tinh de'n bat ky b6 phan niao cua nha va cong trinh phai bang hoac 1dn hon 4 met theo phtldng thing du'ng. d/ Khoang dudng day di phia tren vudgt qua nha va cong trinh phai thtuc hien bien phap tang ctfi,ng an toan ve die.in va ve xay durng. Tru'ng hpp nha, cong trinh xay du'ng hop phap ne'u chn'a th 'a man 1 trong 4 dieu kien a, b, c va d a tren thi chu dau tu con, trinh phai chiu toan b6 kinh phi de cai tao nha7lm thoa man cac di6u kien d6 (bao gorn ca boi thLrng phAn bi pha dO, kinh phi dce cai tao, sra chC'a nha 3, c6ng trinh). N*oai ra cOn dtfoc ho trci them do nha a, cong trinh bi han che kha nang sO dung. M6rc ho tro do-i vdi nha cap 1, ca'p II Ia 10% gid tri va nha ca-p III Ia 30% gid tri ( sau khi da trur gia tri sO' dung con Jai theo thtrc te nhn'ng rnumc toi" thieiu khong thap hdn 60%); nha cap TV va cong trinh phu d6c lap la 30% gia tri, cua phan nha 6, c6ng tr3nh tinh tren dien tich naim trong hanh lang bao ve an toan cua dn'dng day theo gia xay durng mdi cua nha, cong trinh c6 tieu chua`'n ky thuat tu'dng dixong. Do'i vdi nha a, cong trinh bi hanh lang bao ve an toan ditng day dan dien cao ap chiem dung tren 70% tong dien tich mat bang cua nha, cong trinh d6 va cac tai san khac bi han che kha nang su' dung thuoc do'i tmng dcloc ho tro neu tren thi diroc tinh cho toan b di.n tich cua nha, cong trinh. 4.2. Do^i vdi nha a, cong trinh n-am trong hanh lang uiai to-a bao ve lLrdi dien can phai di chuyen ra khoi hanh lang ne'u khong thoa man I trong 4 dieu kien a. b, c va d die'm 4.1 a trin ( ke ca trurdng hop du 4 dieu kien a, b, c va d diem 4.1 tren ) vdi ly' do chinh dnog thi dLruc boi thYdng theo cic dieu 3, dieu 4, dieu 5 va dieu 5 tai Qun dinh nOv. 5- :u w i~p -G U Ci- S i il -IL 1 ' U !0c !i : ac - Li .* chieu cao chuin 2, 5m, dOn dil. Nu'dc xac dinh baJng he so giua L -iJ oc tieu chuan chia 2,5m nhan vdi chieu cao thuc e.c - Trodng hp noc tieu a1 cdy an trai thi kh6ng tinh c6ng them don )i noc tieu ma tinh boi thuf6ng rieng- cay tieu va cay an trai d6 tuLing Cfg, vdi nam tuoi cay - Noc tieu cay song nhir cay v6ng,,l6ng mit . 10.000: o dong,/noc 1.4. Cay Ca phe: Mat dM tc'i da kh6ng qua 1. 110 cay/ha. - Cay 1 nam tuoi: 15.000 d6ng/cay - Cay 2 nam tuoi: 20.000 dong/cay - Cay 3 nam tuoi: 25.000 d6ng/cay - Cay 4 nam tuoi: 30.000 dong/cay - Cay 5 nam tuoi: 40.000 dong/cay - Cay tlu 6 den 10 nam tuo6i: 80.000 dong/cay - Cay tlr 11 nam tuoi tra ln: 40.000 dong!cay 2. Cav an trai: 2.1. Cav Sau rieng, Mang cut: Mat dc. tC)i da kh6na qua 156 cay/ha. - Cay I nam tu07i: 40.000 dong/cay - Cay 2 nam tuoi: 60.000 dong/cay - Cay 3 nam tuoi: 80.000 dong/cay - Cay tr 4 den 5 nam tuoi 100.000 dong/cay Cay tur 6 de'n 7 nam tuoi: 150.000 dong/cay - Cay tu' 8 d en,9 nam tuoi: '00.000 d6ng/cay - Cay t 10 nam tuo6i tr6 ln: 250.000 dong/cay ).2. Cav Xoai: Mat d6 t6`i da kh6ng qua 156 cay/ha. - Cay tnO 1 den 3 nam tuoi: 30.000 d6ng/cay - Cay tO' 4 den 5 nam tuoi: 40.000 dong/cay - Cay 6 nam tuo'i: 50.000 d0ng/cay. - Cay 7 nam tuoi: 60.000 d6n-g/cay - Cv tnu' 8 den 10 nam tuoi 70.000 don6/cThv - Cay tu' 11 nam tuoi tra len: 100.000 (10ong/cdv 2.3. Cayv Mit. DiYa. Me. Ch6m chom. Nh n. Cam. Bui8i, Vii sda: - Cav 1 nanm tuoi: -01 J S nlI - C v 2 na m ti:. 6l ()()fC) 0 dLI,")n c' - Jf C' i V :0Lo o d - Civ k. co n rLii: I .O0()f) nc/cl.n/ 3. Cv a'v ago0 3.1. Cdv Xa cii (mLt do kh6ng, qua 400 cay/ha): - Cay I nam tuoi: 14.000 dong/cay - Cay 2 nam tuoi: 20.000 d6ng/c6y - Cay 3 nam tuoi: 27.000 dong/cay - Cay 4 nam tudi: 29.000 dong/cay - Cay tu 5 den 6 nam tuo^,i: - 36.000 dong/cay - Cay ttr 7 den 10 nam tuoi: 46.000 dong/cay - Cay tai 11 nam tuoi tr6 I&n: 70.000 dong/cay 3.2. Cay lay ao guy (Giang hu'irng. Bkn Iang, Gi. tv. 0o. Sao, DAu): Mat do kh6ng qua 400 cay/ha: - DiI6nc kinh < 10 cm: 50.000 dong/cay - Didng kinh tii 10 cm d6n 20 cm: 100.000 dona/cay - E)DuLn kinh tu tren 20 cm den 30 cm: 200 000 dong/cay - Du'6ng kinh tP' tren 30 cm tr8 ln: 250.000 don,/cav 3.3. Tram b6na vang. Bach dcn. So dua, Bana: mat do kh6ng qua 3.300 cay/ha: - Cay tu'i nam tuoi tra xuon, 2.000 dong/cay - Cay sau 1 nam c6 dArng kinh < 10 cm. 10.000 dong/cay - Dtfdnc kinh tar 10 cm den 20 cm 50.000 dong/cay -DYrng kfnh > 20 cm: 70.000 dcng>/c4y 3.4. Tre ( Tau, Gai, Manh toncl: + Trong duTh I nam tuo'i (to"i da 200 bui/ha): 20.000 dong,/bui + TLi I nam tuoi tr6 ln 5.000 d6ng/cay 3.5. Tre ma, Tam v6nL. Lo 6: + Trong d'oi 1 narrd tuoi (to-i da 1.100 83000 donc/bui b u i/h a): T Li I nam tuo6i trr- &n 31000 nnO/civ -, - >0. F uc: -6 Tron g dldi 1 n;m-tuoi ( toi 0 i I 00 bu i/ha ) .0 6)Jon c7b u' + TU ' In& w5i rrn Je: K () Jv - t T;, Li LJ b6i .(1i'Li C> u' -- i r L UI, ! U Ij tinnh bci, thu-dng tEfng caly, dien tUch con Jai trong caiv g'j th'i tinh b(i f rhWng 1oui cav d6. - Do"i vdi cay hang nam tro6ng xen cay hnhg nam n h trLn,g lua xen bap, chuo'i xen thom ... thi tinh boi thu'(ng chung cho mo,t loai cay co gia tri boi thiLfing cao nha't tren co s6 qui ra dien tich kh6ng dem cay. '-Mot s6 loai cay hang nam do tr6ng day dac kh6ng clem cay de' boi thufng ma qui ra mat d cay trong theo dien tich tufong ing. - Doi vdi cay chuoi va cay thim: kie&m kc so tling cay thic te tren tiYng bui nhurng moi bui xac dinh kh6ng cIdu'c qua 5 cay/bui doi vdi cay chuo'i, khong qua 3 cay/bui do'i v6i cay thdim. - Doi vdi cay tr6ng ven ao ho, tr6ng ranh vu'6n: dinh mtc cay trong duic tfnh duia theo khoang cach cay tieu chuan trong hAng cu'a loai cay trong cl6. - DEoi vdi cac loai cay hang nam, cay lau nam chu'a c6 don gid va dinh mdc trong cay trong Bang quy dinh nAy thi H6i dong kiem ke boi thu'3ng van dung din gid boi thudng cay trong tiLing duirng. Tru'fng hop ca biet khong van dung du'oc don gia loal cay trong tuLing du'ong thi tien hAnh dinh gia boi thildng loai cay d6 (lap bang thuyet minh xac dinh ro ci sa' dinh gia, cac yeu t6 cau thAnh nen ddn gia boi thiLdng) gai S6 Tai chinh - Vat gia tham dinh trinh UBND tinh phe duyet. - Doi vdi cay c6ng nghiep, cay an tral trong tren dact duLdc boi thlfdng tai diem 2.1 muc 2 dieu 3 d tren neu trong sau thdi die'm quy hoach (hoac th6ng bao quy hoach) kh6ng dilcc xem xet boi thiLdng, ho trd. - E)i vdi cay c6ng nghie,p, cay an trAi trong tren dat kh6ng dclroc b0i thLd%ng tai diem 2.2 muc 2 vA diem 3.3.4 muc 3, dieu 3 a tren kh6ng vi pham HLBVDB ne6u trong trildc thdi die6m quy hoach (hoac thong bMo quy hoach) dcILc xem xet h6 tro bang 80% din gia tircng u'ng loai cay trong tren dat duLdc boi thirdng. TruLdng hop dcILc trong sau th6i diem quy h'oach (hodc th6ng Mbo quy hoach) kh6ng du'oc xem xet boi thLrng, h6 tro'. Dieu 7: Tru'dng hop nhA, cong trinh dam bao d' cac dieu kien a; b, c, d diem 4.1 muc 4 dieu 5 a tren va cay ngan ngay, cay c6ng nghiep co 6.o cao khong che ( nhiL cay ho tieu , dau cac loai ... ) lh8ng phai di ddi ra kh6i hAnh lang giai toa lLil dien thi tuy theo mii'c dM thi c6ng lam anh hL'ang d'en cha't *liong c6ng ,rinh, hu' hai cay trai .... do To chuyen vien 7im ke boi [hdCng xac dinh mCTc do thi&t hai de lam ci sa bMi thudng. -; '--1-I -,1-: *. k O I I .r M. Dieu 9: Chinh s6ch tai dinh cu': 1. D'oi v6i nhufng h6 c6 ho khau thu'6ng trO nali co d] t c6 giai toa, bi giai toa he't dat 6 hop phap [hoa,c dien tich dat con lai du'di 40 m d6i vc;i dIt d6 thi va dludi 100 m2 doi v6i dat khu dan cu' n6ng th6n, hoac dien tich con lai tren 40 m: d6i vdi dat d6 thi va tren 100 m2 d6i vdi dat khu dan cu' n6ng th6n nhu'ng khu6n vien dat c6 hinh thu kh6ng the xay du'ng nha 6 du',dc (hi,nh thu nha kh6ng c6 yeu to tham my)], kh6ng con dact su dung a ndi khac, neu c6 nhu cau cho ' mdi thi phai lam din dang ky bo tri tai dinh cu' c6 xac nhan cua chinh quyen dia ph'ddng ndi thifing truc de du',c xet cap dat tai dinh cur. Tuy theo tufng du' an thu'c hien giai toa boi thu'r5ng, UBND tlnh hoac UBND huyen, thi se xem xet bo' trf tai dinh cu! tai cho theo de nghi cu'a Mi d6ng giao dat 6 cuia huyen, thi xa (ap dung doi v(3i cac du, an c6 bo tri tai dinh cu!). 2. DEoi vdi cac du. an c6 bo tri tai dinh cu', cach thuc tien hanh phan 16 dat va nguyen tac giao dat nhu' sau: a. Uu ti&n cho nhC?ng ho s6'm thu,c hien ke hoach giai ph6n; mat bang tiep de"n 1a nhuing ho thuoc do'i tu'dng chinh sach xa hoi nhLr ng(idi c6 cang vdi cach mang, gia dinh liet sy, thLrong binh. b. Cac ho c6 du' dieu kien giao dat tai dinh cu! ma c6 nha, dat bi giai toa nam a mat tien thi sec diu'c dang ky 6 ngay 16 mat tien cu'a khu tai dinh ci!. Trong tri!dng hOp so6 hlrng 16 mat tien kh6ng dlu thi thur tif uu tien se didc tinh cu the cho nhCung tru'dn g hop c6 nha tren dien tich dat tho cu' ldn, c6 da't th'o cu' ma chieu ngang dat mat tien dtrdng rong, chui sui dung dat truc tiep dang san xuat - kinh doanh on cinh ke tu tru'dc ngay c6 quyet dinh quy hoach, nhIng ho ke' tiep dang nay ne&u bo6 tri nhang 16 a ben trong se du'oc chon vi tri thich hop. NhCing tri!dng hop con lai chi di!cc dang ky va bo tri a nhuin,g 16 ben trong theo thu tui nu tien nhu! tren. c. Trt!dng hop ho gia dlinh c6 dien tich dat giai toa ldn (trong d6 c6 dcat .hoS cL duIoc boi th i!dng), va c6 dong nhan khau thLrdng trd tai dia diem giai toa (rtu 0.5 nhan khau tr6 In ) tu' tri!dc ngay quv hoach dtu an (trong d6 co ft nhat 03 nhan kh'u trcn 16 tuoi vd. c6 ft nhat 01 ngu'i con trong h6 d lap gia linh nhi!ng chu'a tAch h 6) neu thifc s Y c6 nhu Liu taich h'6 tai dinh cL thi toy mI F, A i-J Ln) G2U :i-n,ivm i Lch, k- hotach dl chuyen. boi thrdng da uu'ofc co quan chu'c nang giai thich nhieu I-a nhd thuc hiehn dcun quv dinh boi thlOjng hoac tro cap theo Ba?ng quy dinh nay) nhiing 1,ch6n, ch'p hnh di chuyen giao tra mat bang thi c6ng cong trinh thi se bi xuk 1 theo Luat dinh. So tien boi thu`Jng hoac trd cap theo quy dinh (neu c6) dOc5c tam gui vio Ngan hing NhM nodc theo che do tien gci tiet kiem n(gan han do chu dau tu' c6ng trinh tam thdi dutng ten. Cac tru`dng hdp nAy tuy theo tCfng du in UBND huyen, thi xa ra quyet dinh cifang che thi hanh, nhung truWng hop bi cifng che thi hanh giai toa se bi khau triY chi phi to' chuc thurc hien coang che trong so tien b-i thu'dng hoac trd cap theo quy dinh( neu c6) dong thei cac tru'dng hop nay khoing dtrqc xem xet b6o tri dat tai dinh cu (tuy du' dieu kien x6t cap dat tai dinh cu') va kh6ng duoc thu hoi vat tu va cay trdi sau khi to chtc coPng che. H6i dong bMi thuOng to' chic ban so vat tu va cay trai thu hoi nay, so tien nAy diidc nop 100% vao ngan sach NhA nodc sau khi trU cac chi phi lien quan dlen thu gom va to chcc bin. Die^u 12: Trach nhiem cua UBND cac cap va Hoi dong giai toa boi thutng. 1. Trach nhiem cu'a UBND cac ca'p. a. UBND tlnh: - Thanh lap H6i dong giai toa boi thulcng doi vdi cdc dir in trona die'm tren dia ban tinh. - Ban hanh chinh sach gid giai toa cho cac dtf n ddu td tren dia ban tinh va phe duyet do toan chi phi boi thodsng va chi phi thic hien giai toa do-i vdi nhEfng df in co nguon von thuoc ngan sach tinh va nguon von khac dau tO tren dia ban tinh theo de xuat cu'a S8 Tai chinh- Vat gia. b. UBND cac huyen, thi xa: - Thanh lap, chi dao Hoi dong gii toia boi thu'dng va Hoi d6ng tham dinh boi thodng huyen, thi xa thu'c hien tho6ng bao, tuyen truyen van d6ng, to chiic hop dan neu ro 1y do thu h6i da't, trie'n khai kiem ke ip gia, tham dinh, boi thodng,, giai toa. - Phe duyet do toan chi phi giai toa boi thodng doi vdi nhurng du an c6 nguon von thuoc ngan sach huy&n, thi xa theo de xua't cua H6i dong thai'm dinh boi thi!dng (Phong Tai chinh - Ke'hoach) huyen, [hi. c. UBND cac xa, phu'5ng, thi tran: - Phoi kt hop vdi H6i drng giAi to' boi rhu'dn- tuyen truvcn van d6ng nhan dan trcn dia b an chp hnfh tot chinh-Y' ~j vA ,4 Cst '' ''' .t /~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ *~~~ ... . ' ' ' ; , .,;.........,; . ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ; ; ~~~~~~~~~. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...... .. ..... . .. . .... ..... I . . .. . ...................................................................................................................................................... , , * . * 4 ......... ........................ ................... ... ;~\i~c) '~rv~ *ThX~~A mIj aIk;I..................IIIt... .. . . . . . t;r j-;'''''' ................... .....................................................................................................,. ,','. ;,;,,.,.. ,w,Li_#...... ....................................................................................................... !.'~~~~~~~ ~~~~~ ., '. ,Wi ............................... ..................................................... I................................................ ................................................. .......................................................................................... ........................................................................... ......... ................................................................................................................................................ ..................................................................................................................................................... ..................................................................................................................................................... .......................................................................................... ........................................................... ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................... ...................................................................................... ....... ..... .... ... *..... .... .... ..... .... .... ..... .... .... ..... .... ---..... .... .... ..... .... .... ..... .... .... ......-.--..--... :ue pip rnn sUpsPI1 1OI Su9p oe aA ual Ai e .Bu,o,n- I4uPI4jl ex UNHn BU9qtd ueA Pi3 b'OOZ aieu 80 DUPtI 1 Of SNI ss9NOJ I Of1HJ AM1OZZ IMWThL,, VA ; ONOrI l9lHd -HN[IG Nyl A5IOZZ NyCI {3NQp(f1U MV p(I VLn dtl yA VI[ OyD OyS t3A 9MU (I NQ) NJYA JA\IVUI dOHl DQfL) Jy1U NYu IQpONJ ONQ[HN vf1C dQO DMO(G NSlIM A Zb-lW-WEI:SU\I [0uq uewl tA WVHi dH Nta N3S DO3dI .. - .v;. -r. *1-' . -;_'.' ;.' '...... . . ............................................................................ . i ~.I. ...1J., . '. . .. r. .. ................ y............... .').;, .. . .. . . . . ..........%... ..... ........../.' . . I.......... .. I ....... ~.~ . ..... ................................ ........................................................................................................... ....................... 7 ........ ............................................................................................................. X, , L, I L~~~~~~~~~~~~~~~~~~~~~~~1,'h ' t. . . ....... $4wJ..&. . " . ..................................................................................................................................................... ..................................................................................................................................................... ..................................................................................................................................................... ....................................................... ......... . ......................................... .... . .. ......................... ............................................... .................................................... ....................... . . ... ................ ............... I.............................. .. .... ................................I ........................... . . .............................. .......rn qu N AVVH.. dO N7 N'I Jc; . . .. .. .. .. .. .. .. .. .. .. ... . .. .. .. .. . .. '' .- .......V ....... j ....... ....... ....... ....... ....... ....... .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . .. . .. .. .. .. .. .. .. .. .. .. .. .. . .. j. '''- .''1'' '....... ....... ........ ....... ....... .............. ...... ,W ..., )\ ....... ... e sk ,_ - * - - - -- - -- - -- -- ~-- -'m- * - - ---- - - -s - - - - - -... - -X I .... - - -; - - - U - - .......... ...... .. .... 1 1 .. . ........Wl''% ,6 ...........~~~~~~~~~~~~................ ..... ....I....tc....... ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ . ..... . ... . .. ....... .,... .. .. . ....... .. ... ..... . e----N*------ e ~ ~ ~ ~ ~ ~: .. n ...........tlewlaMaaulaA ,e *3'UpBA 'ttU8'4LeX aNGA 'UQQd UX 181 bOOZ u.....0.... ...01.... .... ....... ........... ...... 1ANtS,wlAs Nt ,p d H I N>LAIZ sta~~~~~~~~~~~~~~~~~~~~~. ....d .... .... ..... .....SO D V S Nw N V tUVI OH on AaZUHS Q2N O2H v nzd99ONd NV ^ ...... ..... ..... ... . ... .. ..... ...... ... . ...... ..... ...... ..... .... i :lqq /986N t3vQ .ONQ::)...... ... ... .. ... .. ..sw .. .. ... .. ... ........ .. ... ..... ... .. ... . ... ... .. ... ..3.. ...1... .. ...;v .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . I . . ... . . . . . . . . . . . . . . . . . . . . BIEN BAN HOP THAM VAN Lan bh :01 | PECC3 CONG SONG Ngay bh: .......... ... ................... ................................ ... ..... ... ..I ............................................................................................. .. ................................................................................................................................................... ... .. .. .. .. .. ... .. .. .. .. .. ... .. .. .. .. .. .. ... .. .. .. .. .. ... .. .. .. .. ..I.... .. .. .. .. .. ... .. .. .. .. .. .. ..........I........................................... ........ ............................................................................. .................................................................................................................................................... .................................................................................................................................................... .................................................................................................................................................... ................................ ...................................................................................................... ...................................................................................................................................... .................................................................................................................................................... ..................................................................................................................... ................................ .................................................................................................................................................... .................................................................................................................................................... .................................................................................................................................................... ................................................................................................................... ................................................................................................................... . ................................................................................................................................... .................................................................................................................................................... .................................................................................................................................................... .................................................................................................................................................... ......................................................................................................................................... .................................................................................................................................................... Dai di6n Dai di6n UBND xa Thanh Ldcing Cong ty T van Xay dufng Dien 3 ; N1i s 1 "! ,,, ~~~~~{ * ..:t ? -,/ -> '...:\ ,,--; PECC3 ~~BIEN BAN HOP THAM VAN Ln bh : 01 4M:B-T4 CONG {)ONG Ngay bh: DANIH SA.CH DAI BIE'U THAM DU CUOC HOP THAM VAiN CONG DOING VE BAO CAO EIA VA' RP CUA DU' AN "DI3TNG DA&Y 220kV TAN DINH - PHU'O'C LONG " vA "TRAM BIEN AP 220kV PHIf()C LONG" Ngay 10/08/2004 tai Van ph6ng, UBND xa Thanh Ltfdng STT Ho va te^n Co- quan Chuic vu Ki ten 3' / +~i'fte'. '79..9,/v tEll;1.'4.g.l.,t S,t7.- t-- X z ,/.k_, _ 9? ,/'~~v< }z,>w-6// '4' D'5- 5 Z l~~iAi fx3, . -2 / )9h1 t .r tyta >&Z'8 ^8 F{ 0 bC) < jt,J ;f}S i /rKZ )to y f _ op t /s-/ *.frl t~t 4 - 1 ,, ,a!2r, zw . ' I' t /;, f. .64 f v}ls-i f 4otr {, ; 1 )it,' 1 ,Xr,)5//,, '< w g -WX ,,, g ' st tg*,) X -A / , , 9 ai t C gg4 *-}4160 4)tgleSs i.ita[I. X < ??J- ,> t s (r2t ,: I ^g1 t 9X j A.X~d 7 1 ,K,.$/7 M/t% \rh g 3'[/''' J A Clg- 5 -! t rsYi /c'll aZ>/tfGr,wr . 2: ,G)1>9 gX) r > = 6 arzl~~~~~~~~~~~~C ; 3 ~~CONG E)O" NG N gay bh: MMT4 DANH SACH DAI BIE'U THAM DU CUOC HOP THAM V,&N CONG DONG VE BAO CAO EIA vA RP CUA DV AN "DJ4NG DAY 220kV TAN DINH - PHI1()C LONG "9 vA "TRA.M BIEN AP 220kV PHtf(C LONG" . ~~Ngay 10/08/2004 tai Van phong UBND xa Thanh Lifong STT Ho va ten Cy quan Chuce vu i e ,,,~~~~~ A7 c , , ig &>t41 t'-,' h 'g ',- 5 0 ((l'lt(. ! (t. li 1,7 t!'< > . _ . t- c;(ll?i/t L ( )(\4 ; v *) g|-gr-1 _ b~~~~~~~~~~~~~~~t -7>(t-' .9f\d, gmzLfz,t;kg fizit St 5 psf ~~-#>1/# ,4,,. -t> . :/.=2r ...,>jfi,,,, A___ . z ,17/4f4-gi fet Af'yd 2cd aio -4 r7, r~~- L crr g ly a(v )Xlt ;ltts/ /{; + t/-~~~~ ~~~~~~~ P,) /6i/t';'Z (1}1. . t;r^ $\; /*<( sC+ ,,1 ? / > g 77; N1 a () z9z -/ ,>. ,i<.. /-l :2 , , / il /_ / ,.' L . i t (, ' t. f' L H j , t' l \ } ' \ r e- C * { >./ b '"+ tz|tfl,C?,2v-/.........................._l 2' / / * 7/ re' /' ' 'J '{ ! i /J _Vl, >)~~~~~~~~~~~~~~~ ,,(7v.Xz'-; , v/1'z |/ 1 f? ss + /'J/fl7 t-Z/; _,g ||. . - i4 P PECC3 | BIEN BAN HQP THAM VAN Lin bh :01 MS: BM-MT-42 PECC3 CONG {)ONG Ngay bh: DANH SACH DAI BIEU THAM DU' CUOC HOP THAM VAN CONG DONG VE BAO CAO EIA VA RP CUA D1f AN "DU'dNG DAY 220kV TAN DINH - PHU'dC LONG " VA "TRAM BIEN AP 220kV PHUf'C LONG" Ngay 10/08/2004 tai Van phong UBND xa Thanh Lufdng STT Ho va ten Co quan Chuc vu Ki ten 4~~~~~~~~~~~1~~/ 1 V-1 ;.047 , I .1 .th f > i / f ~~~7 1 6, , 9 /, /YI 4,' k./tg, t2 . ) 7 // /)4t- .6 ( i,> /. ,. 7 -,n ):o , /' X 7-/f /-5 1 Ph //r s-, ,~) t1 (1.4'I I. ' tf (4i.. __ ___ __ __ ___ __ _ Y) , _t;,'i,./ ' i, - - H . - . ~~~~2 t " 0 ' .* !/ t1 . t'- I 4... . , (, ___ ' _ ___ __ ' . _ < _ ) ?. (Th i/\,1' ' "-;'j1)1 I '. ... 'L ',~ ..... _? /'\ -7 ._ 1 -I~~~ . - -.0 ! , 4 t1! ,' 8 >0~~~~~~~~~~~~~~~~~~~~~~~~~~~s ,. ,,,; , 4-' ',l ('4 1& 'i- l'i /I - _. I'"" ;'r -'' '_ ''. ':-' "_ _ _ __ _ _ __ _ . __ _ _ I~ ~~. I: I' I I /h,~~~~~',~~~~~~') L7-.~~~~~~~~~;7 C ~~~~~~ ~ ',- 1~~~~~~~~~~~~~~~~~~~~~~~~~F APPENDIX 6 PHOTOS OF PUBLIC CONSULTATION MEETINGS 4 4 X~ I~ ~ ~ ~ ~ ~~ ~~~ I IN . PAPs attended to public consultation meeting (People's Committee of Thanh Luong commune) PAPs are expressing their expectation of compensation !" 9i - '4 : . Representative of People's Committee of Thanh Luong commune is expressing his PAs a sopinion about the project APPENDIX 7 a DOCUMENTS OF AGREEMENT ON THE ROUTE AND THE RP OF THE PROJECT I l Ii . . ,Y,1:} BA/N NH XN D,&N 05)NG HOA Xl' E I , BUl3HR TAJ-Vjj; p TS'H BI]E PE(i C . ~~~~~~Dot lap- "rif do - '--linh u< . t SS F 2i .... / Pg-KSS ~Bilzh P.hM&c, h)'-+(.t-O-ib 04-M6rg20 ' nd :2 Ye' VjtC t}:..o Lhuani s-v un m)i C;l2a trBm b!6n oS .220K..-fn; da 1 pRIi , . kho-ang 1O00m).---.- ... -. | , -- ~~B60 glAp.3nU da'n st2 xrbn C'116u. ,.;-. | . . ,!/ Ti4nt&fzijd?g d&y 2-20MURT:- | t - $);~~~~~n t-U ranh gi6 i B inb Duedt- i E3tI n P h f6 c C- "CZ P xa Tar. K iali I\ trS tr.arn thco tho-a t>k.uRn tai ' wvn f 1j `-,WVB-YSX.rieay 751071:' 003) ihttr her t_ .~~~~t~ tha thifuan tai cacnt van SQ i 184/'-UB-SX nczy;/25/d7/C,-2003 :,--"a UBiZN1 tlr B3in.h : h~ -h6C. f -E) o'I tr x a ,Ta n IKhia i tl,-5n a"Ip P h i Lic xa Thanh phu :5i cap sOgsXl 4 bdNt tliief hai. .,,.;:I -Doan Lil ap Ph lWctatAo hen vi t-ri tiam m6i (NT6'i 8 i;. rca c:ac i72o;u MS /20 3 tlnh 5,Bjh, Phildc..| ' ~~~~~4/ tCac n8i dungr khd c t h11c E -iiE th.eo -c6n,vft is' -184/ijBLE9S ;na : 2^5/:D702003 cUa TUBNT t'ilnb, Blnph, Pr6c. C'T,; 8i :- . - 4 ffitw K <~~~CO D~\ ,T ...... .~~~~~~~~~~~~~~~~~~~~~~~~~~~~~N-'' FL N . . UY BAN NHAN DAN CONG HOA XA HOI CHU NGHIA VIET NAM HUYFN BINH LONG DEc lap - Tir do - Hanh Phuc I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ So: :L /UB-KSX Bitnh Lonig, ngay 06 thdng 8 nidmii 2004. ' V/v Y kie^n thoia thuan ke hoach tdi dinh ci. Kinh gdi: Cong Ty Tif Va'n XSy Du'ng Dibn 3. UBND Huyen Binh Long da nhan dicjc: - Van ban so 3317/EVN-TVD3-MT ngay 22/7/2004 cuia Cong ty Tuf Vadn Xay Diung Dien 3 ve viec th6a thuan ke' hoa.ch taii dinh cu' cua du an Tram bien ap 11 0KV Binh Long. -Van ban so 3380/EVN-TVD3-MT ngay 27/7/2004 cua Cong ty Tt Van Xay Du.ng Die^n 3 ve vie.c thoa thuan ke' hoach tai dinh ciu cua dtu ain du'ing day truyen tai 220KV Tan einh - Phu'dc Long va Tr,m bien ap 220KV Phu'dc Long. * Sau khi nghien cuu cac bao cao RP do Cong ty Tiu Van Xay Difng Di6n 3 thuc hie,n v'a 5 kie'n d6 xuat cua cac nganh chutc nang Huyen, UBND Huyen Binh Long co y' kie'n nhut sau: Ve chu trutc'ng chung, UBND Huye. n thong nhat vie, c trien khai thu'c hie,n ke' hoach theo cac bao cao RP va dia phuklng se tao dieu kien de vie c trien khai cac dii an neu tren du',dc thuan ldi. Tuy nhien, can cuY tinh hinh thu/c te cong tac den bu GPMB trong th6i gian qua tai dia phittcng, UBND Huyen Binh Long c6 mot so ' kien nhu sau: - Doi vdi tram 220KV v'a Tram bie'n ap 110KV: can xem xet nhufng ho co die^ n tich dat bi thu hoi hdn 25%, ho co nhu cau tai dinh cit khong? - Doi vdi tuy6n ditrng day 220KV Tan Dinh - Phu'dc Long: mo. t so^ quy dinh trong Nghi dinh 22/CP ngay 24/4/1998 cu'a Chinh Phu den nay khong c6n phu hdp ve mac gia den bu. De nghi chu dif an nghien cuu de van dung. - Ve tai san nam trong hanh lang an toan litdi die,n (nha kho chay) theo Nghi dinh 54/1999/ND-CP cua Chinh Phu thi diUcc de lai va phai dam bao mot so' dieu ki&n . Tuy nhien, trong thuc te da so' ho dan cu' deu c6 nhu cau xin chuyen ra khoi anh lang de^ dcam bao dieu kien sCtc khoe, dieu ki&n sinh hoat (xem tivi, nghe dAi, ... kh6ng bi nhieu song). Cong trinh duZLng dien Can Don cung d5 giai quyet theo htrfng nay. ; ' . UBND Huyen Binh Long bao cle C6ng ty biet va tie'n hanh cac thu' tuc tie&p theo. Kinh chao tran trong. Noi nhdn: TM/ UY BAN NHAN DAN HUYENV - UBND Tinh Binh Phtl6c (b/c). U TICH - Cong ty TVXD Dien 3. 0 kt 11UN - Cac phong: TC-KH, CT Huyen. - Ltu VP. - A f l~~~~~~~~~~~~~~~~~ I 0 Uiv 1 A NN' NI-LN I)AN CON(G HOA XA HOI CHl NGHIA VI1 T NAN] FINH IIINH PHU1I(OC Mc lAp - rLf do - Ha11h phc ,4 WS6, /1'6 /B-KSX Bi7/h Phlac, n,t'v t/1ii' - i1(/ilt 2004 V f//, O ihu(M k/1(7honc1 che^;17 bhu, toii liih ctrdw(ili ntgfm, dov 22OKV Tobu Din/h - Plnuc Long, v, tram h7ic (idp 220KV Pht'Jc Long. Ki,zlh gidi: COng ty Tif xa'n xay dfng di&n 3. UBND tijnh nIIn1.11 dLrdC C6Ong Vail sO 3310/EVN-TVD3-TM n(liy 2 1/,107/2004 k&imthco bth () Cio c io CLI C6ng ty TLn vLil1 xay dYlfng d;tn 3 ve V i&c thoii thumi' kt& lioaic (dcn bbi, .Lii di nih CLr (RP) CiLr an du'f6ng day truyeln tAli din 22"()KV Tan Dihll - PhtrlCc Long v.i t-aim bien ap 220KV Phur'c Long. SilL hi clii clzio cac ngainh clhC?c callg va cta phLI'dng C6 1itCll CIUL-ll Xemil XtI \.1 dali .111 hit'u n(L i dUgLM Caic b'an bao Cio ) lie ho.ch, chinih saiclh tli dlillil CL' (RP) dlo CUlmg ty Tu' Vnl XAy dIL1CiLrir dien 3 lap. UBND t'llin cairn ki&t se tit'p tuc chi' daro caic nigaiAln chlic aLlllng (I'Ll ph'1ng(l IIphoi L(Ip Ch.1t che vdi chili da^u tL' thLuc hien ca.c cofnl_ vic tic^p tlco qUyn C Luy n1 jl1h. IJlO 11 i (i lU kli &n thuLll n .ii tloLng cuaUl irinh1l tnienl klhLi CILI' Lill n L.y/. I\1. UY BAN NHAN l)AN TINH Nii nhim: ____ _____ _U _!CH CTY(T: ' 3wi |-4 s , C HU TICC4 u In \/)-II.O i ( I 1! I A /I I I \ . h l . M.,,, ' .K . a~ ~~~~~~~~~~~~~~~~~~~~~<,{f+5 a.'un .~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ At A l