Government of Mizoram *5. > - w+M, Public Works Department E498 Volume 2 .-a,... -4to n(rial ;ut by ICTCE t, LB i s I ~~~~ * ...... . f W g n \Oct ber~ .. ~~. FIL COPY 6@e.'9rs <~~~~~~~~~~~~Oiia Doumn by ICT CES 3LBII)\ l I PREFACE | The Mizoram State Roads Project includes augmentation of the capacity and structural upgradation of selected road network in the state. A total of 185.71km roads will be rimproved/upgraded, and major maintenance works will be carried out on 518.615km roads, in I 2 Pnases. The project was prepared by the Project Co-ordinating Consultants (PCC), on behalf of the PWD, Mizoram. As part of the project preparation, environmental/social assessments were carried out, as required by the World Bank and the Government of India. In accordance to the requirements of the World Bank, the environmental/social assessments (and the outputs) had been subjected to an Independent Review. The independent review2 I evaluated the EA processes and outputs in the project to verify that (a) the EA had been carried out without any bias or influence from the project proponent and/or the PCC, (b) the I EA/SA had been able to influence planning and design of the project; and (c) the outputs, especiaily the mitigation/management measures identified in the EA/SA processes are adequate for the project. I The following documents (dated May 2001) were available for the Review: . Sectoral Environmental Assessment (SEA) for both phases of the project (prepared at the feasibility stage of the project and the Phase I of the project) * Detailed Environmental Assessments (EA) for the work programme in Phase I of the Project, * Environmental Management Plan (EMP) for the improvement/upgradation works in Phase I. * Resettlement & Indigenous People's Development Plan (R&IPDP) for the I improvement/upgradation works in Phase I. * Environmental and Social Management Plan (ESMP) for the major maintenance works in Phase I. As part of the Independent Review, gaps and deflciencies in these base documents were I identified. This report is partly an outcome of the Independent Review, closing the gaps, as per the information/data supplied by the PCC and supplemented by field investigations carried during the Independent Review. This report took into consideration, the comments/observations made by the World Bank on the base documents. The recommendations from the Independent Review are incorporated in the SEA and the other Phase I EA/SA reports (as well as in the Engineering Drawings, and the Contract Documents). All reports now are modified and structured as per the comments from the Independent Review. Note: The Data provided in the reports, unless specifically mentioned, are from the Base EA/SA Documents. PCC was a consortium of consulting firms, led by Intercontinental Consultants and Technocrats Pvt. Ltd., I India (ICT) and Consulting Engineering Services (India) (CES) in association with Louis Berger International Inc., USA (LBII). 2 The Independent Review was undertaken by Ms Lea Associates South Asia Pvt. Ltd. l I TABLE OF CONTENTS CHAPTER-1: INTRODUCTION ....................... 1-1 1,1 Project Background .................................... 1-1 I 1.1.1 Location .................................... 1-1 1.1.2 Project Identification .................................... 1-1 1. 1.3 Feasibility & Phasing .................................... 1-2 1.2 Scope of the project .................................... 1-3 I 1.2.1 Improvement or Upgradation works ......... ........................... 1-3 1. 2.2 Major maintenance works .................................... 1-3 1.2.3 Area of influence .................................... 1-4 1.2.4 Indirect area of influence .................................... 1-4 1.3 Project implementation programme .................................... 1-5 1.4 Environmental issues in mizoram .................................... 1-5 1.4.1 Jhum Cultivation .................................... 1-5 1.14.2 Bio-diversity Conservation . .................................... 1-7 1.4.3 Forest cover .1-7 1.4.4 Road Construction issues in Hilly terrain .................................... 1-8 1.4.5 Water scarcity & water availability for construction .................................... 1-8 1.4.6 Road Safety in the Settlements .................................... 1-8 1.4.7 Vulnerable human population .1-9 1.4.8 Induced impacts & Opportunities .................................... 1-9 1.5 EA/SA in the project .................................... 1-9 1.6 Structure of the S.E.A. report .. .................................. 1-10 CHAPTER-2: POLICY, LEGAL & ADMINISTRATIVE FRAMEWORK . . 1 2.1 Institutional Arrangements .................................... 1 2.1.1 Road Network .................................... 1 2.1.2 Administrative Framework .................................... 2 2.1.3 Environmental Management .................................... 3 2.2 Legal Framework .................................... 4 2.2.1 National Level .................................... 4 2.2.2 State Level .................................... 5 2.2.3 Clearance Requirements in the Project .................................... 6 2.2.4 World Bank Requirements .................................... 9 CHAPTER-3: S.E.A. METHODOLOGY.. 1 3.1 Sea for the project. 1 3.2 SeaSea process. 1 3.2.1 Project Appreciation ......................................... 2 3.2.2 Policy, Legal & Administrative Framework ......................................... 2 3.2.3 Baseline Data Collection ......................................... 2 3.2.4 Public Consultation ......................................... 3 3.2.5 Assessment of Potential Impacts ......................................... 3 3.2.6 Analysis of Alternatives ......................................... 4 3.2.7 Identification of Mitigation & Enhancement Measures ................................... 4 3 3.2.8 Environmental Management and Monitoring ................................. : 5 CHAPTER-4: BASELINE CONDITION ............................. 1 4.1 Physical & Natural Environment ....................... 1 4.1.1 Agro-Climatic Zoning ....................... 1 4.1.2 Climate. 1 4.1.3 Geology & Geomorphology .4 4.1.4 Water ....................... 9 4.1.5 Air ....................... 12 4.1.6 Noise .13 4.1.7 Forest Resources ....................... 14 I 4.1.8 Flora ....................... 17 4.1.9 Wildlife .19 4.2 Socio-Economic Environment ..23 4.2.1 Demographic Profile .............. 24 l 4.2.2 Land Utilisation .......... 24 4.2.3 Settlements .......... 26 4.2.4 Economy......... . 26 4.2.5 Health .......... 27 * 4. 2.6 Road Safety .......... 29 4.3 Baseline of the Project Roads .......... 29 4.3.1 Improvement/Upgradation Roads .......... 29 4.3.2 Major Maintenance Roads .......... 31 CHAPTER-5: PUBLIC CONSULTATION.. 1 5.1 Need ................................... 1 * 5.2 Objectives ................................... 1 5.3 Scoping Workshop ................................... 1 5.3.1 Identification of Issues .. ................................. ....... ..... 2 5.53.2 Identification of Stakeholders. 3 5.3.3 Location Specific Consultation Needs. 4 5.4 Future Public Consultation and Project Cycle. 4 5.4.1 Preliminary design Stage. 5 I 5.54.2 Design finalisation Stage ........... ................................................................... 6 5.4.3 Implementation Stage. 6 5.4.4 Monitoring and Evaluation Stage. 6 CHAPTER-6: KEY ENVIRONMENTAL ISSUES. 1 6.1 Typology of Impacts in the Project .1 6.2 Possible Project Activity and anticipated impacts .1 _ 6.2.1 Improvement! Upgradation Roads. 1 6.2.2 New Bypass and realignments. 2 6.2.3 Bridge Construction. 3 6.2.4 Major Maintenance. 3 6.3 Natural Environment. 3 6.3.1 Climate .3 6.3.2 Physiography ..................................... 3 6 6.3.3 Soils ..................................... 4 6.3.4 Water. 5 6.3.5 Air. 7 6.3.6 Noise ..................................... 7 6.3.7 biodiversity issues ..................................... 8 6.3.8 Archaeological/Cultural Heritage .10 6.3.9 Tourism/Pilgrimage ..................................... 10 I 6.4 Social Environment ..................................... 10 6.4.1 Poverty Alleviation .10 6.4.2 Involuntary Resettlement .11 6.4.3 Indigenous People ...................................... 12 6.4.4 Gender issues and Women Participation ..................................... 12 6.4.5 Highway related diseases .12 6.4.6 Community Resources ..................................... 13 6.4.7 construction camps ..................................... 13 6.4.8 Road Safety .13 CHAPTER-7: ANALYSIS OF ALTERNATIVES .................................... 1 7.1 Route alternatives ........................................................ 1 7.2 "With" and "Without" project scenario ........................................................ 1 7.3 Route finalisation .........................................................2 I 7.73.1 Overall Feasibility ........................................................ 2 7.3.2 Environmental inputs in route fina/isation ....................................................... 3 7.4 Widening options ........................................................................................................4 7.5 Aizawl bypass Options ........................... 4 * 7.5.1 Option I: Zemabawk (via Lawibual) to km4.5 of priority road P1. 7 7.5.2 Evaluation of the altemative bypass options. 7 7.6 Realignment Options ..8 I 7.7 Engineering Alternatives for Priority Roads. 9 7.7.1 Pavement Structure ........9... .. ............ .... 9 7.7.2 Road Width .... 9 7.7.3 Drainage .....9 7.7.4 Slope Protection. 9 l 7.7.5 Retaining Structures for Fill Material ........................................... ................. 10 7.8 Engineering alternatives for major maintenance routes . . 10 7.8.1 Pavement Improvement Treatment for Bituminous Surfaced Roads ........... 10 I CHAPTER-8: ENVIRONMENTAL MITIGATION, ENHANCEMENT . . .........................1 8.1 General .1 8.1.1 Construction related activities .1 8.81.2 Road Transportation Issues .2 8.1.3 Hotspot Mitigation .2 8.2 Natural Environment .2 8.2.1 Climate .2 8.2.2 Physiography .2 8.2.3 Soils .3 8.2.4 Water .4 8.2.5 Air .5 8.2.6 Noise. 6 8.2.7 Biodiversity issues .6 8.2.8 Wild-life and Protected Areas .7 8. 2.9 Social Environment .7 8.2.10 Enhancement Opportunities .8 8.3 Recommendations for EA ..8 CHAPTER-9: ENVIRONMENTAL MANAGEMENT .1 9.1 Overview of the Critical Issues .1 i 9.2 E nvironmental Management Plans .2 9.2.1 EMP for upgradation route .2 9.2.2 Environmental & Social Management Plan .2 9.3 Generic Monitoring Plan ..3 CHAPTER-10: IMPLEMENTATION ARRANGEMENTS ..............................................1 10.1 Institutional Arrangements ..............................................1 10.1.1 PlU- Environmental Cell ..............................................1 10.1.2 ProjectCo-ordinatingConsultants .................. ............................3 10. 1.3 Supervision Consultants .............................................4 10.1.4 Non-Governmental Organisations ..............................................4 10.1.5 Quality Assurance Consultants ............... ...............................5 10.1.6 Contractors ............................................. 5 10.2 Training the Environmental cell - PIU & PWD .6 | ~~~~~~~~~~~10.2.1 need fortraining ........................ .......................6 10.2.2 Targets of proposed Training .6 10. 2.3 Training Components ...........................................7 10.3 Reporting System .8 I10.4 Environmental Monitoring Plan .9 10.5 Environmental budget .10 I l l LIST OF ANNEXURES ANNEXURE-4.1 LIST OF LANDSLIDE LOCATIONS ALONG THE PHASE-I PROJECT ROUTES ANNEXURE-4.2 WATER QUALITY STANDARDS ANNEXURE-4.3 NATIONAL AMBIENT AIR QUALITY STANDARDS ANNEXURE-4.4 NATIONAL AMBIENT NOISE STANDARDS ANNEXURE-4.5 PLANT SPECIES HAVING ETHNOMEDICINAL IMPORTANCE ANNEXURE-4.6 MAJOR KINDS OF TREES/PLANTS REPORTED IN THE STATE ANNEXURE-4.7 NUMBER OF SEEDLINGS PLANTED ON THE GREEN MIZORAM DAY ON 1 1TH JUNE 1999 I ANNEXURE-4.8 MIZORAM AND ITS FORESTS ANNEXURE-4.9 CENSUS DATA OF MAJOR WILD ANIMALS OF PROTECTED AREAS ANNEXURE-4.10 CHECKLIST OF BIRDS OF MIZORAM ANNEXURE-4.11 IMPORTANT FLORA AND FAUNA REPORTED IN THE STATE * ANNEXURE-4.12 CENSUS DATA OF DAMPA WILDLIFE SANCTUARY ANNEXURE-4.13 VILLAGES ALONG THE PROJECT ROADS I ANNEXURE-4.14 DISTRICT-WISE MEDICAL INSTITUTIONS UNDER THE GOVT. OF MIZORAM I ANNEXURE-4.15 DETAILS OF MOTOR VEHICLE ACCIDENTS IN MIZORAM ANNEXURE-4. 16 MOTOR VEHICLE ACCIDENT REPORT 1999 | ANNEXURE-5.2 MIZORAM STATE ROADS PROJECT (WORLD BANK FUNDED) SOCIAL & ENVIRONMENT IMPACT ASSESSMENT - QUESTIONNAIRE ANNEXURE-5.13 NOTIFIED FORESTS OF MIZORAM ANNEXURE-7.1 METHODS OF RAIN WATER HARVESTING ANNEXURE-9.1 CONSTRUCTION METHODOLOGY ANNEXURE-9.2 GUIDELINES OF USE OF EXPLOSIVE AND BLASTING 3 ANNEXURE-9.3 GUIDELINES OF DEBRIS DISPOSAL l l I l LIST OF TABLES Table 1.1: Work Programme in MSRP Table 2.1: Relevant National Legislations Table 2.2: Relevant State Legislations Table 4.1: Climatic Zones of Mizoram Table 4.2: Climatic Features of Mizoram Table 4.3: Monthly Distribution of Rainfall (cm) Table 4.4: Maximum 1 Day Rainfall in Mizoram Table 4.5: Physiographic Setting of the Project Roads Table 4.6: Prominent Landslide Locations on the Project Roads Table 4.7: Quarries Identified for the Project I Table 4.8: List of Major Rivers in Mizoram Table 4.9: Physico-Chemical Characteristics of River Water Table 4.10: Air Quality Data Table 4.11: National (CPCB) Ambient Noise Level Standards I Table 4.12: Noise Level Table 4.13: Estimates of Forest Areas in Mizoram Table 4.14: Classification of Forests Table 4.15: Notified Forests in Mizoram Table 4.16: Forest Cover Change Matrix (1994-98) Table 4.17: Classification of the Forests of Mizoram Table 4.18: Rare & Endangered Plant Species in Mizoram Table 4.19: Medicinal Plants and Usage by Local People Table 4.20: Major Rare & Endangered Fauna Species of Mizoram Table 4.21: Wildlife Protected Areas In Mizoram Table 4.22: Census of Major Wild Animals in the Protected Areas I Table 4.23: State and District Population Table 4.24: Land Use Pattern in Mizoram Table 4.25: Traditional Gender Roles * Table 4.26: Settlements on the Project Roads Table 4.27: Growth in the Incidence of HIV/AIDS in Mizoram Table 5.1: Proposed Consultation Framework for MSRP Table 5.2: Public Consultation of the Preliminary Design Stage Table 6.1: Potential Impacts on water resources due to construction activities Table 6.2: Typical Noise Levels of Principal Construction Equipments Table 7.1: Summary of Results from Feasibility Study Table 7.2: Screening for Environmental Sensitivity Table 7.3: Comparison of Route Options Table 9.1 Format for EMP for Priority route Table 9.2: Format for ESMP to be prepared for Maintenance routes Table 9.3: Format for ESMP in case of unforeseen impacts at specific locations Table 9.4: Monitoring Plan format for EMPs and ESMP Table 10.1: Training Modules for Environmental Management Table 10.2: Desired Monitoring and Reporting Process and Responsibilities LIST OF FIGURES Figure-1.1: Project Roads I Figure-1.4: Typical Cross Section Proposed for the Priority Roads Figure 4.1: Landslide & Soil Erosion Figure 4.2: A Typical Landslide Figure 4.3: River Basins of Mizoram I Figure 4.4: Rivers of Mizoram Figure 4.5: Forest Cover of Mizoram Figures 4.6 & 4.7: Degradation of Forest After Jhum Cultivation Figure 4.8: Location of Medicinal Plants in Mizoram Figure 4.9: Map of Mizoram Showing Project Roads-Phase I in relation to Areas Protected for Wildlife Figure 7.1: Schematic View of Aizawl Bypass Alternatives I Figure 7.2: Option I - Panoramic View of Aizawl Bypass Figure 7.3: Option II - Bypass Passing Through Settlements l CHAPTER-1 | INTRODUCTION The Government of Mizoram, Public Works Department (MPWD) is taking up the Mizoram State Roads Project (MSRP) under a World Bank loan assistance programme (WB Loan I No. 4114 IN) available with the Government of India, for widening, strengthening and maintenance of state roads. Project Co-ordinating Consultants (PCC)' were engaged to assist the MPWD in project preparation and co-ordination. The project preparation activities, which included (a) Feasibility Study of the proposed investments, (b) detailed engineering designs, (c) environmental and social assessments, and (d) procurement I services began in 1998. A Sectoral Environmental Assessment was carried out as per the terms of reference of the PCC services, during and after the (economic, engineering, social) feasibility study of the project. I 1.1 PROJECT BACKGROUND I 1.1.1 LOCATION Mizoram is one of the seven north-eastern states of India. It has international borders with Bangladesh in the West and Myanmar in the east and south. It borders with the states of Manipur and Assam in the north and Tripura in the west. Mizoram is a land locked hilly state, and its transport infrastructure is essentially road based. Most of the state's road network of 6,808km is in a poor condition, and is in need of rehabilitation and upgrading. It is imperative that these roads are strengthened, their capacity augmented and geometrics improved so that these roads become safe, efficient I and economic for travel and meet the future demands. Transportation is currently a development bottleneck in the state, and the Government plans for enhancing economic | and social development hinges on the improvement of the transportation infrastructure. U 1.1.2 PROJECT IDENTIFICATION The project road network, and the proposed improvement originate from a Priority Investment Plan prepared for the network of state roads on the basis of economic, social I and environmental criteria. This Priority Investment Plan was an outcome of the Strategic Options Study (SOS) carried out during 1998-99. l PCC was a consortium of consulting firms, led by Intercontinental Consultants and Technocrats Pvt. Ltd., India (ICT) and Consulting Engineering Services (India) (CES) in association with Louis Berger International Inc., USA (LBII). Revised by Lea Associates 1-1 October 2001 I (Original Document by ICT. CES, LBII) A S S A M Kanhmu , ' |/ . Zohmet * ~~ * t l,~~~{3ilkhawtl-ir I ,jg~~~~ oi /gt'& 1 48} \, * < 3airabi - s 'olasib, 99~iark & I ) zinli~~~~~a HQrlok | I 8 37 Ra ; 9 , {KoH t \ , 11 / | 9 | \ | ~~~~Mitbung ' -TuiAP \ ^ |Iug , uags Vt39 :Khawuag r v ~~~~~~! tiweg / Shh4 ^ th g \ 0\; WN Kawnpui Li1T2 rn ; ) elI1 w -C| >X+1)if ~~~~ase@ p~ ~ ~ ng hb ,-elf ltrP r~~~~~~~~ia C &hlr+awierhi,Oh s \ | / 6 i + ! \ Ksitu g46 1 iits;a! ; 1;4rpara\!s i6 6tgdr@ 9 t ffi ' * \ { * .|.laiphai I VaX6 T8 labu ' 3j1 4 D. M! 1s 413 SQ K \ Xurogseri ~ ,.aSWi/ Borpanu \ 25,< M Sangaux i' cllwr ' 3 hnb;ungphar> \ @ g Di~~~~~ldangF 33tal Legend X s iikk t NSal~~~~~ ~ ~~~ha s Capita of Sbtate > S.E ngilangt- ~~~13 / ' itiHedure Z ~~~~~~41 3 Pnj~ect Prnonty Road Z- . ' Tuipang , CD 5/ ;834 33 Pmjoje Mamter anice Roads , \ Htf~Clh,n I6- M 12 _ 3*%jj; ¢Taw~~~P S rrh ipu\ 20g ;;_ . .*l;1 ) S48;argng } 4 Khawburg- .n1t -.;!t.;-- F--'' w s p j , -\ ' -s.t) l J ; I r FiUe48 octi of Me(fti-r 9_aAi MizorarS - / a\arha>vver~~~~~~~~~~~~S , S pht.,*c t _ c,, s: ''\\~~~~~~~' ; \^''4 s[4ang.I jjw n ' e d La w n gtI a \ & ? p 6 r I <~~~~~ &M 10 +- $9\*Lgn ) 1 S 3rir^;!arS ! 's f j a i !~~~~~IMeFttanece Rcacs -) I * M Ci,,P.frSIaie ?zads - 4- 1 upz rt mtea c n r t ~~~~t _ _ _ _ 1 _ _ F igure 4.8 L ocatioDn of M e irc ir\3 P\ X )ln M izoram Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions IiStt3 of Medicinal Plants is given in Annexure 4.5 (see also Figure 4.8, for geographic occurrence of these plants). Table 4.19 lists the more locally important medicinal plants and their geographic occurrence. Table 4.19: Medicinal Plants and Usage by Local People Medicinal Plants Locality Medicinal Plants Locality Adhatoda vasika Aizawl Adina cordifolia Champhai Agave americanna Aizawl and kolasib A/p/n/a galanga Thenzawl Alpin/a malacensis Lunglei Ammannia baccifera Lenglei Anogessus acuminate Zobawk and Aizawl Anthocephalus cadamba Khawzawl Ant/desma bunius Aizawl Arenga pinnata Mamit Ansto/ochia tagala Lunglei Averrhoa carombola Mamit Begonia rex Thenzawl Bergen/a ligulata Phawngpui Bombax ceiba Dampuib Buddleia asiatica Phawngpui Costus speciosus Aizawl Cucumis sat/rus Datura metal Lunglei Hedychium acuminaturm Hmuifang, mamit Homonoia rlpara Tlabung Hypericumjaponlcum Champhai L/nostoma decandrum Sialsuk Lonicera macranda Kawnpui Orthoslphon aristatus Zobawk Bergendia lingulata Pawngpui Sergendia lingulata Pawngpui Note: For a fuller list, see Annexure 5.5. * Bio-Diversity Conservation The entire North-East India"4 forms the transition zone between India, Indo-malayan and Indo-Chinese geographic regions and is one of India's global biodiversity "hotspots". Mizoram has significant areas of biological and ecological significance having gene pools of a variety of flora and fauna not found elsewhere. This has been recognised in the declaration of the ecologically sensitive and critical areas as protected areas and wildlife sanctuaries in the state; and the more important areas in the state are being protected/conserved. The total area protected as such is 7889km2, or about 37% of the total geographical area of the state. However, small areas of rich bio- diversity might remain outside the protected areas, and some of these might occur close to the project corridors. This will require investigation during subsequent EAs (and as such 3 has been undertaken for Phase I works). | 4.1.9 WILDLIFE Wild animals are becoming gradually scarce in Mizoram now. A census data of Wild 3 animals in different wildlife sanctuary is given in Table 4.22. 13 Source: Mr. Lalanundanga, Pachunga University, Aizawl. | 14 Consisting of the 7 states of Assam, Meghalaya, Arunachal Pradesh, Manipur, Nagaland, Tripura and Mizoram. Revised by Lea Associates 4-19 October 2001 (Original Document by ICT, CES, LBII) l Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions Game birds, which are seen in the less populated areas, include the Jungle Fowls (Grallus fevigineus), Hornbill Pheassants, Doves Pigeons. A detailed list of birds found in Mizoram is given in Annexure 4.10. Snakes are not so numerous. They seem to abound more in the south than in the north. Most of the snakes are non-poisonous. The information about important fauna species reported in the project area including major mammals, reptiles and birds species is presented in Annexure 4.11. * Rare & endangered Species The rare or endangered fauna species reported in the Mizoram are given in Table 4.20. Given that the rare species are protected within the wildlife sanctuaries or national parks, the likelihood of occurrence of these species close to the project roads are small. However, small habitats of rare or endangered fauna species might occur close to the project roads, and would require detailed examination during subsequent EAs (and as such has been completed for Phase I works). Table 4.20: Major Rare & Endangered Fauna Species of Mizoram Species Habitat On Project Speces Habitat On Project Species Requirements Roads Requirements Roads Presbytis geei Forest Unlikely Elephas maximus Hilly areas where bamboo Unlikely - ~~~~~~~~~~~~~~~~~~~~~~& tall grass abound Nysticebus coucang Tropical forest Unlikely o Subalusbuba/is Swampy grass jungles Unlikely H-fylobates hoolock Dense forest Unlikely > Bosgaurus Dense tropical forests Unlikely Neofeis nebulosa forest Unlikely I Caproagius Grass jungles Unlikely E Fe/is benga/ensis Jungle & wilderness Likely Ardeotis nignceps Forest Unlikely * Fe/is temmineki Dense forest Likely Grus nigncollis Natural vegetation Unlikely Fe/is vivervina Forest along steams/ Unlikely Cairina scutulata Natural vegetation Unlikely _ n~~~~~~~~~rver/ swamps 3Felis marrnorata Thick forest in cold Unlikely 'A bu c/r Natural vegetation [ Unlikely climate : ioo Arctlctis binturong Dense forest Likely Ana gibberiform Natural vegetation Unlikely ________ _______ I I__ _ _ _ _ _ _ _ salbogu/a n-s_ _ _ _ _ _ _ _ _ _ _ _ Note. This is only an inventory of major rare or endangered Megapod/um Natural vegetation U7likely fauna. Other rare or endangered fauna may exist In Mizoram. freyclnet . Wildlife Protection Areas About 4.2% of the geographic area of the state (884km2) hectare of the forest area constituting is under 2 National Parks and 4 Wildlife Sanctuaries (see Table 4.21). Table 4.21: Wildlife Protected Areas In Mizoram No Name of Sanctuary Protected Sanctuary Forest Types Area (kin2) Area (k Ss2) 1. Dampa Wildlife Sanctuary 500 500 Sub-tropical semi-evergreen | ~~~~~~2. Murlen Wildlife Sanctuary 200 150 Sub-tropical semi-evergreen & Sub-Montane 3. Blue Mountain Wildlife Sanctuary 50 50 Sub-montane & Tropical 4. Ngengpui Wildlife Sanctuary 110 110 Sub-tropical & Semi-evergreen 5. Lengteng Wildlife Sanctuary 120 80 Sub-montane 6. Khawnglung Wildlife Sanctuary 41 35 Sub-tropical & Semi-evergreen Revised by Lea Associates 4-20 October 2001 (Original Document by ICT, CES, LBII) S A ',I J/ er' 7 S:r,\l' J 66,' y f t \25 ' _h \ Sangau;, \ \sI # ~~~awipul t s ,A;wqrt X S nngp< tnpar; r I f D Itlan ; LaSrn9t,,,gIIa2 Legend M t. , I I | ~~~~~~~~~~~~~~~Natcril Hi,~Wvay G , vt \ S zTuipang,, | P~41 rcject PrcrLty Rcad uD te>>a&} 1 ] I S fl t ~~~~33 / 1 :c Marler'arerrce Rcads---| ,P3rva r X / t~~hcpai rerer30da .--1 ; s~~~~~ L3wnr;nneso J :r8e Slate 3vrc.,Cat- Figure 4.9: Map of Mizoram Showing Project Roads-Phase I in relation to Areas Protected for \WVildlife Mlzoram State Roads Project - Phase I SEA: 4 - Baseline Conditions The census of the wildlife sanctuaries are presented in the Table 4.22 below: Table 4.22: Census of Major Wild Animals in the Protected Areas No Name of Species Zoological Name Dampa TR Murlen NP Phawngpui NP Ngengpui WS 1997 1999 1997 1999 1997 1999 1997 1999 1 Tiger Panthera tigrls 5 - 1 1 1 2 2 I 2 Leopard Panthera pardus _ 3 - 4 4 5 3 4 3 Elephant Etephus maxfmus 4 - - - - 8 7 4 Indian Bison Bos gaurus 5 - - - - 15 3 I _5 Samber Cervus unicolor 42 - 12 22 2 40 8 6 Barking Deer Muntiacusmunyak 70 - 34 101 114 85 9 7 Serow Caprlcornissumatraensts 11 - 8 60 86 12 8 Goral Nemorhaedus goral 5- - 291 260 - 9 Wild pig Susscrofa 25 - 59 170 170 40 12 10 Himlayan Black Bear Se/enarctos tbetanus 3 - 2 22 15 1 1 11 Hoolock Gibbon Hy/obatesH oolock 15 - 18 8 12 22 13 12 Rhesus Macaque Macaca Mulatta 107 - 80 275 250 45 - 13 Common Langur Presbytis entellus 102 - 36 - 24 26 22 14 Leaf Monkey Presbytis phayrei 8 - - - - - - 15 Slow Loris Nyeticebuscoveang - 11 9 6 5 1 | A brief description of the 6 Wildlife Protection Areas is given in the following sub-sections. These areas support a number unique and precious species (note that these areas also support the more important flora in the state, and are the repositories of the bio- diversity). | Dampa Tiger Reserve Dampa Tiger Reserve is situated in the western part of Mizoram (on the International border with Bangladesh about 127km from Aizawl) extending 92013'12"-92027'27"E longitude and 23032'42"-23041'36"N latitude, at altitudes ranging between 200 and 1200m above the mean sea level (MSL). * The Tiger Reserve consists of moist deciduous forests at the lower reaches, and evergreen & semi- evergreen forests with natural grassland at higher altitudes. Dampa is the largest sanctuary of the state (notified in 1985 and was declared a Tiger Reserve in 1994). The virgin forests of Dampa tlang and Chhawrpial tlang are its unique natural features. Important fauna found are Tiger, Leopard, Elephant, Gaur (Indian Bison), Wild * Dog, Sambar, Barking Deer, Sloth Beer, Hoolock gibbon, Leaf Monkey, Common Langur, Rhesus Macaque, Giant Squirrel, Porcupine, Slow Loris, Jungle Cat, Wild Boar, etc., and varieties of Birds (see Annexure 4.12). There are 10 villages around the Tiger Reserve, with a population of roughly 10,000 3 (Mizo, Chakma and Riang tribes) who practice jhum cultivation. The Tiger Reserve is managed by a Field Director at headquarter (W. Phaileng), two Range Officers (at Teirei and Phuldungsei) and ten Wildlife Beats. The project road M3 passes close but is outside the boundary of the sanctuary/reserve. Revised by Lea Associates 4-21 October 2001 (Original Document by ICT, CES, LBII) Mlzoram State Roads Project - Phase I SEA: 4 - Baseline Conditions Murlen National Park Murlen National Park is situated about 245km east of Aizawl, extending 23032'-23042'N latitude and 92013'-92°27'E longitude in altitude ranges of 400 to 1900m above MSL. This I park lies close to the India-Myanmar border, and is significant due to its proximity to the Chin Hills. Large tracts of relatively undisturbed sub-tropical evergreen/ sub-montane forests are found in this park. Important wild animals and birds found in this park are Tiger, Leopard, Himalayan Black Bear, Hoolock Gibbon, Sambar, Barking Deer, Ghoral, Serrow, Rhesus Macaque, Wild Boar, Hume's Bartailed Pheasant, Kaleej Pheasant and many varieties of Orchids. There are 5 villages around the park with a population of 4000, and one village (Murlen with 70 families) is situated inside the park in the core area. Relocation of Murlen Village outside the park is under process. A Range Officer (located at N. Khawbung) and 4 Beat | Officers manage the Park. The Project Road Ml passes close, but is beyond the boundary of the Park. 1 . Phawngpui (Blue Mountain) National Park Phawngpui National Park is situated in south-east Mizoram at 22039'N latitude and I 93°02'E longitute adjacent to Myanmar. The highest Peak of Mizoram, the Phawngpui (2360m) is located within this park. The general forest type in the park is montane sub- tropical. Though not substantial, some Oak dominated primary forest patches are still available in certain parts of the park and are separated by secondary growth in various stages. * The important wild animals and birds found in this Park are Ghoral, Serrow, Barking Deer, Sambar, Leopard, Blyth's Tragopan, Kaleej Pheasant, Hoolock Gibbon, Common Langur, Rhesus Macaque, Stump Tailed Macaque and a variety of Birds and Orchids. Five villages surround the Park, and have a population of 3500, practicing Jhum cultivation, which is a fire hazard in this Park. Range Officer (at Sangau) and 5 Beat Officers manage the Park. | Ngengpui Wildlife Sanctuary The Ngengpui Wildlife Sanctuary is situated in south-west Mizoram at 92045'- 92050'E 3 longitude and 22°21-22030'N latitude in altitude ranges 200 to 1200m above MSL. It is close to the India-Myanmar and India-Bangladesh borders. Virgin sub-tropical/evergreen/ semi-evergreen forests are found in the Sanctuary. The wild animals found are Tiger, I Clouded Leopard, Elephant, Gaur, Barking Deer, Sambar, Wild Boar, Hoolock Gibbon, Rhesus Macaque, Leaf Monkey, Common Langur, etc. 3 Seven tribal villages surround the sanctuary. A Range Officer (at Ngenpui) and 5 Beat Officers manage the Sanctuary. Revised by Lea Associates 4-22 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions . Lengteng Wildlife Sanctuary Lengteng Wildlife Sanctuary is situated in eastern Mizoram adjacent to the Murlen National Park. This area was recently (1999) notified by the State Government. The I altitude ranges are between 400 and 2300m above MSL, and the Sanctuary has second highest Peak in Mizoram. In the eastern side of the Sanctuary, large tracts of virgin sub- tropical evergreen and sub-montane forests are found. The important wild animals and birds found are Tiger, Leopard, Sambar, Barking Deer, Ghoral, Serrow, Hume's Bartailed Pheasant, Kaleej Pheasant, Hoolock Gibbon, Rhesus Macaque, Wild Boars, etc. The I Sanctuary is (temporarily) managed by a Range Officer. At its nearest point, the Project Road Ml is 4km away from the Sanctuary. Khawnglung Wildlife Sanctuary Khawnglung Wildlife Sanctuary is situated 170km from Aizawl, in Central Mizoram at 92°55'-92°59'E longitude and 23004'-23010'N latitude in altitude ranges of 400-1300m above MSL. Sub-tropical and semi-evergreen forests are found in the Sanctuary and the common wildlife include Leopard, Barking Deer, Sambar, Hoolock Gibbon, Wild Boar, etc. In 1997 a Tiger was reported in the Protected Area. | The Project Road M4 passes nearby the Sanctuary but outside the boundary. | 4.2 SOCIO-ECONOMIC ENVIRONMENT Mizoram is one of the most backward states in the country. The hilly terrain and the lack of accessibility, lack of any major development initiative are the possible reasons. With the majority of its people living in a poor condition, and a heavy dependence on primitive hill agriculture jhuming), Mizoram does not have any major industries or sources of employment15. However, the state has good potential for economic development, particularly if alternative and intensive methods are introduced (in agriculture, horticulture, tourism, handicrafts, etc.). The lack of an adequate transport infrastructure has been a major inhibiting factor for development of the state. As part of the project, social impact assessment has been carried out. Detailed data and analysis from the social assessment is part of the R&IPDP Report. The major issues discussed in the R&IPDP report are the following: I . Poverty & Poverty Alleviation Programmes * Alternative Livelihood Programmes . Gender Issues * HIV/AIDS Issues In the following sub-sections, the socio-economic parameters are discussed in brief. For detailed analysis, refer the R&IPDP Report. IS Governments, State & Union, are the only significant employers in the formal sector. Revised by Lea Associates 4-23 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions I 4.2.1 DEMOGRAPHIC PROFILE The state has a population of 891,058 persons (as per the provisional census of India) in 2001. District wise population, density and growth rate of the state is shown in Table 4.23. The state has a relatively low population density of 42 persons/km2. Aizawl is the most populated district, followed by Kolasib, which is growing at a fast rate. During 1991-2001, population in Mizoram grew faster than the all India average. However, the growth rate of population in Mizoram during 1991-2001 was lower than the earlier decades. Kolasib, nonetheless, grew at higher rate than the earlier decades, whereas District Mamit recorded negative growth rate during 1991-2001. Table 4.23: State and District Population State/District Population 2001 (No.) Decadal Growth Rate (%) Gender Ratio Density (person/kM2) Persons Males Females 1981-91 1991-01 1991 2001 1991 2001 Mamit 62,313 32,766 29,547 23.57 (-)3.50 891 902 21 21 Kolasib 60,977 31,874 29,103 26.82 36.01 924 938 32 44 Aizawl 339,812 173,930 165,882 57.23 39.24 917 913 68 95 Champhal 101,389 51,869 49,520 32.31 29.77 969 954 25 32 Serchhip 55,539 28,445 27,094 20.36 18.45 959 955 33 39 Lunglei 137,155 71,353 65,802 28.79 23.10 910 953 25 30 Lawgtla; 73,050 38,425 34,625 52.68 34.78 885 922 21 29 Saiha 60,823 31,121 29,702 47.72 33.16 939 901 33 43 Mizoram 891,058 459,783 431,275 39.70 29.18 921 938 33 42 Source: Census of India, 2001 4.2.2 LAND UTILISATION A completely mountainous state with rich bio-diversity, the forest area of the State is 18775km2, constituting about 89% of the total geographic area. The unclassified forestlands (70% of the total forests) are controlled by the Village Councils. While the I Village Councils reserve parts of these forests as Safety and/or Supply Reserves, the rest of the unclassified forests is allotted to the villagers for carrying out jhum cultivation. | The land utilisation pattern in the state is presented in Table 4.24. Net sown areas account for only 5% of the total geographical area. Double cropping is almost absent. Table 4.24: Land Use Pattern in Mizoram Land Use Area (km2) / of Total Area Forests 15985 76 Barren and Unculturable Land 646.2 3 Culturable Waste 1739.5 8 Fallow Lands 1628.1 8 Net sown area 1088.1 5 Total Area 21086.9 100 Source: Statistical Abstract, Department of Agriculture & Minor Irrigation, Mizoram, 1997-98 Revised by Lea Associates 4-24 October 2001 (Original Document by ICT, CES, LBII) Mlioram State Roads Project - Phase I SEA: 4 - Baseline Conditions Gender Relations Certain gender roles are firmly established by tradition, while others are more fluid. All tasks involved in the jhum cycle are either done jointly or by women alone (refer Table * 4.25). Table 4.25: Traditional Gender Roles Activity Sub-Activity Responsibility In Jhum Activities Site selection Assigned by draw of lots to male head of family Clearing forest Cutting of large trees of men; other work jointly Burning Jointly of men and women Sowing Jointly of family or by women Weeding Mainly of women Protection Of family groups/ young men * Harvesting Jointly of men and women Storing Small storage by women I . Celebration Jointly of men and women In Domestic & Other Collecting water Of young men or women Activities Collecting fuel Of young men sometimes women Cooking Of women C Home gardening Of women Animal husbandry Of women The petty trade is completely controlled by women, whether in the vegetable market in Aizawl or in small rural markets. Women run all small roadside shops. Overall, women students are doing well, but education and subsequent work opportunities are highly gendered. The highest number of graduates in the state is from the faculty of * home-science, a discipline wholly meant for women students. Apart from conventional professions like teaching and nursing, women are seen in professions like medicine, pharmacology, agriculture, and even police. However, even with the liberal acceptance of pre-marital relations and unwed mothers; the visibility of women in the economic life; their freedom of movement and control of local markets; and good literacy status, gender discrimination is traceable in Mizoram. Mizoram is a patriarchal society, patrilineal and patrilocal. Tribal tradition and 'customary * laws', which are still legally binding in Mizoram, have assigned women a subordinate status. Mizo women have no right to property. Women are consulted, but are not Revised by Lea Associates 4-25 October 2001 (Original Document by ICT, CES, LBII) I 3 ~~Mizoram State Roads Project - Ph7ase I SEA: 4 - Baseline Conditions decision-makers. There are some women in the elected Village Councils, but none in the State Legislature. I 4.2.3 SETTLEMENTS There are 21 towns and 1 City (Aizawl), which accounts for 46% of the population of the state. Though the urban population of 46% is higher than that of the national average of 26%, it is due to the Aizawl City, which accounts for more than half the urban population. The Project Roads pass through a large number of small and big villages and towns (see I Table 4.26: a list of these settlements is also given in Annexure 4.13). All these settlements will be ultimately benefited, socially and economically by the project. I Table 4.26: Settlements on the Project Roads Phase I Phase II Work Road Districts Settlements Road Districts Settlements Traversed Number No./10km Traversed Number No./10km i Improvement Aizawl, PiB Sherchhip, 13 1.83 * Works P1A Sherchhip Lunglei Ml Charnphai 8 0.83 M4 Champhai, 5 .9 M2 Mamit 8 0.88 Major M4 Sherchhip 5 109 M Maintenance M5 Lunglei, 6 1.26 M6 Lunglei 5 1.61 Works M5 Chhimtuipui (W) M7 Mamit, Aizawl 4 1.33 Mis Sherchhip - M9 Champhai 6 0.80 M16 Aizawl | 4.2.4 ECONOMY * Agriculture The economy of the state is mainly agriculture based. Principal crops grown are rice, I maize, pulse and oilseeds, vegetables, fruit crops, sugarcane, tea, coffee, and spices. The scope of medium irrigation is limited due to terrain. There, however, are some minor irrigation projects and some more are proposed. Potential areas for development of settled agriculture, horticulture, and tea/coffee/rubber plantations are shown in Figure 4.8 and 4.9 respectively. * Industries The state is industrially under-developed. Only a few small-scale cottage and forest-based industries exist in the state (see Figure 4.10). The Government of Mizoram has set up a number of specialized agencies to promote various development activities in the field of I industry. Prominent among these are Zoram Industrial Development Corporation Limited (ZIDCO), Mizoram Khadi and Village Industries Board (MKVIB), Zoram Electronic Development Corporation (ZENICS), and Mizoram Food and Allied Industries Corporation (MIFCO). Revised by Lea Associates 4-26 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions Two industrial estates have been set up at Aizawl and Kolasib. Industrial Complexes are I also being set up in Zuangtui Industrial Estate Area, Aizawl. Other important growth centres are Bairabi, Serchhip, Champhai, Sairang, Vairengte, Chhingchhip, Saitual, Thenzawl, Hnahthial, Lunglei, etc. . Tourism * The state is endowed with scenic beauty, temperate climate, rich flora and fauna besides tribal art and culture. It has 1 Tiger Reserve, 2 National Parks and 3 Wildlife Sanctuaries. These hold good potential for development of tourism. The main bottleneck for encouragement of tourist inflow is the lack of efficient transport and communication system and modern tourist infrastructure. The State Government has planned to open to I tourists the following recreational centres: * Berawtland (Near Aizawl) * Tamdil Lake (A natural lake about 87km from Aizawl) * Reiek Tland (Reiek hill for climbing, trekking) Other associated developments are also being planned. It is suggested that a proper road linkage to the places of tourist interest be developed on a priority basis to augment the inflow of tourists to the state. 4.2.5 HEALTH The major diseases reported in the state of Mizoram are malaria, gastroenteritis, bronchitis, amoetraisi dysentery, etc. HIV/AIDS is an issue of great concern in Mizoram. * Health Care Facilities Health care is provided through various hospitals and health centres located in different districts of Mizoram. In all there are 7 General Hospitals, 7 Community Health Centres, 43 Primary Health Centres and 13 Subsidiary Health Centre where medical aid and treatment is available for the local residents. The district wise details of the hospitals and health centres are given in Annexure 4.14. | . ~HIV/AIDS Mizoram, due to its geographical location is vulnerable to HIV/AIDS. It is bordered by Myanmar (which is seen as the epicentre of the HIV epidemic in Asia), and Manipur I (which is the epicentre of IDU related HIV infection in India). Further, Myanmar and Thailand that are part of the 'Golden Triangle' supply opium to other destinations through Mizoram. Enforcements and interceptions by the police and other drug traffic prevention agencies have not been very effective. The state has prohibited consumption of alcohol, u but unlawful alcohol supply is available in all parts of Mizoram. Since 1990 October onwards the Health Department and ICMR (Kolkata) have been conducting periodic blood tests to establish the incidence of HIV/AIDS in Mizoram. The Revised by Lea Associates 4-27 October 2001 * (Original Document by ICT, CES, LBII) 3 Mlizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions results are shown in Table 4.27. The health department/ICMR data is supplemented by I the test and survey records16 at the Civil Hospital (Aizawl) since 1990. 3 Table 4.27: Growth in the Incidence of HIV/AIDS in Mizoram l~~~~~~~~~~~~~C 0, at 0, ct xX m C, C% ClC Particulars - _ _ I a ,o Xoz S ,> o > Ss > ti; > tit> a > - 0.) IU I .0-1 B Z .2:~~~~~~~~0 l Injecting Drug Users 1D39 166 11 180 4 263 13 125 6 110 3 57 7 99 4 STD/ CSW 311 292 4 130 - 277 4 170 3 151 6 225 16 287 221 l Blood Donors 6 1-2520 -2747 3 4435 2 4433 Sl570 -4715 -8468 - Others (Volunteers, - - - - 4 3 - - 233 2 4 2 257 l ~Others 24- 316 - 9 - 202 - 7 - - - 102 - - Total 164 9 3294 15 3066 7 5181 22 4375 9 5664 9 5103 25 9111S 26 1 ~~ACET/EHA'7 survey amongst IDUs (2206) reveals that 73.79%/ are using Proxyvon (propoxyphene), which is peculiar to Mizoram. The survey also established that in the | ~~~sample, 1,929 of the 2,206 classified themselves as unemployed youth (whether the same people are school dropouts has to be clarified). The survey found that there are about w ~~900 commercial sex workers (CSWs) in Mizoram. The majority of them come from poor I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~V w ~~~and/or broken families and a number of them are divorcees. 1 ~~As the sexual partners of the IDUs in Mizoram could be high risk groups, the rate of I transmission to the general population is anticipated to be very high. Although specific data on the high-risk behaviour of the sexual partners of the IDUs in Mizoram is not | ~~~available, the following suggest that the high-risk group might be abundant. . There are already about 900 commercial sex workers in Mizoram, which has a total _ ~~~~~population below 900,000. These commercial sex workers (although their clientele consists || of people from outside the state) themselves are at a very high risk of contacting HIV, and pass on to the general population. * The IDUs in Mizoram are reported to have multiple sexual partners. About 50% of the | ~~~~~IDUs have multiple sexual partners (including commercial sex workers, but also including I~~~~~~~~~~~~~~~~~ - ~~~~~casual and/or non-commercial sex partners). As free sex is not a big social taboo in Mizoram, the risk of spreading HIV from the IDUs is high. I . Though most of the IDUs in Mizoram are male, injecting drug use among women is widely w ~~~~~~reported. Therefore, the increase in sero-positivity among the children is a high risk. 16 The Civil Hospital started the HIV tests and the periodic surveys from 1990. The hospital keeps records in | ~~~~~an appreciable manner, and also documents the findings, periodically. '7 EHA/ACET run a project called SHALOM in Mizoram to extend support for intravenous drug users. | Revised by Lea Associates 4-28 October 2001 I ~ ~~(Original Document by ICT, CES, LBII) Otes(outes 3 5 l Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions Assortative mixing among IDUs is there, but most of the sexual partners of the IDUs are non-IDUs themselves. Although awareness among the IDUs is relatively high, awareness among the sexual partners of the IDUs is low. These non-IDU partners include (predominantly male) population originating from outside the state (mostly the highway- users), many of who are reported to be totally ignorant about HIV/AIDS. There is a trend that many people from outside the state (Myanmar, Bangladesh, and districts of Assam and other north-eastern states) are settling down in Mizoram, the number of high-risk group population is increasing. 4.2.6 ROAD SAFETY The passenger vehicles (buses, cars, jeeps, two-wheelers) constitute more than 80% of the total vehicle population in Mizoram. Amongst the passenger vehicles, cars, jeeps, etc. represent the highest share of passenger transport with buses representing only a small proportion, which is less than 5%. Except for a few handcarts noticed at some locations, the slow moving vehicles do not exist. * Number of accidents on the roads in Mizoram, resulting in serious injuries and fatal casualties of the travelling public, are reported every year. Majority of these accidents occur by rolling down the road. This can be attributed to the poor geometry of the roads, which pass through hilly terrain and negotiate sharp curves and bends. The cause of the accidents, however, is reported to be mainly the negligence of drivers. The details of accident data for Mizoram are given in Annexures 4.15 and 4.16. 4.3 BASELINE OF THE PROJECT ROADS This section presents a description of each of the roads that have been selected for the project. The description is based data available from secondary sources and site visits. These have been supplemented by the information obtained from the field visits during the EA for the phase I. I 4.3.1 IMPROVEMENT/UPGRADATION ROADS . PIA Aizawl-Thenzawl-Buangpui Road This road section is the first 100km of Aizawl-Lunglei road. The design length of this project road, however, works out to be 98.712km. The road follows the existing alignment of the road for Aizawl-Damdiai, and Sialsuk-Thenzawl-Buangpui sections. The Damdiai- Sialsuk section follows the existing narrower road via Hmuifang. Geographically, the project road PIA can be divided into the following three sections. I * Aizawl - Damdiai 35km * Damdiai - Sialsuk via Hmuifang 30km * Sialsuk - Thenzawl - Buangpui 35krn The sections between Aizawl-Damdiai, and Sialsuk-Thenzawl-Buangpui follow the natural contours of the hills with generally steep slopes, both on the hill and valley sides. These slopes are prone to landslides during rains. The road sections have 3.5m paved Revised by Lea Associates 4-29 October 2001 (Original Document by [CT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions carriageway with a formation width of about 5m. The road shoulders either do not exist or * are in very poor condition. The provision for road drainage is very inadequate. The condition of pavement is generally bad. Ruts, potholes, and cracks are noticed almost everywhere. At places the pavement has completely failed. Some areas south of Thenzawl are low lying and prone to floods. These areas are mainly used for paddy cultivation. The roads in these areas will have to be built on raised formation with adequate provision for drainage. The project road section between Damdiai-Sialsuk follows the eastern route via Hmuifang. This route passes through five villages, namely, Lungsai, Thiak, Sumsuih, Hmuifang and Chamring, and is also known as the "Five Villages Road". It is an unpaved jeepable road without shoulders and with no proper arrangements for drainage. The formation width does not generally exceed 4m. The road follows generally the natural contours of the hills with generally steep slopes on the hillside and deep gorges on the valley side. These slopes are not only prone to landslides in rains, but with the bad geometry of sharp curves and steep gradients, make travel on these roads unsafe and | dangerous. The road traverses over the hills and flattens at the top to gently rolling ground covered with lush green grass. It continues towards south traversing over beautiful hill ranges and descends into a valley that ends at Sialsuk. With a beautiful scenic view to the west, clean air and a generally salubrious climate, the route offers potential for developing tourism I around the area. The project road crosses rivers Char and Vanva at km88.171 and km97.055 respectively. The existing 12.2m long slab concrete bridge at Char is proposed to be widened and the 24.4m long steel bridge on Vanva requires reconstruction. . P1B Buangpui- Lunglei Road This road is 71km long and has been selected under phase II. It connects the urban areas of Haulong and Lunglei. The road link can be divided into the following sections. 0 Buangpui - Haulong 32km . Haulong - Lunglei 39km The road passes through hilly terrain with generally unprotected steep slopes on both hill and valley sides. On the hillside the cut slopes vary in height from about 5 to 30m, with I average height of about 10m. On the valley side also, the generally precipitous slopes extend to very large depths. These steep and high slopes, which are prone to landslides during rains, together with sharp curves and steep gradients make travel on this road very unsafe. The carriageway width of the road varies from 2.8 to 4m, with an average of 3m. The road shoulders exist at some locations, but are in a very bad condition. The formation width varies from 3 to 5.5m, with an average of 4.5m. The riding quality of the pavement Revised by Lea Associates 4-30 October 2001 (Original Document by ICT, CES, LBII) U Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions is very poor. It is acutely distressed with ruts, potholes, cracks and even complete failure at many places. Except for shallow earth drains in some areas, the provision of road drainage is generally I inadequate. About 200 slab and pipe culverts are provided on this road at locations of hillside seepage, waterfalls, etc. The road crosses river Tlawng at km150.300. The existing steel bridge, 42.7m long, will require reconstruction. * BP1 Aizawl Bypass In order to enable through traffic of NH-54 at Aizawl to use the shorter route along the | proposed Aizawl-Thenzawl-Lunglei project road P1 (171 km) a link bypassing Aizawl is proposed between NH-54 and the project road P1 near Aizawl. This bypass will take off from NH-54 at Zemabawk and join the project road P1 at km4.5. The length of the bypass is about 16km. It will entail construction of some cross drainage works, like culverts and a bridge, about 25m long, across river Chite. A couple of quarries I are located in the vicinity of the proposed bypass. The bypass alignment would also pass through a forest plantation. 4.3.2 MAJOR MAINTENANCE ROADS | * MI Kawlkulh-Ngopa-Tuivai Road This road, 96.625km long starts from the junction at Kawlkulh and ends at Tuivai river crossing. In between it connects villages Kawlkulh, Tawitawkawn, Hliapui, NE Bualpui, Pawlrang, Ngopa, NE Khawdungsei and Khawkawn. It is a bituminous road with an average pavement width of 3.15m with no proper arrangements for the roadside drainage. The formation is about 5.5m. Except for a short stretch between km43.5 to km43.75, which is affected by a major slip in the area, the riding quality of the pavement upto Ngopa is generally fair and can be considered even good beyond Ngopa. The road passes through hilly terrain negotiating steep gradients, unstable slopes and sharp curves. There is a major steel bridge, 30m long, across river Tuiphal and another steel bridge across river Tuivai is under construction. More than 400 culverts are constructed on this road. Many of these culverts are in need of repair. About 112 more 1 culverts are proposed to be constructed to improve the cross drainage of this road. A stone quarry is located along the road at km25.7. . M2 Zamuang-Tuilutkawn Road The road starts from the Zamuang on Bairabi-Zamuang-Kanhmun road, and ends at I junction of West Phaileng and West Kawnpui roads. It has a length of 60.44km and connects villages Rengdil (km3.78), Kwarthah (km12.4), Tuidam (km23), Kawrtethawveng | (km3l.47), W Bunghmun (km4l.1) and Serhmun (km48.7). Revised by Lea Associates 4-31 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions The road passes through hilly terrain negotiating steep gradients and unstable slopes at many locations. Major landslides have been reported to occur at km38.6 and near the site of stone quarry at km33.3. It is a bituminous road with an average pavement width of 3.5m and average formation width of 4.4m. The condition of pavement is poor. Ruts, cracks, edge failure and other forms of pavement distress are seen at many places. At some locations, e.g., km5O.9 to km6O.4, the pavement has completely failed. There is no provision for roadside drainage. The existing cross drainage system, consisting of 267 culverts, is not adequate and additional 164 culverts need be constructed. There are no 3 bridges on this road. M4 Keitum-N. Vanlaiphai Road This road takes off from NH-54 at Keitum and after passing through villages Tuichang (km6.8), Khawlailung (kml6.6) and Chekawn (km24.7), ends at N Vanlaiphai. The length is 45.78km. It passes through a hilly terrain with varying hydrological and topographical features. The alignment cuts through ridges and valleys with gradients varying from steep as in km1l.7 to kml2, to gently rolling as in km43 to km44.3. The hill slopes are unstable with many potential landslide sites along the road. At places, as at km4O.9, the road formation has 3 considerably sunk because of the landslides. It is a bituminous road with an average carriageway width of 3.3m and formation width of 4.3m. The condition of the pavement is poor. Ruts, cracks, edge shear failure, sub-base/sub-grade failure and other forms of pavement distress are noticeable. Some portions of the road are water logged. There is no arrangement for roadside drainage and the provision for cross drainage is also not adequate. There are 180 existing culverts, most of which are in need of repair. Sixty-eight new culverts need to be constructed to improve the cross drainage. There is one major steel bridge with wooden wheel track, 60m long, across river Tuichang at km6.1. This bridge needs repair. | . M5 Lungsen-Chawngte Road This road takes off from Lunglei-Tlabung road at Lungsen. After passing through villages Rangte (km6), Lalnutui (km22.2), Lungrang (km28.7), and Rualalung (km37.7) it ends at Chawngte. The length is 47.67km. It passes through hilly terrain negotiating steep gradients and sharp curves at many places. The formation has subsided at many places. I The road has a bituminous surface with an average carriageway width of 3m and formation width of 4.5m. The condition of the pavement is very poor. Ruts, edge shear failure, sub-base / subgrade failure and other forms of pavement distress are noticeable. Some portions of the road are water logged. The existing arrangement for roadside drainage is very poor. The provision for cross drainage is also not adequate. There are I 188 existing culverts, most of which are in need of repair. About 90 new culverts will have to be constructed to improve cross drainage. There are no bridges on this road. Revised by Lea Associates 4-32 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions . M6 Zobawk-Haulong Road This road takes off from Aizawl-Lunglei Project Road (Pl) at Haulong and meets NH-54 at Zobawk. It connects villages Zotui (km9.7), Chengpui (kml3.7) and Ralvawng (km22). a The length of the road is 31km. It passes through hilly terrain negotiating steep gradients and sharp curves at many places. It is an earthen road, except for about first 800m bituminous surfaced section, which is ravelled, and in poor condition. The average formation width is 4.2m. The existing arrangement for roadside drainage is very poor. The provision for cross drainage is also not adequate. There are only 25 existing culverts, I most of which are in need of repair. Ninety-five new culverts are required to improve the cross drainage. There are no bridges on this road. . M7 Damdiai-Sialsuk This road represents Damdiai-Sialsuk section of the existing alignment of Aizawl-Lunglei | State Highway via Samiukhai. It is a 30.1km long road negotiating steep gradients, sharp curves and unstable slopes prone to landslides. The road sections between km41.7 to km4l.72, km56.8 to km56.92 and near km6l.88 are reported to be potential landslide sites. The road has a bituminous surface with an average carriageway width of 3.2m and formation width of 5.5m. The condition of the pavement is generally poor. Ruts, edge shear failure and other forms of pavement distress are noticeable at many locations. The provision for roadside drainage is not adequate. At many places the landslides have blocked the side drains. The provision for cross drainage is also not very adequate. There are 138 existing culverts, most of which are in need of repair. About 50 new culverts will have to be constructed to improve cross drainage. One major steel bridge, 24.4m long, across river Changte at km46.5km needs repair. M9 Khawzawl-East Lungdar Road This road takes off from Seling-Champhai BRTF road at Khawzawl and ends at E Lungdar in the south. It connects villages Chawngtlai (kmlO), Khawhai (km3O.2), Sialhawk (km48.1), and Biate (km57.3). It is a 75km long hilly road negotiating steep gradients, sharp curves and unstable hill slopes. The road has a bituminous pavement with an average formation width of 4.5m. The condition of the pavement is poor with nearly the I whole of the section between Biate and E Lungdar, completely ravelled. There is no proper arrangement for roadside drainage. At many places the landslides have silted and blocked the side drains. The provision for cross drainage is also not adequate and needs improvement. There are 346 existing culverts, many of which are in need of repair. More than 300 new culverts will have to be constructed to improve cross drainage. There are no bridges on this road. | MIS Serchhip - Thenzawl - Thenhlum This road with a length of 105km starts from the town of Serchhip and ends at Thenhlum. Enroute it passes through the town of Thenzawl. Presently it is maintained by the Border Roads Task Force (BRTF). The condition of the pavement is fair. It has been recently Revised by Lea Associates 4-33 October 2001 (Original Document by [CT, CES, LBII) l Mizoram State Roads Project - Phase I SEA: 4 - Baseline Conditions included in the project under the package of major maintenance roads, Phase II. A I ~ ~~detailed study will be carried out during Phase II. l l l l I l I l l I |Ieie yLaAscae -4Otbr20 I~ ~~(rgnlDcmetb C,CS BI l l U CHAPTER-5 PUBLIC CONSULTATION As part of the project preparation, to ensure that the community support is obtained and the project supports the felt needs of the people, public consultations was carried out as an integral component. A continuous involvement of the stakeholders and the affected community was obtained. This chapter presents the approach and content to the public consultation programme in the project, during the SEA stage. This chapter also describes the results from consultation during SEA, which formed input to consultation during the subsequent EAs. I 5.1 NEED The WB OP/BP/GP 4.01: Environmental Assessment requires that affected groups and | nongovernmental organisations be consulted as part of the Environmental assessments of the project (particularly those with potentially significant impacts). People affected by the project are those living and working along the corridor and include businessmen, residents, farmers, agricultural workers, squatters and encroachers etc. Some religious and cultural properties within the area of impact may need relocation where consultations prove to be an effective tool in avoiding tension within the community. I 5.2 OBJECTIVES The objectives of Public consultation as part of this project are: 1 . Improve understanding of the potential impacts of proposed projects; * Identify alternative sites or designs, and mitigation measures; a To improve environmental and social soundness; * Clarify values and trade-offs associated with these different alternatives; * Identify contentious issues; | Establish transparent procedures for carrying out proposed projects; and * Create accountability and sense of local ownership during project implementation. 5.3 SCOPING WORKSHOP The purpose of public consultation at the SEA stage was aimed at information dissemination and finding out people's perceptions to the project improvements and to the resultant direct and indirect effects. This helped in providing an overview of the socio- economic and environmental issues for the roadside community. Revised by Lea Associates 5-1 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 5 - Public Consultation Information dissemination was a necessary precondition for consultation and participation. In order for meaningful consultations to take place between the project and the affected groups and local NGOs, the project provide disseminated all relevant information prior to consultations. For the first round of consultations the information included a summary of the project description and objectives, and the negative potential negative impacts from the proposed project. State level consultations were held through a Stakeholders Workshop (The Road Show) at Aizawl in the month of July 1999. This workshop 3 ~~was attended by the prominent personalities from the state. The Chief Minister also attended and addressed this workshop. The other participants included the PAPs, the PWD officials, the Project Coordinating Consultants (PCC) and Photo-plate 5.1: View of Mizoram State Road Show officials from the Revenue Department. (see Figure 5.1) The list of participants in the workshop is given in Annexure 5.1. The basic objective of this workshop was to build awareness about the project among the people, district level administration, Non-Government Organizations (NGOs) and to obtain their suggestions and ideas about the implementation of the project. 5.3.1 IDENTIFICATION OF ISSUES Based on the scooping workshop and understanding of the project area the issues to be raised during further consultations during detailed Environmental Impact Assessment and Resettlement Action Plan were identified. These issues identified were: * Air Quality; | . Noise levels; * Water pollution | . Relocation of water harvesting Structures . Drinking water sources, water scarcity in non-monsoon months, construction water requirements * Roadside trees, Forest Products, endangered flora and Fauna | . Health issues, Such as water borne diseases / HIV / STD * Possession of skills and the training needs I * Employment opportunity during civil works Revised by Lea Associates 5-2 October 2001 (Original Document by ICT, CES, LBII) 3 Mizoram State Roads Project - Phase I SEA: 5 - Public Consultation 1 * Location of labour camp and hot mix plant sites * Location of dumping sites | * Safety issues * Involvement of PAPs in Rehabilitation and Resettlement Plans 3 * Impact on property and land acquisition * Resettlement Options * Enhancement of common property resources . Extension of Government Welfare schemes 5.3.2 IDENTIFICATION OF STAKEHOLDERS | An initial list of stakeholders were prepared while carrying out analysis of alternatives, identification of specific issues, and preparation of initial mitigation and management plans as follows: Directly affected People o People losing assets o People losing employment o Community affected due to loss of common property, such as graveyards, churches, water harvesting structures, etc. 3 * Indirectly affected people o Roadside villagers prone to air and noise pollution, accidents, communicable diseases, etc. o Villagers deriving products from the roadside vegetation such as timber, wild fruits, medicinal plants etc. o Villagers loosing access * Organisations having local knowledge to contribute o Village Councils (or the Presidents of Village Councils) | o NGO's such as YMA, MHIP etc. a Religious institutions (or Churches) | o Mizoram Khadi and Village Industries c Horticulture Department | o Department of Minor irrigation and Agriculture o Mizoram Handloom and Handicraft Development Corporation Revised by Lea Associates 5-3 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 5 - Public Consultation . Agencies might need to be responsible for impact management o Village Councils o Revenue Department o Department of Forest | o State Pollution Control Board o NGOs o Pachunga University, Aizawl and other Educational Institutions I 5.3.3 LOCATION SPECIFIC CONSULTATION NEEDS Several project road specific consultation needs identified at scoping stage were: a Where widening is involved, the encroachments and temporary shops that occupy the road * frontage will be affected and they or their representative need to be involved in the consultation process; . Where owners of property, land and building /structures or their tenants are involved, U consultations are required; * In cases where community structures are affected, the local management and community groups need to be consulted; a In cases of bypasses, the problems of land acquisitions will need consultations with agricultural landowners and workers; . People will have to be involved in identification of accidental hotspots; I . Need for improvement of intersection, sharp curve, level crossing etc. has to be ascertained from people through consultation process; . The noise sensitive receptors are to be identified through public consultation process. I 5.4 FUTURE PUBLIC CONSULTATION AND PROJECT CYCLE Consultation involves soliciting people's views on proposed actions and engaging them in a dialogue. It is a two way information flow, from project authorities to people and, from I people to project authorities. While decision making authority would be retained by the project authority, interaction with people and eliciting feedback allows affected 3 populations to influence the decision making process by raising issues that should be considered in designing, mitigation, monitoring and management plans and the analysis of alternatives. The public consultation sessions envisaged in the project is given in table 5.1. l Revised by Lea Associates 5-4 October 2001 I (Original Document by ICT, CES, LBII) l Mlzoram State Roads Project - Phase I SEd: 5 - Public Consultation Table 5.1: Proposed Consultation Framework for MSRP * ______PoeSa People/Organization to be Environmental issues to be Project Sta ge Consulted discussed / presented Pre-design stage All stakeholders People notified about the project to inculcate X (Carried out for awareness and to seek opinion on environmental Phase-I & will be issues. carried out for Phase People living along the project Introducing project proposals and identification of | II) corridor and village council related environmental and socio-economic issues. * representatives PWD officials (PIU members), concerned State Ministers and District Officials I NGOs working in the vicinity of the project area and based in ______________________ Aizaw l Baseline Conditions Local people and village council Identification of potentially affected households, and Impact representatives community assets, roadside trees, presence or Assessment stage absence of rare/endangered flora and fauna (Carried out for species. Phase-I & will be District Government Officials Socio-economic development, opportunity for carried out for Phase employment generation, agriculture, forestry, II) wildlife, environmental health and sanitation I | Project Affected Households Demography and economic profiles, access to community facilities, water supply, health and ._______________________________ displacement. Mitigation and Selected affected people and Compensation and resettlement preferences, I Enhancement I stakeholders employment in various activities related to road Measures construction and subsequent management of (Carried out for assets, social forestry, public amenities, etc. Phase-I & will be carried out for Phase II) Implementation PIU and NGO Bring transparency; Successful implementation of RAP and EMP; and Create accountability and sense of local ____________________j ownership; 5.4.1 PRELIMINARY DESIGN STAGE Consultations would be carried out at the preliminary stages of design to identify * Location specific social and environmental issues to be addressed through designs; 3 . Socio-economic profile of community along the project routes; * Extent of likely impact due to the project; I * Expectations and reservations of people towards project; and * Resettlement and rehabilitation options. I Census of all the properties within 15 meters on either side of the existing centre line would be carried out. To prepare the baseline and identify R&R options and socio | economic survey of 25 percent of the Project Affected Households would be conducted. Moreover local level consultations would be carried out through focus group discussions with the community residing along the highway select the best alternative to minimise impacts. The venue of the meetings would be kept at a major village grouped/flanked by Revised by Lea Associates 5-5 October 2001 * (Original Document by [CT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 5 - Public Consultation other smaller villages. At these meetings, the people would be formally invited covering * project affected persons, prominent village persons, village council members, teachers, health workers and doctors including women. | The consultations would be held based on a structured questionnaire (see Annexure 5.2). At meetings, these questionnaires would be distributed through the Village Council Presidents (VCP) and people would be informed about the subsequent meeting when their responses would be recorded. Table 5.2: Public Consultation of the Preliminary Design Stage Date Village Participating villages Participants Participants Male Female 23.08.99 Melriat Melriat, Hualngohmun, VCP/PAPs/Other Villagers 97 13 I Kelsih 23.08.99 Aibawk Aibawk, Tachhip, PAPs/Other villagers 67 4 Sateek, Damdiai 24.08.99 Sialsuk Sialsuk, Samlukhai PAPs/Other villagers 102 20 25.08.99 Thenzawl Thenzawl PAPs/Other villagers/PHC, 87 Doctor/Health officer 5.4.2 DESIGN FINALISATION STAGE Once the designs are prepared giving due concern to the identified social and I environmental issues, the PCC would go back to the community to give feedback on how their concerns were addressed in the project designs. During these consultations issues, which could not be avoided on technical grounds, would also be discussed at length and mitigation/ compensatory measures would be finalised. On the basis of the above consultations designs would be finalised. A summary of the R&IPDP and all EA documents would also be prepared, and would be kept in public places for disclosure. However, a formal public hearing will not required for the project in the light of circular of Ministry of Environment and Forests dated 15-10-1999. I 5.4.3 IMPLEMENTATION STAGE The NGOs along with the PIU would take over the process of consultation and participation at this stage. NGOs would play a key role in acting as a link between the I project authorities and the project affected persons. NGOs would undertake individual consultations and group meetings, and would seek participation of the people themselves 3 in smooth implementation of the R&IPDP and EMP. The NGOs would also try to generate accountability and sense of local ownership by involving the community in selection of relocation site, selection of income generating programmes and formation of self help groups in management of community assets. U 5.4.4 MONITORING AND EVALUATION STAGE Participation would also be encouraged in monitoring and evaluation of RAP and EMP. Sample surveys and local level consultations would be carried out at this stage to identify gaps and deficiency in planning and frame necessary actions to achieve project objectives. Revised by Lea Associates 5-6 October 2001 I (Original Document by ICT, CES, LBII) l CHAPTER-6 KEY ENVIRONMENTAL ISSUES l This chapter discusses the key environmental issues in Mizoram with special reference to the proposed improvements. The project impacts are described in order of importance after all the project activities have been discussed. The discussion follows the | environmental components in the same order as chapter on Baseline Conditions. | 6.1 TYPOLOGY OF IMPACTS IN THE PROJECT As is envisaged in the project objectives, the improvement works will be carried out mainly along the existing alignments. Direct impacts will be spatially restricted and only limited land acquisition is anticipated. All potential environmental impacts can be classified into three broad groups: I . Direct: caused by the road (construction and operation) itself I Indirect: linked closely to the project but not as easy as direct to quantify * Cumulative: additive, multiplicative or synergistic effects of a combination of the two types of impacts stated above. Further classification of the these groups into the following categories based on their nature: * Positive and negative impacts * Predictable and random impacts i . Local and widespread impacts * Temporary and permanent impacts | Short-term and Long-term impacts. I 6.2 POSSIBLE PROJECT ACTIVITY AND ANTICIPATED IMPACTS The various project components such as upgradation, major maintenance, realignments and bypasses, will all have different extent and intensity of impacts, though they all are essentially endeavours to improve connectivity. Works along existing alignments will generally have only incremental impacts, while the bypasses involve the permanent * conversion of land to roadway. I 6.2.1 IMPROVEMENT/ UPGRADATION ROADS For the priority roads, the works envisage widening of pavement, to an intermediate lane carriageway (5.5m wide) with shoulders (0.5m either side) and drains, repair and reconstruction of bridges and culverts, roadside drainage, construction of retaining walls and other slope protection works. This would require a minimum formation of 7.1m along the straight sections and 8m along the curves. The existing formation width varies between 5-6m in most of the sections. To accommodate the proposed cross-section, a Revised by Lea Associates 6-1 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues cutting on the hillside for a minimum of 2m width is anticipated. This will necessarily entail additional cutting on the hillside so that the cut surface of the hill is stable, and the increased use of materials. Also, Mizoram being a rich area in the variety and density of flora, the vegetation along the side of roads will be cut. Field surveys of project area were carried out to identify and assess specific potential impacts of the proposed road improvement program on the environment. Based on these surveys, the following environmental issues, which need to be specifically addressed, were recognized. Most of the impacts will arise at construction stage. I . Cutting of hill slopes, stability of cut slopes * Land slides and soil erosion * Flora and fauna including potential occurrence of endangered species * Conservation of natural and other protected areas * Water requirement during road construction * . Disposal of debris W waste management, particularly from construction camps * Road safety and signage. I Most of the negative impacts relating to the above environmental issues can be addressed and reduced by adopting appropriate mitigation measures at the design and construction stages of the project. IE 6.2.2 NEW BYPASS AND REALIG N M ENTS The construction of new bypasses will mean conversion of land use directly attributable to the project. The possible alignment for the Aizawl Bypass that has been located close to Aizawl, due to lack of any road leading to it, has no habitation along the alignment and the present land use is predominantly agricultural (jhum land) or unclassified forests (also a small stretch of reserved forest). The acquisition of a stretch of 10m width for the new bypass alignment, shall be a critical issue in terms of the * Loss of flora, I . Extent of cut involved, * Vulnerability of the alignment to human habitation, which would induce further land use changes once the project is complete. I These above would be significant especially as these represent a direct, long term and irreversible impact. Loss of cultivable land will also affect livelihood of the landowners. | Any other sensitive features such as plantations along the new alignment will also be adversely impacted. The Environmental Impact Assessment for the phase II will consider the impacts of the Aizawl bypass in detail. Apart from these major bypasses, there would be several realignments along the upgradation routes, mainly to improve the existing geometric deficiencies. These can have I a considerable impact on the vegetative cover, relatively rich bio-diversity areas on these sections and would involve huge quantities of filling. The stability of these sections and the loss of biodiversity need to be addressed in the Environmental Assessment. Revised by Lea Associates 6-2 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues I 6.2.3 BRIDGE CONSTRUCTION The project shall involve the reconstruction, major maintenance of bridges along the project routes. Though the rivers they cross are not perennial, they carry certain flow due I to the heavy rainfall distributed over 9 months a year, which might be affected during construction. During the construction stage, disruption to the aquatic life and riverine ecology is anticipated. Other impacts of the proposed bridges will be increased levels of air pollutants and noise levels in previously pristine areas. These adverse impacts necessitate a detailed investigation during the EA focussing on the water environment, the impact on resident flora and fauna, impact on human population, if any near the proposed sites. I 6.2.4 MAJOR MAINTENANCE The major maintenance component of MSRP includes 9 road stretches, measuring a total * length of 518km. No widening of the existing roads, realignments or any other major construction works are envisaged under this component of the project. The maintenance works would mainly consist of improvements to the existing pavement surface, road drainage, slope protection works, repair/replacement/addition of culverts, and provision of suitable road signs and other road furniture to improve the safety and comfort of travel I on these roads. The works on these roads being restricted to the existing road width, no significant adverse environmental and social impacts are apart from localised impacts 3 during construction that can be easily managed. The impacts on the various natural environmental components due to the proposed * improvements proposed in the project are described in the subsequent section. I 6.3 NATURAL ENVIRONMENT I 6.3.1 CLIMATE Direct impact of the road project on the climate are long-term and probably very small in magnitude compared to other influences like removal of vegetative cover along the project roads. The micro-climate may be impacted temporarily due to the removal of vegetation. However, few impacts are anticipated on the regional climatic conditions- temperature, rainfall, etc., which can be attributable to the project. Though the project will involve clearing of a significant vegetative cover, the consequent impact on the climate is unlikely to be significant. 6.3.2 PHYSIOGRAPHY Road construction activities involve alterations in the local physiography and drainage patterns. The upgradation as part of the project shall involve cutting on the hill sides for the entire length. The impacts on physiography may include destabilisation of slopes due Revised by Lea Associates 6-3 October 2001 I (Original Document by [CT, CES, LBII) Mizoram State Roads Project - Phase I 5E4: 6 - Key Environmental Issues to cutting, quarrying, increased vulnerability to landslides etc. These adverse impacts on * the topography are anticipated and need to be addressed. Earth/rock cutting of hillsides for widening of priority roads will result in instable slope and | may cause landslides. Other factors that may, also aggravate the problem of soil erosion and land slides are: | . Felling of plants/trees for widening of the road. a Poor drainage, particularly during the construction phases, due to alteration to surface conditions. | Action of rainwater during monsoon. * Vibration from blasting and construction machinery. Appropriate slope protection measures like retaining and breast walls, bio-engineering * techniques will need to be employed to check the occurrence of landslides. These would be based on geomorphological assessment of the project routes (to assess the existing geological, drainage, and vegetative conditions and characteristics along the entire stretch). This will form a basis for the finalisation of the slopes that are being worked out for PIA and will be worked out for Phase-II routes also. The erosion potential of the soil is function of a combination of rainfall, windspeed, soil type and local topography. Due to the removal of the vegetative cover, the vertical surfaces of the hills shall be exposed, making them vulnerable to erosion. Since maintenance component does not envisage any cutting on the hillsides, any | increased risk of landslides is limited to the locations which are already vulnerable. I 6.3.3 SOILS The project will involve the acquisition of agricultural lands (mostly used for jhum plantations) and would entail the loss of vegetative cover. Acquisition of such lands for l the project will be a direct, long term, negative impact of the project. Temporary acquisition will also occur for workers camps, stockyards, storage yards, etc. During the construction period, the impact may be the loss of agricultural produce or standing crops. Productive soil may be lost if agricultural lands are borrowed without proper safeguards. Along major maintenance routes, the loss of topsoil is not likely to be significant since the maintenance will occur within the available clear width and no land acquisition is expected. The formation width is being maintained at its present condition and no major U borrowing of earth is envisaged. This will further limit the amount of topsoil lost for routes included in this component. . Materials for construction As the upgradation routes shall involve the cutting of hillside, there will be significant | earthwork generated, some of which will be utilised for the earthwork requirements for the project. Apart from these, the cut materials shall be used in the embankments to be constructed for the various realignment sections. However, disposal of the extra excavated/cut material generated by a project will be a major concern. If disposed Revised by Lea Associates 6-4 October 2001 (Original Document by ICT, CES, LBII) l Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues without environmental/ecological considerations, this may result in major negative impacts. A network of commercial quarries has been established throughout the state. A separate I study on material sourcing and quarries has been prepared as part of the Feasibility Study for the project. Whilst operation of quarries is an independent and regulated activity, the project will increase the rate of utilisation and resource depletion. The current operation and practices of the quarries are in itself a major environmental concern. The project will not use quarries, which do not implement environmentally safe practices. The operation I of quarries will have to follow the rules and regulation as per the GoM Gazette notification. River sand is a scarce commodity in the entire state. Any borrowing of sand for the project shall have significant impacts. As an alternative, the viability of the usage of crusher dust has been explored for the project. There are several crushers along the various project routes that can willingly supply the material. The adequacy of availability needs to be worked out in the EA. I Another significant impact would be during the transportation of these materials from their sources to the construction sites. The detailed EAs should focus on the specific issues of the transportation and handling of materials and the availability of suitable material for road construction in the vicinity of the selected project routes. I 6.3.4 WATER As discussed in the baseline, water scarcity is common throughout the state. The impacts I on the water environment can occur at all stages of a road project. The proposed works can cause disruption to users by either removing the source, restricting access or deteriorating the quality of water from a source. The major potential impacts that can occur due to any water project are summarized in the following table 6.1: Table 6.1: Potential Impacts on water resources due to construction activities Impacts Due To Construction Indicators Loss of water bodies Area of water bodies affected Loss of other water supply sources Hand pumps, water drums etc affected Alteration of drainage, run off, flooding No. of cross drainage channels I Depletion of Ground Water recharge Area rendered impervious Use of Water Supply for Construction Quantum of water used Contamination from improper sanitation and Area of camp / disposal site and proximity to Waste Disposal in Construction Camps water bodies / channels * Surface Water Resources With rugged and highly dissected topography, the state has very few surface water bodies as ponds, tanks etc. Wherever the project routes encounter such water bodies, the significant impacts on surface water resources would be the loss of capacity due to Revised by Lea Associates 6-5 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues increased width of formation (for the proposed widening), disruption to access during the construction period, impairment of water quality due to sediment-laden run-off from construction sites, alteration of local drainage, contamination from fuel and lubricants, use of water for construction (and consequently exclusion of the local community from the use of such sources of water). Also, there are several water resources, rich in terms of biological significance, as swamps and marshy areas. Such areas will be identified during the EA stage. The detailed EAs will consider, inter a/ia, the extent of encroachment into the water bodies and consequent loss of storage space, and impacts on the aquatic ecology. In addition, the impacts of the contamination of these sources by run-off from construction camps, sites where construction actually takes place (the work zone), and run-off from roads in the operation phase will be examined once other details like the routes to be upgraded, their proposed treatment and the consequent extent of impacts are firmed up. Maintenance works are expected to be limited within the available formation width. Therefore, they are unlikely to impact any surface water sources at least in terms of reduced storage capacity, though indirect impacts due to construction need to be addressed based on the site-specific conditions. Water for Construction The water table in the state is very low and water scarcity is common during the dry seasons. Though the rainfall is spread over a period of 9 months, due to the porous nature of the soil and the low water retention capacity, storage of water for construction is an issue of concern. The viability of purpose built water-harvesting structures along the various watercourses and streams will be worked out during the detailed EAs. Impact on Surface Water Quality The water quality data (refer Chapter 4 on Baseline Conditions) reveals that all the physico-chemical characteristics of major rivers are well within the prescribed tolerance limits of Central Pollution Control Board (CPCB). The implementation of the road projects will not have any adverse major impact on the quality of surface water in the area. Contamination of water bodies may however, result due to accidental spilling of construction materials, oil, grease, fuel and paint from the equipment yards and asphalt plant. But, the quantities of such spills are generally small and can be controlled through proper supervision of works. Particular care will be taken during earthworks, excavation and dumping/disposal of construction wastes or overburden. Landslides may cause blockage and contamination of the watercourses. Proper care will be required during rainy season to prevent this blockage. The disposal of debris materials, and construction of bridges and culverts will have to be monitored and supervised to check pollution of water bodies. l Revised by Lea Associates 6-6 October 2001 * (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues I 6.3.5 AIR The existing levels of traffic along the roads in the state are very low. The notable exception is Aizawl where the air quality monitoring has revealed exceptionally high I concentrations of all pollutants of concern. Since traffic volumes will remain low, generally under 3000 PCU/day, the increased air pollution due to vehicular emissions is not an issue of major concern. The upgradation works envisage major earthworks to widen the embankment to accommodate the improved cross-section. This will involve a lot of movement of loose earth and its subsequent compaction. Dust generation is expected to be substantial during the construction stage. In addition, the emission of toxic gases due to the operation of | hot-mix plants is a concern during this stage. The major maintenance component does not envisage major earthworks but the other activities like the laying of the profile correction course, providing asphaltic overlay, etc., will cause air pollution, at least in areas in the vicinity of the locations of hot-mix plants. Thus, impacts on the air environment will be an issue along the maintenance routes albeit not as significant as for the upgradation roads. I 6.3.6 NOISE Noise related with construction as well as operation phase will be cause of concern. While in the former, the impact on the workers will be important, during the operation phase, the focus will be on sensitive roadside receptors such as churches, schools and hospitals within the settlements (and habitats of wild fauna, if found in surveys during detailed EAs). Increased noise levels are likely to occur in the vicinity of the construction sites. Due to the various construction activities, there will be temporary noise impacts in the immediate vicinity of the project corridor. The construction activities will include the excavation for foundations and grading of the site and the construction of structures and facilities. * Crushing plants, asphalt production plants, movement of heavy vehicles, loading, transportation and unloading of construction materials produce significant noise during construction stage. The typical noise levels associated with the various construction activities and the various construction equipments are presented in Table 6-2. I Table 6.2: Typical Noise Levels of Principal Construction Equipments (Noise Level in dB (A) at 50 Feet) CLEARING STRUCTURE CONSTRUCTION I Bulldozer 80 Crane 75-77 Front end loader 72-84 Welding generator 71-82 Jack hammer 81-98 Concrete mixer 74-88 Crane with ball 75-87 Concrete pump 81-84 Concrete vibrator 76 EXCAVATION & EARTH MOVING Air compressor 74-87 Revised by Lea Associates 6-7 October 2001 (Original Document by ICT, CES, LBII) IMizoram7 State Roads Project - Phase I SEA: 6 - Key Environmental Issues CLEARING STRUCTURE CONSTRUCTION Bulldozer 80 Pneumatic tools 81-98 Backhoe 72-93 Bulldozer 80 Front end loader 72-84 Cement and dump trucks 83-94 Dump truck 83-94 Front end loader 72-84 Jack hammer 81-98 Dump truck 83-94 Scraper 80-93 Paver 86-88 GRADING AND COMPACTING LANDSCAPING AND CLEAN-UP Grader 80-93 Bulldozer 80 I Roller 73-75 Backhoe 72-93 Truck 83-94 PAVING Front end loader 72-84 Paver 86-88 Dump truck 83-94 Truck 83-94 Paver 86-88 Tamper 74-77 Dump truck 83-94 Source: U.S. Environmental Protection Agency. Noise From Construction Equipment and Operations. Building Equipment and Home Appliances. NJID. 300.1. December * 31 1971 Though the noise levels presented for the various construction activities far exceed the permissible standards, it is important to note that the construction noise is generally intermittent and depends on the type of operation, location and function of the | equipment. Along the major upgradation routes, none of the clearing machinery will need to operate and therefore, the noise levels will only be from the construction equipment in the column on the right. It is anticipated that since overlay is the major component, the noise levels during construction will be lower than those along the upgradation routes. During operation stage of the project, as the traffic is not expected to increase to very high levels, impacts due to noise from vehicular pollution will not be very significant. 6.3.7 BIODIVERSITY ISSUES Most of the bio-diversity rich areas in the state are protected/conserved. Smaller, sporadic areas with high bio-diversity may be found outside such protected areas. The project may have only slight direct impact on the protected areas, but the possibility of induced I impacts can not be ruled out, if the accessibility to the protected areas increase very substantially. I . Protected Areas / Wildlife Sanctuaries Except for the maintenance road Ml no protected areas such as National Parks and I Sanctuaries are reported within corridor of influence of the project roads. The Lengteng wild life sanctuary is located about 4km from Ngopa along this road. Since only improvement of the pavement surface is envisaged without altering its existing alignment, formation width and geometry, no adverse impact of this improvement work on the Revised by Lea Associates 6-8 October 2001 (Original Document by ICT, CES, LBII) l I Mizoram State Roads Project - Phase I SEA: 6 - Key En vironmental Issues Wildlife Sanctuary is envisaged. The anticipated increase in traffic is minor, and will not * result in over-exploitation of the Sanctuary. . Forests Though 89% of the total state area is under forests, a major portion has been categorized as unclassified forests, where no specific regulations regarding the clearance of forests and vegetative cover apply. The upgradation shall for a major length involve the acquisition of such unclassified forestlands. Also, several maintenance routes pass through | forest areas. Loss of vegetative cover due to the clearance of land for the accommodation of the | formation is an issue of concern. * Relatively High Bio-Diversity Areas outside the protected Areas | It is anticipated that areas rich in biodiversity could be found on the roadside, particularly if the road is currently not in a very good riding condition. All these areas need to be examined in terms of the bio-diversity richness, and for habitats of rare/endangered/important flora/fauna. Assessment is required whether these habitats are unique or not. During detailed surveys of Phase I EA, such areas have been found, I some of which supports endangered flora/fauna. However, none of these flora/fauna is unique. The project will, nonetheless protect/conserve such flora/fauna. The proposed mitigation measures in Phase I include involving the community (and researchers) in conservation efforts and monitoring, in addition to the hard protection measures installed from the project. * Flora | Ecological degradation from the construction of the proposed roads by way of direct loss of vegetation (trees shrubs & grasses) due to cutting of hill slopes will be nearly 2000 trees apart from the loss of vegetative cover. The number and type of trees and plants to I be uprooted will be analysed in detail in EIA report. The impact resulting from the removal of trees along the roadside may reduce shade and shelter for wildlife habitat. Other impacts include reduction in soil fertility and moisture and decreased humidity and vehicle air pollution buffering. The generation of dust during * construction may deposit on the leaves of the plants along the roads. Other construction activties like workers camps, debris disposal and water impounding structures will also have negative impact on land along the project roads. Ecological I degradation may occur due to use of plant and trees as fuel wood and wildlife poaching by the construction workforce. . Endangered flora species There are stretches along the project routes where endangered plant species as Cyathea (tree fern) and orchids as Dandrobium exist. The preservation of these species and their Revised by Lea Associates 6-9 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues association to the particular location needs to be assessed prior to carrying out any measures on the conservation and preservation of these biodiversity rich areas. * Medicinal plants The state of Mizoram is home to several medicinal plants, with 231 species of such plants reported. An investigation along the project routes in terms of the prevalence of such species, and their utility to the community shall be carried out as part of the EA. I 6.3.8 ARCHAEOLOGICAL/CULTURAL HERITAGE There are no protected archaeological monuments / structures along the corridor. The only structures that can be impacted are the graves and memorial stones within the existing formation and the church buildings abutting the project routes. As part of the Design stage, public participation shall be taken up as an integral part of the project preparation to address the issue on these structures. The loss of access roads leading to the churches, and the increased noise levels both during the construction and operation stages of the project shall need to be addressed as part of the social assessment that shall be carried out. The maintenance component will have marginal impact on any historic/archaeological properties located on the roadside since the treatment envisaged for these routes is restricted to the clear space available at present. 6.3.9 ToURISM/PILGRIMAGE Mizoram, with a rich biodiversity and natural beauty offers a great potential for tourism development. Improved access and connectivity should provide a boost to this industry in 3 the state, which has much to offer to the discerning tourist. Providing better access to the sites of tourist interest can go a long way in realizing their full potential. 6.4 SOCIAL ENVIRONMENT I 6.4.1 POVERTY ALLEVIATION Roads are often argued to be the conduit of wealth. Citations are there to indicate that 1 vigorous road development precedes rapid economic development of a nation. As connectivity and accessibility improves, social networks are strengthened, economic opportunities galore. Poverty alleviation is a basic need of the nation. It is also a constitutional duty'. Any project therefore, has to address the issue of being of assistance to achieve a national goal. | ' The Constitution of India upheld the right of life, which includes the right to 'live with dignity". Poverty alleviation has been a recurrent theme in the Indian polity. Revised by Lea Associates 6-10 October 2001 (Original Document by ICT, CES, LBII) I Mizoramn State Roads Project - Phase I SEA: 6 - Key Environmental Issues Sustainable poverty reduction is the World Bank's overarching objective. Since the I complete range of programmes and policies affect the well being of the poor, there are many complementarities between poverty reduction and other operational priorities. In 3 most cases it has been observed that the burden of poverty falls disproportionately on the relatively vulnerable groups, so it is essential to increase their income-earning opportunities, their food security and their access to social services. The cardinal virtues that can be built in such infrastructure building projects are, (a) Participation of poor in infrastructure building projects; (b) Thrust on resource poor areas where increasing number of poor live; (c) Exclusive measures to ensure access of poor to infrastructure projects; (d) Strong institutional arrangements; and, (e) Emphasis on participation of NGOs. The above encompasses the issue of poverty reduction as MSRP is expected to bring | about a number of opportunities to the poor people of the region like increased employment, increased market facilities, increased mobility of human resources, increased local economic and credit opportunities, increased institutional networks, increased I awareness level and increased scope for better management of public schemes. The project is seen as a major generator of economic momentum, and shall benefit the * economically backward region. I 6.4.2 INVOLUNTARY RESETTLEMENT The proposed improvement works would lead to substantial involuntary resettlement as land take is required apart from the accommodation of the formation width, to make provision of bypasses and realignments. The involuntary taking of land result in: * . Relocation or loss of shelter * Loss of assets or access to assets; or . Loss of income sources or means of livelihood, whether or not the affected persons I must move to another location. Involuntary resettlement may cause severe long-term hardship, impoverishment and * environmental damage unless appropriate measures are carefully planned and carried out. Attention to such matters is especially important when the people who may be adversely affected are poor and vulnerable, do not have the capacity to absorb such adverse impacts, and cannot remain productive without significant help. If involuntary resettlement is unavoidable, it should be well planned and executed so that economic growth is enhanced and poverty reduced, especially for such vulnerable people. Revised by Lea Associates 6-11 October 2001 (Original Document by ICT, CES, LBII) I Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues To address the issues related to involuntary resettlement, a R&R policy shall be drafted * for the project by the Government of Mizoram in accordance with the WB OP/OD requirements. 6.4.3 INDIGENOUS PEOPLE Approximately 95% of the population in the state of Mizoram belong to tribal community. As per the considerations of OD 4.20 of the World Bank, tribals or indigenous communities2 should be taken care of with special assistances in case of involuntary I resettlement and a Indigenous People Development Plan (IPDP) needs to be prepared if the proposed project activities adversely affects tribal families still maintaining their | traditional way of life. I 6.4.4 GENDER ISSUES AND WOMEN PARTICIPATION Though women constitute almost half of the population in the state they are neglected from the socio-economic development3 point of view. Socio-economic parameters like I literacy, work force participation rate, general health conditions etc. reveals that social status of women is very backward in the project area and thereby brought forward the | scope of considering the households headed by women as vulnerable. It is imperative to bring the issue of women's development in the process of socio- economic uplift within the scope of the RAP for MSRP. For this a conscious effort should be made towards integrating the issue in the project. They have to be integrated in the project as full-fledged participants taking part in all the I stages of the project starting from planning through implementation and even in the post- project stages. 6.4.5 HIGHWAY RELATED DISEASES There have been various studies carried out indicating the high prevalence of Injecting Drug Users (IDU) in Mizoram and the high risk behaviour of this population making them 2 The terms 'indigenous people," "indigenous ethnic minorities", or, "scheduled tribes" describe social groups with a social and cultural identity distinct from the dominant society that makes them vulnerable and disadvantaged in the development process. Also social history of our country has shown that due to socio- economic backwardness, inherent temperamental difference and relative isolation and oppression from the dominant society the indigenous people or the scheduled tribes have always been left at the ledge of the society. The tribal communities are always found to be the worst affected by any development activity that cause displacement from their own home and land. 3 India ranks 103 out of 137 countries in the gender development index (GDI) that reveals the reality of I insufficient level of development of women as compared to men in this country. The economic condition of women headed households varies considerably depending upon factors such as marital status, social context of female leadership and decision making, access to facilities and productive resources, income I and composition of the household. These conditions form the basis for defining indicators to assess the vulnerability of such households. Revised by Lea Associates 6-12 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 6 - Key Environmental Issues vulnerable to STDs including HIV/AIDS. Seeing the gravity of the spread of all these diseases proper measures are required to be taken to create awareness about their severity and to control such spread of diseases. 6.4.6 COMMUNITY RESOURCES The project shall involve impact on several public utilities, apart from various common property resources as hand pumps, bus shelters, urinals etc. It shall be worked out during the design that all common property resources impacted shall be replaced to the I community by the project. It is important to weigh the benefits against the costs of adverse impacts by examining development options and entail no or minimum | displacement. I 6.4.7 CONSTRUCTION CAMPS The project shall involve a significant number of migrant labour force involved for the entire duration of the construction. The interaction of these workforce with the local I community shall be an issue to be addressed. The locations of the construction camps and other labor camps shall be sited based on such considerations. 6.4.8 ROAD SAFETY The sprawl of the settlements in Mizoram are mostly along the major transport routes, with the residential and commercial structures opening onto the roads. These combinations create hazardous conditions for all the road users. Though there is not much traffic existing, the poor pavement structure condition and lack of warning/informatory signs especially in settlements are the cause of accidents on the road. Also, in the absence of any flat lands for playgrounds for children, roads become more vulnerable in terms of safety of children. l l l I Revised by Lea Associates 6-13 October 2001 (Original Document by ICT, CES, LBII) l CHAPTER-7 ANALYSIS OF ALTERNATIVES This chapter discusses the alternatives that have been considered for the project (or part thereof) and selection of the best alternatives for the project. It also includes a discussion on the "with" and "without" project scenario. 7.1 ROUTE ALTERNATIVES The Mizoram PWD, fully realising an apparent need for upgrading the state road infrastructure carried out a Strategic Options Study (SOS) for the state road network in 1999. The SOS, covering a network of 3,534 Km of state roads had objectives of (a) establishing a rationale for determining development priorities for road improvement programmes, and (b) identifying roads for feasibility studies. The SOS based on analysis' * carried out for the road network was completed with inputs from social, environmental screening, engineering aspects of the project. The study identified 15 roads measuring a total length of 1,222 km (276 km. of 3 priority roads for improvement and 773 km. roads for major maintenance work). These roads were further examined during the Feasibility Study in terms of their (a) economic, (b) engineering, (c) environmental and (d) social viability. After detailed analysis, a set of 185 km of road for improvement/upgradation and 578 km for major l maintenance. I 7.2 "WITH" AND "WITHOUT" PROJECT SCENARIO Mizoram, is one of the most underdeveloped states in the country. Though the state has a good potential for development of agriculture, horticulture, tourism etc, the lack of an adequate transport infrastructure is a major bottleneck factor in such the development. * The ' with' and 'without' project scenarios are analysed with this backdrop. Providing better connectivity will ensure that goods and people from areas accessed by the road can move in and out of the areas quicker and save time. However, there would I be an increase in the vehicular pollution-air and noise, in the vicinity of the road. The terrain along the project roads is hilly, and any widening of these project routes will call in for the cutting of the hills and removal of the vegetative cover along the hill slopes. The project routes pass through several villages and settlements, where any widening will result in an acquisition of private structures and agricultural lands. The impacts associated The evaluation criteria for the prioritisation of the road network included: traffic, road network condition, capacity, V/C ratio, Road Connectivity, Socio-economic factors, environmental issues and economic factors Revised by Lea Associates 7-1 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SE4: 7 - Analysis of Alternatives due to the project will be mitigated / compensated through providing appropriate mitigation measures, so that adverse impact will be minimized and development becomes environmentally sound and sustainable. | If the project is not implemented, there is every likelihood that the project roads will deteriorate further. Though the MPWD envisages a 5-6 year maintenance cycle for State Highways and 10-year cycle for Major District Roads, the actual work carried out is usually on an ad hoc basis. Therefore, only certain roads may be maintained regularly. In the absence of the project, the department will also find it extremely difficult to generate | funds for such a massive improvement of the road infrastructure from its own resources. With specific reference to the major urban centres of Aizawl and Lunglei, without the bypasses, the traffic would continue passing through the two settlements and continue to pose a safety risk for the residents in these already congested towns. Therefore, the "with" project scenario, with its minor adverse impacts is more acceptable than the "without" project scenario which would mean an aggravation of the existing problems. The potential benefits of the proposed road improvements are substantial and far-reaching both in terms of the geographical spread and time. Hence, it is clear that the implementation of the project will be a definite advantage to the state in order to achieve * all-round development of its economy and progress for its people. 7.3 ROUTE FINALISATION The Feasibility Study included engineering, economic, environmental and social evaluation of the various improvement options. The Economic viability of the project has been carried out within the broad framework of "Cost Benefit Analysis". The analysis was done for the three priority roads and the 14 major maintenance roads identified in SOS. 7.3.1 OVERALL FEASIBILITY The economic analysis involved comparison of project costs and benefits - both in economic terms- under the 'with' and 'without' project conditions. In addition, Net Value Added Approach has been used for determiing the net benefits to the sustainable Development Programme for the State as well as other development envisaged in the future. Economic Internal Rate of Return (EIRR) has been worked out for all the study I corridors. The environmental and social impacts of the project have been assessed in conjunction with the economic and engineering feasibility for the project. The recommendations of the environmental screening provided suitable modifications in the approach to the engineering designs for the project, which formed the basis for the economic evaluation. Based on environmental and social screening, the corridors were classified into various categories of environmental sensitivity. This was based on the following environmental attributes: topography, cutting of mountain ecosystem and disposal of debris, water bodies, water availability, disposal of debris, land slides and geological characteristics, surface erosion, forests, wildlife areas, presence of endangered species of flora and fauna, religious structures and community assets. Revised by Lea Associates 7-2 October 2001 (Original Document by [CT, CES, LBII) Mlzoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives The resultant environmental sensitivity categories for each of the road screened during I feasibility and the economic internal rates of return obtained are tabulated in Table 7.1. Table 7.1: Summary of Results from Feasibility Study EIRR Route No. Route Section Environmental Category Without time With time saving saving I Pi Aizawl - Lunglei Significant impacts, reversible, 19.61 15.86 P2 Bairabi - Kanhmun mitigation needed 18.33 17.40 P3 Kawnpui - Aizawl 78.94 59.51 Ml Kawikulh-Ngopa-Tuivai Impacts minor, reversible, 51.21 44.44 I ______________ construction stage impacts M2 Zamuang-Tuilutkawn 14.25 10.50 M3 Tuipuibari-West Kawnpui 30.70 29.96 M4 Keitum-N. Vanlaiphai 47.38 37.34 M5 Lungsen-Chawngte 37.06 33.05 M6 Zobawk-Haulong 28.01 25.00 M7 Damdiai-Sialsuk 33.70 29.13 M8 Lunglei-Tiabung 28.24 19.53 M9 Khawzawl-E. Lungdar 29.91 28.06 M1O Saiha - Chhuarlung - Tuipang 20.81 Na M11 Chawngte - Diltlang 35.59 31.58 M12 Chawngte - Borapansury 31.83 28.54 M13 Kawichaw - Phura 20.81 NA M14 Ratu - Suangpuilawn 19.88 17.28 As the EIRR of all the routes being taken up, both as part of the upgradation and major I maintenance works are above 12%, the project roads and their proposed improvements were economically viable. 7.3.2 ENVIRONMENTAL INPUTS IN ROUTE FINALISATION 3 Environmental and social screening of the candidate roads was carried out to determine the magnituede of actual and potential impacts due to the project and to ensure that environmental considerations are given adequate weight in the selection and design of proposed improvements. The environmental screening took into consideration, the impacts on the environmental | and social components both within and outside the existing roadway. A matrix method of evaluation was chosen for the evaluation and assessment of impacts. All valued environmental components that are of significance to the project were considered. After the identification of these components through stakeholder consultation and reconnaissance surveys, each of the component was assisgned a weight based on the I baseline data, prevailing conditions and professional iudgement. Impact scores (positive for beneficial impacts and negative for adverse impacts) were 3 assigned for each project activity based on the severity criteria. A matrix was formulated by combining the environmental components and the proejct activity on the x and y axes. Impact score for environmental component = Importance value x Algebraic sum of impact scores | The environmental components selected for screening were as follows: 0 Forest areas, protected areas, wildlife sanctuaries Revised by Lea Associates 7-3 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives * Rich biodiversity including medicinal plants * Road stretch passing through river flood zone/wet lands village ponds Significant groups of trees along road and density of roadside trees * Cutting of mountain ecosystem and disposal of debris | Landslide prone areas Settlements (towns and villages) and market places * Quarries close to the road * Sensitive receptors as schools and hospitals * . Road junctions with heavy pedestrian - vehicular conflicts * Road stretches with steep slopes * Roads with poor embankment conditions due to floods and soil erosion I . Water resources around the project routes * Cultural properties including graveyards, churches etc. The results of the screening in terms of the environmental sensitivity is presented in Table 7.2. Table 7.2: Screening for Environmental Sensitivity Si. Priority Name of the road Total Total Net Remarks No. Road Negative Positive Score Score Score 1. 1 Aizawl-Thenzawl- -3631 +2365 -1266 Impact is appreciable but Lunglei (171 kms.) reversible, control measures needed 2. 2 Bairabi-Zamuang- -2897 +1725 -1172 Impact is appreciable but Kanhmun: SH+ODR reversible, control (60 Kms.) measures needed 3. 3 Kawnpui-Aizawl via -2659 +1420 -1239 Impact is appreciable but Lungdai: MDR (45 reversible, control _____ _________ kms.) measures needed . For details of the evaluation of the Project Priority Road PIA, refer Table 7.3. I 7.4 WIDENING OPTIONS The existing formation width along the priority routes identified vary between 5.0 to 6.0m. 3 The proposed intermediate lane carriageway with drains and shoulders necessitate a formation width of 7.1m. This shall necessitate additional land acquistion for almost the entire length. Located in a hilly terrain, it is not possible to carry out an eccentric widening towards the valley side as the slopes are very steep and the stability of the fill and the retaining of the fill slopes will become an issue of concern. Similarly, concentric 3 widening, will entail both cutting and filling, which again is not a practical solution. Therefore, widening towards the hill side, has been proposed uniformly all along the upgradation routes. No widening of major maintenance roads is proposed. This obviously is a better environmental alternative than widening. Therefore, no detailed analysis of widening I options for major maintenance was attempted. 7.5 AIZAWL BYPASS OPTIONS As part of the up gradation programme, a new bypass has been proposed around Aizawl, for a length of 16km. A discussion on the criteria for the selection of alternative alignments, evaluation of the alternatives and selection for Aizawl bypass is presented below. Revised by Lea Associates 7-4 October 2001 (Original Document by ICT, CES, LBII) Ld; I Z~u - ZA - 'I'l' Bil m m IK ~J 8u ~- : (D NK oL 0 C- ) CD~ 3 EJ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~. (D>1 cr~~~~~~~~~~~~~~~~~~~ S 0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~44 - - - - - -- - - - -- - - - - - - - - - -~~~: Z4 s~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~. 4.. Mizoram State Roads Project - Phase I S5E: 7 - Analysis of Alternatives In order to enable the through traffic of NH-54 at Aizawl to use the existing shorter route I along the improved Aizawl-Thenzawl-Lunglei project road P1 (171 km) instead of following NH-54 (235 km), a link bypassing Aizawl is proposed to be provided between NH-54 and the project road P1 near Aizawl. This (bypass) road link will take off from NH- 54 at Zemabawk and join the project road P1 at the chainage of about km 4.5. Reconnaissance survey of the area through which the (bypass is proposed was conducted to identify its possible alignment(s). The reconnaissance team included the Highway Engineer, Social and Environmental Expert from both consultant and PIU. During this survey it was found that there were only two possible options, which could be considered. The description as also the schematic view of the relative disposition of these two * alignment options is given as follows. Zemabawk (Aizawl NH-54) Lawibual I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ~~~~~~~~ ~~Option II IF Option I |~~~~~~~~~~T mveng I~~~~~~~ Salem I~~LX Thakthing Kulikawn (km. 0.00 on PIA road) Km. 4.5 Towards Thenzawl Figure 7.1: Schematic View of Aizawl Bypass Alternatives | Revised by Lea Associates 7-6 October 2001 (Original Document by [CT, CES, LBII) Mlzoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives I 7.5.1 OPTION I : ZEMABAWK (VIA LAWIBUAL) TO KM4.5 OF PRIORITY ROAD P1 In the starting sections, this alignment follows a short jeepable track, though with many missing links. This route passes mainly through open agricultural lands. Option II From Zemabawk via Lawlbual to km 0.00 of priority road Pl This route passes through agricultural land and major settlements namely m Veng, Salem, Thakthing and Kulikawn before meeting P1 at kmO.00. This alignment option I would therefore involve considerable displacement in these settlements and problem of land acquisitions. Typical photographic views of the two options are given in Figures 7.2 to 7.3. Figure-7.2: Option I - Panoramic View Figure-7.3 Option II - Bypass Passing of Aizawl Bypass Through Settlements 7 .5.2 EVALUATION OF THE ALTERNATIVE BYPASS OPTIONS A comparison of the above two options indicates that option I is clearly the better of the two choices for the following reasons, . Option I alignment follows, as far as possible, the ridge line with lesser drainage problems and would involve relatively lesser earthwork in cutting. . This alignment appears to provide the most direct and the shortest linkage between NH 54 I and the project priority road P1, just outside Aizawl. * There being no settlement of any significance in the area along this alignment, it would have considerably less social and environmental implications than alignment option II. I Based on the above investigations, the alignment option I was selected up for further study. Detailed investigation of this alignment will be done during the EA of Phase II. | The length of the bypass is 16km. It will involve construction of some cross drainage works, like culverts and a bridge, about 25m long, across river Chite. Though the alignment option I has been found to be suited in terms of engineering, environmental, economic and social components, minor modifications in the alignment needs to be carried out addressing the site-specific environmental and social concerns. These would be carried out as part of the Phase II EA. Revised by Lea Associates 7-7 October 2001 I (Original Document by [CT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives I 7.6 REALIGNMENT OPTIONS Though there is only one major settlement to be bypassed (Aizawl), the provision of several small realignment sections, along the various upgradation routes will be I necessitated during the detailed engineering design. The road sections generally follow the natural contours with many ascending and descending gradients while traversing the 3 hills. This results in a very uncomfortable travel. Many places along the section could be improved both in vertical and horizontal alignment. Apart from these, the realignments may be worked out to: I . Minimise adverse social or environmental impacts * Shorten the length of the existing longer alignment. At each of the locations, where realignments are to be worked out, a comparison / analysis of the route options along the existing and realignment sections will be worked out. The criteria that needs to be evaluated are as per Table-7.3: Table 7.3 Comparison of Route Options Design Chainage (Km) I Option I Existing Alternative Engineering Concerns Geometry Length (km) Gradient * ~~~~~~~~~~~Number of Horizontal Curves Curves with: R =>40m 30m<= R < 40m 20m<= R < 30m R<20m Earthwork (M3) Cut: * Fill: CD Works Approximate Cost In Millions of Rupees Environmental and social concerns Biodiversity Stability of cut slopes Water resources Loss of vegetation Loss of structures Utilities and common property resources Environmental Mitigation l Costs Revised by Lea Associates 7-8 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SM: 7 - Analysis of Alternatives I 7.7 ENGINEERING ALTERNATIVES FOR PRIORITY ROADS 7.7.1 PAVEMENT STRUCTURE For the Priority roads, the option of a full width new pavement is the best solution. All existing pavement materials, which vary in quality and quantity are removed and salvaged, re-processed or disposed. The pavement structure is then rebuilt to structurally sound designs conforming to IRC and other international design standards after compacting the existing subgrade to achieve design CBR. This alternative has no significant environmental impact, and absolutely no social impact. I 7.7.2 ROAD WIDTH The guidelines provided in the Indian Roads Congress (IRC:52-1981) "Recommendations about the alignment survey and geometric design of hill roads"were generally followed. A narrowest possible road formation width was designed keeping in view the requirements of traffic capacity and safety as also the social and environmental implications of cutting needed for road widening, I 7.7.3 DRAINAGE It is proposed that all priority roads be normally provided with full concrete road side drains. In the open area the drain would be a V-type drain of sufficient depth to allow effective drainage, but shallow enough to allow a vehicle's wheel to enter in emergencies. In the areas of major settlements, trapezoidal covered drains are proposed. I For the cross drainage works, two type of culverts namely slab and pipe culverts have been proposed. Whereas the existing culverts will be replaced or reconstructed to the existing type, the new culverts to be additionally constructed will be mostly of pipe type except in areas of major settlements. In these area, slab culverts of appropriate designs * will be constructed. In order to protect the hill environment, appropriate culvert outlets, like falls, cascades with or without stilling basins, etc. will be provided on the outlets of culverts. 7.7.4 SLOPE PROTECTION Appropriate slope protection works like breast walls supplemented, wherever necessary, by other slope stabilizing measures, like benching, wire netting, drainage works and appropriate bio-engineering techniques will be provided to improve the hill slope stability at the potential landslide prone locations along the project roads. Depending on the height of the cut to be supported and other site conditions, following three types of Breast walls have been proposed at different locations of the project roads. . Dry Random Rubble Masonry . Bamboo crib walls /Gabions Revised by Lea Associates 7-9 October 2001 * (Original Document by ICT, CES, LBII) Mlzoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives * Composite Random Rubble Masonry I * Gabions * Mortared Random Rubble Masonry The final selection needs to be worked out based on cost and implementation effectiveness. All these options are environmentally beneficial. I 7.7.5 RETAINING STRUCTURES FOR FILL MATERIAL Retaining walls of appropriate designs will be provided to retain the material used for I constructing road in fill and as toe walls, for lending back support to the material dumped on the valley side. The following wall types have been considered for providing retaining / toe walls at different locations of the project roads. | Dry Random Rubble Masonry Composite Random Rubble Masonry M Mortared Random Rubble Masonry l Bamboo Crib Walls / Gabions - Gabions I The final selection needs to be based on cost and implementation effectiveness. All these options are environmentally beneficial. 7.8 ENGINEERING ALTERNATIVES FOR MAJOR MAINTENANCE ROUTES No widening of the existing roads, realignments or other major construction works are * envisaged for these roads. The work mainly includes pavement improvement treatment, road drainage and improving slope protection works. Since the proposed project activities will be confined within the existing formation width, the project work will not thus affect any plants/trees along the road corridor. Among the several alternatives designs, standards adopted for such items by IRC will be followed. 7.8.1 PAVEMENT IMPROVEMENT TREATMENT FOR BITUMINOUS SURFACED ROADS Based on the condition of the pavement, the following three categories of the pavement improvement treatment are proposed. Category 1: Resurfacing only * Surface deterioration is generally low. * No major structural deterioration or settlement I . Only pavement materials are affected * Wearing course is partially cracked both longitudinally and transversely * Potholes are less than 20%. * Wearing course has not worn out more than 10% * Edge cracking is low * Raveling is common Revised by Lea Associates 7-10 October 2001 (Original Document by ICT, CES, LBII) l Mizoram State Roads Project - Phase I SEA: 7 - Analysis of Alternatives I Category 2: Rebuilding Base and Wear Course Surface deterioration is visible throughout length Structural deterioration is visible * Deterioration affects soling materials * Carriageway is rutted in many places * Potholes are 20% to 50% * Rutting along the wheel tracks is generally deep Category 3: Re-construction Surface deterioration is generally high . Very high raveling Structural deterioration due to subgrade failure is common * More than 50 % of soling material is lost | Carriageway is very rough and bumpy * Potholes are common - more then 50% * Ruts are common I The selection of the major maintenance to be carried out has been worked out based on the evaluation of the various maintenance routes. None of these options cause any significant environmental impact. I I| ~~Revised by Lea Associates 7-11 October 2001 (Original Document by ICT, CES, LBII) l l CHAPTER-8 ENVIRONMENTAL MITIGATION, ENHANCEMENT l | Environmental mitigation measures represent the project's endeavor to reduce its environmental footprint to the minimum possible. These are conscious efforts from the project to reduce undesirable environmental impacts of the proposed activities and offset these to the degree practicable. Enhancement measures are project's efforts to gain acceptability in its area of influence. They reflect the pro-active approach of the project towards environmental management. Mitigation as well as enhancement measures are discussed in the following sections. This chapter follows the same sequence of discussion for various environmental components as the Chapter 6 on Environmental Issues. 8.1 GENERAL The negative impacts of road projects can be reduced or minimized only if proper safeguards are put in place during the design stage itself. These can include reducing | pollutant discharge from the harmful activities at source or protecting the sensitive receptor. An effective mitigation strategy will utilize a combination of both options to arrive at practically implementable measures. Enhancement measures require I commitment beyond the conventional from the project. They are a manifestation of the importance the project attaches to the host community, their customs, traditions and values. I 8.1.1 CONSTRUCTION RELATED ACTIVITIES Most of the direct impacts of a road project occur during the construction stage. This stage is also important since the people living near the sites are inconvenienced without I the collateral benefits of a functional road. Moreover, construction related activities are confined within an identifiable boundary and so is the affected population. It is also the stage of the project when the MPWD, can exercise maximum control to ensure that the environmental impacts are minimized. Most of the mitigation measures can be incorporated as good engineering practice during the design phase itself thus ensuring the mainstreaming of environmental concerns early in the project. Adherence to design drawing and specifications will reduce the adverse impacts during construction to within acceptable levels. Moreover, continuous supervision of the construction activity can also work as a deterrent to errant behavior. Therefore, incorporating environmental provisions within the construction contracts becomes vital to ensure effective implementation of mitigation measures during construction stage of the project itself. Revised by Lea Associates 8-1 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mitigation, Enhancement | 8.1.2 ROAD TRANSPORTATION ISSUES Issues related with transportation along improved roads are beyond the control of the proponent, the MPWD for MSRP, in most cases. The predicted timeframes are quite long * and the mitigation for most impacts are beyond MPWD's jurisdiction. They require intervention from agencies such as the Revenue Authorities, the Motor Vehicles Department and the Police to mitigate encroachment, increased roadside pollution due to vehicular emissions and accidents etc. The MPWD can from its side carry out the maintenance of the roads at specified intervals and act as the co-ordination agency for road transportation related impacts. | 8.1.3 HOTSPOT MITIGATION There are several locations where undesirable impacts of the project occur which can be easily distinguished due to their unique characteristics. These are termed as 'Hotspots'. Targetted interventions can help reduce the undesirable impacts to within acceptable limits. These can either be built into designs for road construction as part of good 3 engineering practice or specific mitigation measures can be detailed and separately implemented. Though the former is always more desirable, it may be difficult to achieve during project preparation for a variety of reasons. Irrespective of the route adopted, hotspot mitigation is a definite value-addition to any project and should always form a basis for 'selling' the project to the host communities. 8.2 NATURAL ENVIRONMENT 8.2.1 CLIMATE As already discussed in the section in Key Environmental Issues, the proposed improvements to the roads are unlikely to significantly alter the climatic conditions in Mizoram. Only short-term microclimatic changes such as increased local temperature are * likely due to the removal of roadside vegetation. No changes are anticipated in the wind characteristics or the rainfall within the area due to the project. Therefore, the project | does not propose any specific measures for mitigating impacts on the Climate in the project area. The compensatory plantation to be carried out (see later) should be able to restore the micro-climate conditions of before the removal of trees within 2-3 years. 8.2.2 PHYSIOGRAPHY | The mitigation of impacts of extensive cutting envisaged as part of the upgradation component is essential for the smooth functioning of the improved road. Since the proposed cuts may extend to a height of 5-lOm or more the stability of the cut slopes will be worked out. The measures which to be evaluated during the detailed EAs will include breast walls, bioengineering techniques, etc. The suitability of each technique for specific locations will need to be ascertained. While the one-time cost of the former method is Revised by Lea Associates 8-2 October 2001 (Original Document by ICT, CES, LBII) I Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mltigation, Enhancement higher, the latter will require much more maintenance and during the initial years some extra protection. Moreover, much steeper slopes can be retained by the use of 'hard' engineering solutions such as retaining walls than by 'soft' bioengineering. The trade-off will have to wait for the data from the individual stretches before a final decision regarding the choice of the technique can be made. At certain locations, a combination of these two techniques be the best option available. Along maintenance routes, only limited cutting is anticipated. Therefore, little change to the existing slopes is anticipated. However, at some locations cutting may be inevitable I and at those locations, the options will have to be ,dealt with in the same manner as for the upgradation roads. 8.2.3 SOILS 3 Erosion The various mitigation measures proposed for erosion of soil include: | Planting road side vegetation * Providing brick or stone pitching on slopes steeper than 1 V: 2H. | Material for construction Though the commitment of the resources for the road construction is irreversible, environmentally sound techniques can be used for their extraction and transport, which would otherwise have adverse environmental impacts of their own. Since the rivers are to be protected from possible abuse, the project should consider using fine stone dust from crushing units instead of river sand. Mitigation measures include, for quarries and crushers: * Provision for screens and wind-breaking walls at crushers; * Provision for covering the vibrating screens as well as the conveyors for graded aggregate; * Provision of water sprinkling in crushing sites; * Plantation of broad leafed trees as vegetative screen. 3 For borrow areas, the works would be as per the relevant IRC guidelines (IRC 10: 1961). Transportation of Material * The material for construction for will travel considerable distances, especially debris and stone crusher dust which may be used as a substitute for sand as fine aggregate. The * vehicles used for these need to be covered with tarpaulin to avoid any dusting during transport. All the approach roads will be clear and motorable to prevent unnecessary spillage of material. Provision for watering the approach roads, stock-piles of material for I construction, etc., will be explored during the detailed EAs. The relevant clauses will be incorporated in the contracts for construction through EMP. Revised by Lea Associates 8-3 October 2001 I (Original Document by iCT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mitigation, Enhancement I 8.2.4 WATER The impacts on the water environment will be avoided or minimized by adopting measures which are already part of good engineering practice. Mitigation measures will include design of additional structures and their incorporation into the designs. Surface Water Resources Avoidance measures include changing the alignment of the road to avoid cutting into ponds, provision of embankment or retaining wall to prevent encroaching into storage area of a pond, etc. Mitigation measures will include contractual obligations for relocation of sources of water supply at location desired by the host community, excavation of volume of the waterbody equal to the volume filled up by the project, turfing of the embankment, provision of balancing culverts of adequate capacity where the level of the formation is being raised, provision for adequately sized drains in settlement areas to prevent flooding etc. All these measures form a part of the good engineering practice and should be part of the design drawings themselves. Additional mitigation measures include structures like oil interceptors and sedimentation chambers which are designed to remove the pollutants of concern rather than prevent their discharge. Provisions for safe disposal of wastes from construction workers' camps, especially if near water courses, should place the onus of the contractor by requiring the site to have a proper waste treatment and disposal system (usually a septic tank-soak pit combination will be sufficient). These measures need to be made an integral part of the contract by incorporating the same in the EMP. * Groundwater Resources Avoiding wells, handpumps and tubewells located close to the road will minimize the impacts on groundwater resources. Incorporation of these resources within slightly modified road cross sections would be the best. If they need to be removed, replacement of each unit at a location decided in consultation with the local residents who use the facility should be completed before the existing one is removed. Since the village councils in Mizoram are quite active, their inputs may be sought on the possible relocation sites within the nearest settlements. 3 Water Harvesting Structures The scarcity of water in Mizoram during the non-monsoon months will have to be tackled by the contractor out of his own resources. The project should look at the availability of space along the project route where water can be stored for the summer. These locations should preferably be permanent which can be handed over to the local residents at the end of the project so that their perennial water shortages can be reduced to a certain extent. l Revised by Lea Associates 8-4 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mitigation, Enhancement I 8.2.5 AIR Reduction in congestion due to better highway design being one of the objectives, an improvement in ambient air quality is expected to be one of the outcomes of the I proposed improvements. However, these may be offset by the projected increase in traffic. Since the project cannot directly influence the adverse impacts of the operation stage, the efforts are concentrated in reducing air pollution during the construction phase. Several provisions can be incorporated within the contract, through the EMP, to ensure that the deterioration in air quality is limited to the maximum extent possible. The notable I provisions are listed below: * The asphalt plants, crushers and the batching plants will be sited at least 1 km in the downwind direction from the nearest human settlement. * . All precautions to reduce the level of dust emissions from the hot mix plants, crushers and batching plants and other transportation of materials will be taken up including . Vehicles delivering loose and fine materials like sand and fine aggregates shall be covered to reduce spills on existing roads * Water will be sprayed on earthworks, temporary haulage and detour roads on a regular basis. During and after compaction of the sub-grade, water will be sprayed at regular * intervals to prevent dust generation. i The hot mix plant will be fitted with dust extraction units. . It shall be ensured that the dust emissions from the crusher and vibrating screen at the stone quarries do not exceed the emission standards set by Central Pollution Control Board. * Aizawl Bypass To minimize the possibility of increased air pollution through Aizawl city, the Priority Road would start operation only when the Bypass (BPI) becomes operative. This arrangement will ensure than induced/attracted traffic does not flow through the city of Aizawl, where air quality is already a concern. Disposal of Debris Since massive quantities of earthworks will be involved, including the cutting of the hill slopes for widening the roads, disposal of the excess cut material will be a major concern. The disposal of debris as fill for short sections where realignments are envisaged may be one option. But the volume that will be used will be miniscule. The presence of the sensitive flora (see later) within the project influence area further reduces the options available for the disposal of excess rock and soil cut. Some areas will have to be made no- go for disposal and at other locations only controlled tipping would be possible. Such locations, where disposal must be prohibited should be finalized along all the routes before the contractor moves to site. Gaseous Emission Control | To ensure the control of exhaust gas emissions from the various construction activities, the contractor shall take up the following mitigation measures: l Revised by Lea Associates 8-5 October 2001 * (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Envlronmental Mitigation, Enhancement . An adequate cyclone/scrubber to control emissions from the stack of hot mix plants will I need to be provided in the event of the emissions exceeding the SPCB norms. Other potential measures include plantation around periphery of the hot-mix plants. . To ensure the efficacy of the mitigation measures suggested, air quality monitoring shall I be carried out at least once a month during the period the plant is in operation. * All vehicles, equipment and machinery used for construction will be regularly maintained to ensure that the pollution emission levels conform to the SPCB norms. A vehicle y maintenance schedule prepared by the contractor and approved by the Engineer shall be adhered to. During the operation stage, the mitigation that the project can carry out is related more to * facilities for checking levels of pollution. Other more effective measures such as stricter emission standards and improved fuel quality are beyond the control of the project. The MPWD can only lobby for these at inter-departmental fora and co-ordinate with other agencies for an improvement in the overall air pollution scenario. Plantation may be important for filtering out some pollutants, most notably particulates. Though the benefits I are only token, roadside plantation must be encouraged for reasons elaborated in subsequent sections. 8.2.6 NOISE The contribution of project design towards mitigation of increased noise levels would be the improved riding surface and geometry, which will reduce vehicular noise generation, at least during the initial years after construction. The mitigation measures for noise are essentially aimed at protecting the receptor. During the construction stage, the most vulnerable population is the construction crew which is subjected to very high noise levels, a/beitintermittently. Provision of covering the equipment whose operation is noisy such as hammers, vibrators will be made a part of conditions of contract. In addition, supply of ear plugs will be made mandatory as part of I the Personal Protective Equipment (PPE) for the crew. Disturbance to the local populations will be prevented by specifying construction timings. No noisy construction activities will be permitted around the silence zones, a distance of 100m from the sensitive receptors as hospitals, educational institutions, etc. Blasting will be carried out as per provision of the Indian Explosives Act. Blasting will not be undertaken at night. Prior I intimation of the operational hours of the blasting will be given to the people living near such blasting sites. 8.2.7 BIODIVERsITY ISSUES The presence of orchids and Cyathea (with their associations with plants like Macaneia) on the roadside make several stretches of the road 'hotspots' from biodiversity perspective. The detailed EAs will have to provide the basis on which the site-specific | protection measures for saving these rare floral species will be implemented. In addition to the construction activities perse, the siting of labour camps, vehicle parking and storage areas, stockpiling of debris before final disposal, the choice of disposal sites Revised by Lea Associates 8-6 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mitigation, Enhancement will be determined based on the constraints imposed by species richness along certain * stretches of the routes. Designs of protection measures will be worked out for individual locations and management practices must be specified for stretches identified as important from a biodiversity perspective. 8.2.8 WILD-LIFE AND PROTECTED AREAS The concerns related to the disruption to wildlife and degradation of protected areas are specifically due to their presence close to the project routes. These concerns will be I effectively addressed by incorporating measures to avoid disturbance within the protected areas. Examples of such measures are: . Restricting construction in the vicinity of the area to periods when the chances of disturbing the protected species are minimum * Preventing any construction camp in the vicinity of the protected area | Siting polluting activities such as hot-mix plants, crushers and batching plants beyond a safe distance from the sensitive area . Ensuring that even the temporary works do not intrude upon the protected areas U . Training the workforce to handle chance-found endangered species C Co-ordinating the monitoring of the construction activities with the Forest department officials These measures will be developed further for the site specific conditions for each sensitive area after considering the species involved and its adaptability based on the past records, the proposed treatment to the road in the vicinity of the area, the extent of the area along the road in comparison to the total area designated as protected area. These improvised provisions will subsequently form a part of the Conditions of Contract by their inclusion into the EMP/ESMP as applicable. 8.2.9 SOCIAL ENVIRONMENT The Resettlement and Rehabilitation (R&R) policy has been prepared PWD based on World Bank's Operational Directives (O.D.) 4.30 and 4.20 for resettlement of involuntarily displaced persons and indigenous people. In particular; . Wherever possible, displacement will be reduced on or avoided altogether by sensitive I design of civil works (e.g. alternative designs or modification to the design). . Where displacement is unavoidable, those displaced will have their living standard improved. They will be located as a single unit among the peer groups or will be assisted I to integrate into their new community. Particular attention will be paid to the needs of the most vulnerable groups to be resettled. * PAPs will be compensated, at replacement cost, for assets lost. Adequate social and physical infrastructure will be provided. * PAPs and lost community would be encouraged to participate in the design and the implementation of RAP. An Entitlement Policy worked out at part of the R&IPDP will deliver a comprehensive package of compensation and assistance to entitled persons, families groups suffering Revised by Lea Associates 8-7 October 2001 (Original Document by ]CT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mitigation, Enhancement losses as a result of the project. Entitlements will provide practical measures for compensation and assistance which will mitigate the direct impacts of the road project on individual people and their property, as well as common property resources. It will provide mitigation for; * Loss of assets, including land and house or work place * Loss of livelihood or income opportunities Collective impact on groups such as loss of community infrastructure, common property resources, and others | All losses will be compensated and assistance will be provided at replacement value, irrespective of their legal standing in the project area. Special assistance will be extended to the vulnerable to enhance their earning opportunities. I Mitigation measures also will be worked out for the control of spread of highway diseases as part of the detailed EAs and control of ill effects of induced development. * Opportunities will be explored in the project for women development and encourage participation in the project. 8.2.10 ENHANCEMENT OPPORTUNITIES The following enhancement opportunities will be explored as part of the detailed EAs for the 2 project phases: * Biodiversity Conservation I . Day-tourism potential along roadsides * Water storage capacity for settlements I 8.3 RECOMMENDATIONS FOR EA The discussion of the various aspects of impacts of road project underlines need for 3 detailed investigations during the subsequent stages of project preparation and implementation due to a combination of the sensitivity of the project areas and the anticipated impacts of the road building activities. Following recommendations are made I. for the completion of the EA process during project preparation stage: Preparation of Environmental Impact Assessment: Detailed assessment of adverse I impacts, their mitigation and possible enhancement details need to be worked out for the upgradation routes, separately for each of the two phases of MSRP. The EIA would 3 include comprehensive treatment of the route-specific issues and impacts along with elaborate mitigation and enhancement measures. I Social Impact assessment and Preparation of Resettlement Action Plan: Social Impact Assessment of the project is an important component of project preparation. GOI I and GOM regulations and World Bank policy require social impact assessment during the design stage to avoid, reduce or mitigate potential negative impacts of project action and enhance positive impacts, sustainability and development benefits. Revised by Lea Associates 8-8 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 8 - Environmental Mit,gation, Enhancement The project's social impacts and resettlement component includes assessment of social impacts of the project and development of appropriate mitigation plans as required. These plans must comply with appropriate national and local laws and guidelines, and with World Bank policy directives. Social assessment is carried out in close co-ordination with environmental assessment team and design team and includes consultation and participation among project stakeholders, local communities and potentially affected I groups. As the involuntary displacement of tribals is expected to be a combined Resettlement and Rehabilitation Action Plan (RAP)-cum-Indigenous Peoples Development Plan needs to be prepared under MSRP for both the phases of the project. | The maintenance component of the project is not expected to directly affect the roadside properties and land takes. However, in case of any unavoidable direct impact a resettlement action plan would need to be prepared following the required World Bank I Guidelines and the persons would be entitled for compensation and assistance as per R&R policy of MSRP. Mizoram PWD will implement this RAP with assistance from other government agencies, and non-governmental- and community-based organisations, and consultants. Additional surveys need to be carried out to identify the existing status of spread of highway diseases and the general health status along the corridor during detailed social impact assessment and mitigation and control measures planned thereof. Special I attention needs to be given during data collection and consultation to the women likely to be affected due to the project. Information needs to be collected regarding their role in | the society to assess extent of vulnerability. Preparation of Environmental Management Plans (for the improvement/upgradation road): Route specific environmental management plans will have to be prepared for ensuring the implementation of the proposed measures during construction phase of the project. Implementation and supervision responsibilities, sufficient allocation of funds, timeframes for anticipated activities etc. should be dealt with in this document, which will eventually form a part of the Contract documents between the MPWD and the Contractor. Preparation of Environmental and Social Management Plan (for major maintenance works): The activities proposed under the maintenance component will be carried out I within the available clear space only. Consequently, the impacts would be substantial in terms of extent as well as intensity. To address these, a (generic) Environmental and Social Management Plan needs to be prepared for the maintenance routes. This document as part of the contract document shall ensure that the impacts of the proposed activities are managed with due regard for the social and biophysical environment in vicinity of major maintenance routes. Revised by Lea Associates 8-9 October 2001 I (Original Document by ICT, CES, LBII) l l CHAPTER-9 ENVIRONMENTAL MANAGEMENT | This chapter covers the management and monitoring mechanisms that are required to ensure that project implementation is carried out with the due regard for the environment. These include the measures that are to be carried out. Assigning I implementation and supervision responsibilities with adequate funds and powers will be important aspects of the proposed arrangements. l 9.1 OVERVIEW OF THE CRITICAL ISSUES The preceding chapters have dealt all environmental issues on a state-wide basis with a focus on the impacts directly linked to road construction and/or improvement works. The critical issues identified during this study and the screening carried out during feasibility, with special reference to the improvements proposed as part of MSRP are listed below: * Biodiversity Conservation . Dumping of construction wastes * Harvesting of water for construction * Geological stability I . Vulnerability to landslides and erosion * Social impacts (R&R) on Mizo population Implementation of appropriate mitigation measures during the design, construction and operation stages shall reduce the negative impacts of the project to acceptable levels. To ensure that these mitigation measures are implemented, arrangements need to be worked out that the design and specification of the appropriate measures be inbuilt into the contract document and specifications for the project. This needs to done through the * incorporation of the Environmental Provisions as a part of the contract document. Realising the criticality of the various issues, especially in terms of critical issues as landslides, water harvesting, dumping sites etc, the EMPs need to work out the locations and the extent of treatments/measures at each of those locations. However, it becomes imperative that the effective mitigation in many a case will depend on the ground I situation during the construction, which needs to be evaluated by the Environmental Specialist of the Supervision Consultant. l 3 Revised by Lea Associates 9-1 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project- Phase I SEA: 9 - Environmental Management 9.2 ENVIRONMENTAL MANAGEMENT PLANS 9.2.1 EMP FOR UPGRADATION ROUTE The environmental management plans provide the basis for including the environmental provisions recommended by the environmental impact assessment study into the Conditions of Contract for construction phase and into the operation phase. As a standalone document, the EMP is required to: . Provide contractors with sufficient information about the anticipated environmental impacts I of the project, * Detail out and provide Implementable designs for mitigation and enhancement measures to be implemented without any additional information. The EMP shall be prepared to include the following: • An overview of the project, a brief description of the project route and proposed treatment along with anticipated adverse impacts would give a feel to the contractor regarding the sensitivity of the work area. * the budgetary provisions for each activity, the responsibilities for implementation and supervision in sufficient detail to resolve any conflicts. * the implementation schedule and monitoring schedules The format which could provide the basic skeleton of the environmental management * plans (EMPs) detailing out the timing, management actions and responsibilities for each action along the upgradation route is presented below in Table 9-1. This shall form the * basis for the working out the task assignment for specific mitigation and enhancement measures, based on the significance of the anticipated impacts during the detailed assessment to follow in the next stage. Table 9-1 Format for EMP for Priority route l Environmental | Enhancement/ Mitigation Reference to Management Implementation Issues/ Impacts I measures (specify locations Contract Actions Responsibilities where applicable) Documents AtosRsosblte Pre-Construction Phase * P.1.n Construction Phase C.L.n Operational Phase w O~~~~.1.nllll 9.2.2 ENVIRONMENTAL & SOCIAL MANAGEMENT PLAN At this stage, it is anticipated that due to the limited nature of major maintenance work, this component can proceed with an Environmental and Social Management Plan rather than a full EIA. Management actions, similar to the ones for up gradation routes can be worked out for the major maintenance routes. However, since the impacts anticipated at * this stage are of much lower intensity, the proposed mitigation measures are essentially corrective. Table 9-2 is the suggested format for the impacts that are envisaged at this Revised by Lea Associates 9-2 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 9 - Environmental Management stage. In these cases, the suggested measures that can be incorporated in a generic Environmental and Social Management Plan are provided in table 9-3. Table 9-2: Format for ESMP to be prepared for Maintenance routes Environmental Mitigation Reference to Contract Location Responsibility Impact/lssue Measure Documents I l | Implementation Supervision Construction Stage C.1.n l l O eration Staqe O.1.n Table 9-3: Format for ESMP in case of unforeseen impacts at specific locations Reference to Responsibility Environmental Impact/Issue Mitigation Measures Contract Location Documents Implementation Supervision A.1.1 Clearance of vegetation A. 1.2 Disposal of waste from I removal of pavement A.1.3 Water harvesting for construction * A.1.4 Removal of Community Utility A.1.4 Land slide locations and geological stability A.1.5 Relocation of Cultural Property I A.1.6 Impact on ecological resources, wildlife habitats etc. I A.1 8 I 9.3 GENERIC MONITORING PLAN Monitoring plans form the basis for verifying the extent of compliance during the implementation and operation stages of the project. They provide periodic feedback for | project management to keep the programme on schedule. Monitoring plans should describe the objectives and rationale for monitoring, the parameters to be monitored, the methodology to be adopted, frequency of monitoring and responsible agencies. The relevant standards with which comparisons are to be made and triggers beyond which remedial actions need to be initiated should be specified for each parameter. These would form the basis for evaluating the effectiveness of the measures proposed as well as of monitoring progress in a given task over the duration specified in the overall management plan. Table 9-4 gives a prototype-monitoring plan, which could be used for the EMPs of upgradation as well as the generic ESMP for maintenance routes. l Revised by Lea Associates 9-3 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 9 - Environmental Management Table 9-4: Monitoring Plan format for EMPs and ESMP Env. Project Institutional oamp Stage Monitoring Responsibility onent Parameter | Method | Standards Location DFrequency Dratio Implem Supervi 3lApPlicable n entation sian The parameters to be monitored need to be worked out in accordance to the project needs and requirements. As they are identified during the course of the detailed environmental assessments. I I I I l I I l l Revised by Lea Associates 9-4 October 2001 U ~ ~~(Original Document by [CT, CES, LBII) l CHAPTER-1 0 IMPLEMENTATION ARRANGEMENTS I The PWD has extensive experience in building and maintaining roads over the years. However, the traditional emphasis on least-cost solutions is now shifting towards quality construction with other concerns such as environmental conservation. The organisational set-up of the PWD and modifications required in order to meet these new challenges are discussed in the following sections. This chapter discusses the implementation arrangements including the reporting, monitoring and training requirements for the project. I 10.1 INSTITUTIONAL ARRANGEMENTS The MSRP will be implemented by the Public Works Department. The PWD headed by the Engineer-in-chief, is responsible for the effective implementation of the project activities. The PWD has appointed the Project Co-ordinating Consultants (PCC) for providing assistance in preparation and implementation of the project. To effectively oversee the project preparation and to ensure the timely implementation of the project, a Project Implementation Unit (PIU) has been established. The Project Director heads the Project Implementation Unit (PIU), which at present includes 3 Executive Engineers, looking into the Procurement, Environment and Social Aspects. Each of these executive engineers are assisted by an Assistant engineer for carrying out their responsibilities. The PIU is expected to play a key role in implementation of the project including the overall control of construction activities and implementation of contracts. During the implementation the upgradation components, the PIU will be assisted by Supervision Consultants. The SC will assume the role of the Engineer and ensure construction in an environmentally sound manner through their Environmental Specialist. The monitoring of Construction Activities by the PIU will be carried out in conjunction with the Mizoram Pollution Control Board Officials for the pollution component (Air, Water, Noise). For the implementation of R&R activities, local NGO will be procured. The following figure shows the proposed set up for the implementation of MSRP. I 10.1.1 PIU- ENVIRONMENTAL CELL The implementation of the environmental mitigation measures would be the responsibility of the Environmental Cell of the PIU, comprising the Executive Engineer (environment) assisted by an Assistant Engineer. With appropriate training and exposure, the existing 3 setup would become competent to implement the EMP. The setup may be further modified and strengthened, as the project is implemented. | The Environmental Cell will be assigned with specific responsibilities with regard to: Revised by Lea Associates 10-1 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements * Monitoring progress of the project, on the implementation of the environmental provisions, as per planned schedule of activities. . Supervising implementation of mitigation measures by the contractor along the upgradation routes. I . Assist the PWD Engineers at site by providing appropriate environmental advice, and developing appropriate mitigation measures, along the maintenance routes. . Documenting the experience in the implementation of the environmental process. I . In collaboration with the Environmental Specialist of the Supervision Consultant, prepare and conduct training materials for the Public Works Department by incorporating the experience of implementation processes and other issues concerning protection of the I environment. * Maintaining ongoing interfaces with the other relevant institutions in the context of the works. The Environmental Cell of the PIU will ensure that all the EMP mitigation measures would be implemented fully and that it will prepare regular progress reports for transmission to the regulatory authority by certifying that the relevant environmental measures have been complied with during project implementation. The specific roles and responsibilities of the Environmental Engineer and the Assistant Environmental Engineer are presented in the following section. | Environmental Engineer The overall responsibility of the Environmental Engineer will be to guide and assist the PIU and the PWD to develop, implement and strengthen the environmental management practices in highway development projects for the current and future projects in Mizoram, drawing upon the experiences gained in the implementation of the MSRP. The principal 1 duties entrusted to the Environmental Engineer include: * Review the preparation of the Environmental Assessments for the project and finalization in close co-ordination with the World Bank; I . Ensure that the project design and specification adequately reflect the Environmental Management Plan; . Co-ordinate the obtaining of requisite Environmental Clearances for the project; I * Develop training programme for the PWD staff, the contractors and others involved in the project implementation, in collaboration with the Environmental Specialist of the Supervision Consultant; * . Review and approve the Contractor's Implementation Plan for the environmental measures, as per the EMP; a Liase with the Contractors, Supervision Consultants and the PCC on the implementation of the EMP; * Liase with the various Central and State Government agencies on environmental and other regulatory matters; * * Continuously interact with the NGOs and Community groups to be involved in the project (for the maintenance of additional plantation suggested for the project); | Establish dialogue with the affected communities and ensure that the environmental concerns and suggestions are incorporated and implemented in the project; * Review the environmental performance of the project through an assessment of the periodic environmental monitoring reports submitted by the Supervision Consultants; Revised by Lea Associates 10-2 October 2001 * (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements provide a summary of the same to the Project Director, and initiate necessary follow-up actions; * Provide support and assistance to the Government Agencies and the World Bank to supervise the implementation of the EMP during the construction as well as operation I stage of the project; . Document the good practices in the project on incorporation and integration of environmental issues into engineering design and on implementing measures in the road I construction and maintenance programs, and dissemination of the same. This shall form a useful tool to other similar agencies in other parts of the country especially on the environmental management of hill roads; . Report to the Project Director on the environmental aspects pertaining to the project. Assistant Environmental Engineer | Reporting to the Environmental Engineer, the Assistant Environmental Engineer (AEE) shall play a key role in the implementation of the EMP. The principal duties assigned to | the AEE shall be as follows: * Review the preparation of the Environmental Assessments for the project; * Liase with various Governmental Agencies during the obtaining of requisite Environmental I Clearances for the project; e Assist the Environment Engineer and the Environmental Specialist of the SC in preparation of the training materials and in conducting training; I . Review the Contractor's Implementation Plan for the environmental measures, as per the EMP along with the Environmental Specialist of the Supervision consultant; _ Liase with the Contractors, Supervision Consultants and the PCC on the implementation of I the EMP; l iase with the various Central and State Government agencies on environmental and other regulatory matters; 3 . Carrying out consultations with the NGOs and Community groups to be involved in the project (for the maintenance of additional plantation suggested for the project); * Establish dialogue with the affected communities and ensure that the environmental I concerns and suggestions are incorporated and implemented in the project; * Carry out site inspections, check and supervise periodic environmental monitoring, carried out by the Supervision Consultants and other monitoring agency, and initiate necessary follow-up actions; . Document the good practices in the project on incorporation and integration of environmental issues into engineering design and on implementing measures in the road I construction and maintenance programs, and dissemination of the same. * Report to the Environment Engineer / Project Director on the environmental aspects pertaining to the project 3 . Prepare periodic (monthly, quarterly and annual) reports for dissemination to the PIU, World Bank etc. I 10.1.2 PROJECT CO-ORDINATING CONSULTANTS The Project Co-ordinating Consultants have been appointed to assist the PIU during | project preparation. The Environmental and Social experts of the PCC have been responsible for the preparation of EA documents including the EMP. The major inputs of the PCC will end with project appraisal. However, their specialist technical inputs will continue within the project duration. Revised by Lea Associates 10-3 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements I 10.1.3 SUPERVISION CONSULTANTS The Construction Supervision Consultants (CSC), to be selected through ICB, are expected to have the in-house capacity to advise on and supervise the implementation of the EMP I including making the decisions regarding applicability of enhancement design options and any modifications, if needed. For this purpose, the CSC will employ full time environmental specialist. The prime duty of the Environmental Specialist would be to * supervise the implementation of the EMP by the Contractors and to ensure that the day- to-day construction activities are carried out in an environmentally sound and sustainable manner. The scope includes development of environmental procedures and good construction practices, development and delivery of training programmes etc. | Environmental Specialist - Supervision Consultant The Environmental Specialist, a civil engineer preferably with postgraduate specialization in environmental engineering, will have 15 years of working experience related to the integration of environmental and social issues in the design, construction and operation of transport projects. Experience in construction management and operational maintenance of highways is preferred. The specific roles and responsibilities of the Environmental Specialist (of the Supervision Consultant) is presented below: | Supervise the implementation of the EMP by the Contractors. I Develop, organise and deliver environmental training programmes and workshops for the staff of the PIU, Contractors (of both upgradation and maintenance routes), Field Supervision Staff, PWD officials (responsible for the supervision of the Maintenance works) I and the Quality Auditors. i Review and approve site specific environmental enhancement/mitigation designs worked out by the Contractor (for water falls, bio-diversity rich locations etc) * Hold regular consultation meetings with the Environmental Cell in the PIU R Review the Contractors' Environmental Implementation Plans to ensure compliance with the Environmental Management Plan (EMP) * . Develop good practice construction guidelines to assist the contractors in implementing the EMP * Monitor tree plantation programmes and the periodic environmental monitoring (air, noise, I water, etc.) programmes to ensure compliance with the State requirements and the EMP * Prepare and submit regular environmental monitoring and implementation progress reports | Assist Environmental Cell to prepare good practice dissemination notes based on the experience gained from site supervision I 10.1.4 NON-GOVERNMENTAL ORGANISATIONS As part of the project implementation, the MSRP plans to undertake plantation and maintenance and protection of the vegetation along the project roads (in addition to the compensatory afforestation that has been proposed by the Forest Department, Government of Mizoram). The maintenance of these plantations would be entrusted to an 3 NGO. The environmental responsibilities of the NGO include the maintenance of roadside plantations and conservation of biodiversity. The specific roles and responsibilities of the NGO include: * Provide, plant and maintain three year old saplings on the valley side along the Free lands and Unclassified forest lands along the project road and along either sides of the road in Revised by Lea Associates 10-4 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements sections through non-hilly terrain. Indigenous species would be selected for plantation, and maintained for five years, including protection and monitoring of the survival. . Undertake adequate measures to ensure maximum survival of the saplings during transportation to the site, and post plantation by proper handling and maintenance. I . Ensure proper watering, removal of weed, litter and debris from the vicinity of the plantation. The NGO will ensure the protection of the fencing provided to the saplings from trampling and browsing by the cattle. I . Identify locations of medicinal plants and other endangered plant species, and create awareness amongst the population, the importance of the conservation of the same. . Conduct awareness campaigns for the settlements around Aibawk, against poaching of I Chinese Pangolins. * Periodically visit the construction activities in the Ecological Identity Areas identified along the corridor and ensure that the construction activities are taken with due precautionary I arrangements. In case of any non-compliance, will report to the Environmental Engineer of the PIU and the Environmental Specialist of the Supervision consultant for further action * Will depute 4 personnel (preferably graduates) to undergo training by the Environmental Specialist of the SC, or for participation in other income generation programmes as Orchid cultivation, creation of gene pools for medicinal plants etc. These trained personnel will in turn carry out training in each of the project villages, in co-ordination with the Village * Councils. Note that NGOs will be procured to assist in implementation of the R&IPDBP also. I 10.1.5 QUALIrY ASSURANCE CONSULTANTS For the major maintenance component, the supervision will be carried out by the PIU I through the local PWD Divisions. A quality assurance consultant will undertake periodic supervision to ensure the quality of the works and workmanship. Since the environmental concerns along maintenance corridors are few, the environmental expertise required for | these will be limited. However, it is expected that the QA Consultants, who are to be procured under National Competitive Bidding, will have sufficient staff, albeit part-time to ensure that the provisions of the Environmental and Social Management Plan (ESMP) are implemented in letter as well as spirit along all the routes under maintenance. Further, the QA Consultant will impart training to the Contractors and the PWD staff, similar in | content and coverage as has been proposed for the Environmental Specialist of the Supervision Consultants. The Contract Documents for the major maintenance works are being suitably modified to incorporate these requirements. 10.1.6 CONTRACTORS The execution of the works will be responsibility of the contractor. It is expected that the environmental measures will also be implemented by the same contractor who executes the road works. This will ensure that the construction of the road and I mitigation/enhancement designs will progress smoothly and efficiently. It follows that the contractor has enough environmental/social expertise to incorporate environmentally- sensitised construction practices. As executioners of the EMPs and ESMP, the contractors * are expected to follow the letter and spirit of the specifications. Though each contractor will have a set-up for executing works specified in the EMP, it is expected that a certain portion of its staff will have enough environmental awareness necessary for the successful completion of the works entrusted. Revised by Lea Associates 10-5 October 2001 (Original Document by ICT, CES, LBII) Mtzoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements The Contractors too will have to employ an Environmental Engineer. The best situation would be the use of Civil Engineers with relevant implementation experience of highway projects and with an understanding of the environmental issues. The roles and | responsibilities that shall be entrusted to the Environmental Engineer shall be as follows: . Develop and detail out an implementation plan for the Environmental Provisions as envisaged in the EMP, and get it approved by the SC . Continuously interact with the Environmental Specialist of the SC and the Environmental Cell of the PIU regarding the implementation of the environmental provisions; & Identify suitable locations for siting of labour camps, construction waste disposal locations, construction and vehicle parking/maintenance sites and obtain the approval of the Environmental Specialist of the SC of the same. * Ensure the implementation of the various mitigation measures proposed for the protection of bio diversity etc, prior to the commencement of construction activities at that particular sub-section of the project road. * Ensure that proper environmental safeguards are being maintained at borrow sites and quarries from which the contractor procures material for construction. I * Supervise the proper construction and maintenance of the facilities for the labour camps, including the provisions for the safety and health of workers and their families. | Ensure that proper facilities are available for the monitoring of ambient air quality and collection of water and soil samples as provided for in the environmental monitoring plan * Liase with the various Government Agencies (including the State Pollution Control Board) during the construction period and obtain the requisite clearances Carry out the measurement of quantities for environmental enhancement, prepare the bills of quantities for the work carried out for enhancement. 10.2 TRAINING THE ENVIRONMENTAL CELL - PIU & PWD I 10.2.1 NEED FOR TRAINING The Environmental Cell of the PIU is already in place. However, the lack of environmental and social expertise and sensitivity of the PWD, has been mitigated to a certain extent due to the exposure to the preparation of the Environmental Assessments for the MSRP, is a matter of concern. This deficiency should be mitigated as soon as possible to enable I the PWD in integrating the social and environmental issues in its day-to-day operation and in internalising the environmental and social issues in the future road development projects. To achieve this goal, the Environmental Cell at the PIU, need to be trained on road development and environment management and the effective implementation of the environmental issues. 10.2.2 TARGETS OF PROPOSED TRAINING | The training programme should equip the members of the Environmental cell to implement and supervise the EMP and expose senior members of the PWD to environmental and social issues associated with the highway projects. Such a group of senior staff can then be given the responsibility of active dissemination of the culture of environmental/social consciousness and ethics within the rest of the organisation. Revised by Lea Associates 10-6 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements Once the staff of the Environmental Cell have received training and have gained * experience through the implementation of the EMP, they should be ready to resume leadership role within the PWD in providing training and in implementing future projects. 3 In order to disseminate environmental experience gained by the PWD, each staff would be required to maintain good records and prepare dissemination notes on specific issues and problems encountered and resolved, and how the experience gained could be I integrated in future road projects. Competent members of the PWD should be offered additional environmental training and should be encouraged to train other staff. 10.2.3 TRAINING COMPONENTS 3 The environmental training aspects of the Environmental staff of the PIU should encompass the following: * Understanding of the relevant environmental regulations and their application to the I project. * Environmental management practices in hill roads upgradation and maintenance * Main impacts of the project on the environment. I . Mitigation measures as given in the EMP and their implementation through incorporation in the design, construction supervision and monitoring. * Duties and responsibilities of the Contractors, Supervisor Engineers, Supervision Consultants and the PIU. * Public/community consultation and its role during the implementation of the project. | Liaison with other departments and relevant agencies (such as Forestry). * Supervision of the implementation of the EMP and social issues during construction and operation. Resolution of environmental and social issues and their reporting. | Monitoring during construction and operation. * Weekly, monthly and quarterly report preparations and submission. * Preparation of dissemination notes, holding of workshops, and training of other staff in PWD. The training modules will be worked out for the project and will be of relevance to the specific context of the roads in Mizoram, focussing on the following issues: * Conservation of biodiversity * Slope stability and vulnerability to landslides | Siting criteria for identification of dumping sites Harnessing water resources, including rain water harvesting . Concepts of bio-engineering. The training modules suggested are given in the Table-10-1. I Table 10.1: Training Modules for Environmental Management TS. nngMoeEnvironmental Aspects Training Conducting No. Training Recipients Mode of Training to be moduentrlAiects Agency 1 Environmental staff of Lecture System Environmental overview Environmental Specialist, "Environmental and Social Workshops Environmental Regulations Supervision consultant Management Cell". Group Discussion and Acts Associated NGOs in Short term training course Environmental issues implementation and PIU associated with hill road staff associated with projects Revised by Lea Associates 10-7 October 2001 (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements l No. Training Recipients Mode of Training eion enta t Training Conducting _____ ____ _____ ____m odule construction supervision Environmental management Plan Environmentally sound s ~~~~~~~~~~~~~~~~~~~~construction management Planning for environmental sustainable operation of hill roads __ Long term environmental issues in road management 2 All PIU staff construction Seminar Environmental overview Environmental Specialist, supervision consultant and Workshop Environmental Impact Supervision consultant contractors Lectures Assessment Environmental Management Plan Implementation Environmental Regulations I and Acts Environmental pollution associated with road projects Environmentally sound construction management Road Projects and Environmental Issues 3 All PIU staff and Executive Short term training courses Environmental overview Environmental Specialist, Engineers and PWD Visit to case studies Environmental Regulations Supervision consultant, officials associated with the Seminar and Acts Environmental Cell, PIU project routes Environmental Pollution Road projects and I environmental issues EMP for road projects 4 Collaborating Government Audio Visual Environmental Overview Environmental Cell of PIU Agencies such as Pollution Communication Environmental Regulations and PCC Consultant Control Board, Traffic and Information Training and Acts Transport Departments, Environmental Pollution State Forest Department etc. and all staff of PWD 5 All staff of PIU entrusted Short term training course Theoretical course to Extemal agency. with environmental related environmental impact matters assessment and procedures. Environmental Regulations, Acts and Clearance procedures. Environmental data acquisition and monitoring analysis. Hands on training on compliance monitoring and operation stage monitoring. 7 PIU Staff for Environmental Visits to case study areas Bio-Engineering Methods Environmental Specialist, related matters and expert lectures Nater Harvesting Supervision consultant Techniques Biodiversity Preservation :Disposal of Construction Naste 10.3 REPORTING SYSTEM Reporting system provides the necessary feedback for project management to ensure quality of the works and that the program is on schedule. The rationale for a reporting I system is based on accountability to ensure that the measures proposed as part of the Environmental Management Plan get implemented in the project. Revised by Lea Associates 10-8 October 2001 (Original Document by ICT, CES, LBII) l Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements l The reporting system will operate linearly with the contractor reporting to the Supervision Consultant, who in turn shall report to the PIU. All reporting by the contractor and Supervision Consultant shall be on a quarterly basis. The PIU shall be responsible for preparing targets for each of the identified EMP activities. All subsequent reporting by the I contractor shall be monitored as per these targets set by the PIU before the contractors move on to the site. The reporting by the Contractor will be a monthly report like report of progress on construction and will form the basis for monitoring by the PIU, either by its own Environmental Engineer/s or the Environmental Specialist hired by the Supervision Consultant. The monitoring and the subsequent reporting would include: I . Monitoring of facilities at construction camps * Monitoring of air, noise, soil and water parameters including silt load | Monitoring of survival rate of trees planted on valley slopes * Monitoring of cleaning of drains and water bodies * Monitoring for biodiversity - protection measures during construction phase . Monitoring of bio-engineering measures suggested Table 10.2: Desired Monitoring and Reporting Process and Responsibilities 1 Supervision Consultant Project Implementation World Bank Contractor (SC) Cell (PIU) (WB) Fo.a Item Implementatio Overseel Field No. Item n and Reporting to Compliance RepoB to Desioed Reporting to PIU Monitrngg Ws Supervision _ _ _ ~~~SC_ _ _j_ CONSTRUcTION PHASE ci C2 OPErSATON PHASE 01 I ~~~~~~02 10.4 ENVIRONMENTAL MONITORING PLAN The purpose of the monitoring programme is to ensure that the envisaged purpose of the project are achieved and result in desired benefits to the target population. To ensure the effective implementation of the EMP, it is essential that an effective monitoring * programme be designed and carried out. The environmental monitoring programme provides such information on which management decision may be taken during | construction and operational phases. It provides basis for evaluating the efficiency of mitigation and enhancement measures and suggest further actions that need to be taken * to achieve the desired effect. The monitoring includes: * Visual observations; I * Selection of environmental parameters at specific locations; * Sampling and regular testing of these parameters. I Revised by Lea Associates 10-9 October 2001 I (Original Document by ICT, CES, LBII) Mizoram State Roads Project - Phase I SEA: 10 - Implementation Arrangements Environmental monitoring of the parameters involved and the threshold limits specified are discussed below. The details of the various monitoring indicators and their thresholds are described in the Environmental Management Plan. I 10.5 ENVIRONMENTAL BUDGET The Environmental Assessment and its incorporation into the designs and the contract documents have been taken up at all stages of the preparation and will continue during the implementation of the project. As part of good engineering practices in the project, there have been several measures as erosion prevention, rehabilitation of borrow areas, I safety, signage, provision of temporary drains, etc the costs for which are included in the engineering costs. Therefore, these items of costs have not been included in the EMP budget. Only those items not covered under budgets for construction and RAP are shown in the EMP budget. The EMP costs include: a Mitigation / Enhancement Costs * . Monitoring Costs * Training and Mobilisation Costs 3 Advocacy and Policy Making Costs. The summary budget for the Environmental management costs for the Upgradation and Major Maintenance Routes to be taken up in Phases I and II of the project are presented X in the Table 10.3. In addition to the heads listed below, a contingency of 5% has been provided (The budget for the Phase II are estimates based on worst case scenario and need to be firmed up during the detailed EA). I Table 10.3: Environmental Budget - Phase I& II (INR in million) Phase I Phase II Budget Head Upgradation / Major Upgradation / Major Improvement Maintenance Improvement Maintenance Mitigation/Enhancement 7.92 5.88 12.92 6.35 Monitoring 1.65 2.96 2.20 3.20 Training and Mobilisation 5.08 0.50 0 0.63 Total 14.65 9.34 15.12 10.18 Revised by Lea Associates 10-10 October 2001 (Original Document by ICT, CES, LBII) ANNEXURES Mlior(vn State Roads Project Sectoral Envi-on,nental Assessment Annexure 4.1 | _____ List of landslide locations along the project road Roads Surveyed Chainage Pi Km. 2+110, 5+815, 8+050, 11+685, 15+635, 19+160, 25+185, 28+000, 38+470, 43+030, 46+030, 46+000, 56+340, 64+885, 73+700, 78+130, 85-840, 94+048, 98+907, 121+700, 132+160, 146+200, 155+230, 1629-330. P2 Km 0+100, 1+050, Km. 2+040 to 2+275, 3+605 to 3+690, 4+467, 4+794, 4+910, 11+435, 13+220, 15+000, 16+780, 16+840, 19+050, 21+850, 22+180, 23+760, 24+100, 277-500, 30+580, 31+500, 35+485, 43; 000, 49+700 * P3 Km. 1+125, 4+175, 4+100, 5+800, 8+420, 11+840, 11+900, 10+300, 10+800, 13+460, 14+920,17+050, 17+700, 48+000, 23+800, 25+630, 27+760, 26+430, 28+240, 31+500, 35+820 BI Km 11 +440 to 11 +460, 3+290, 7+760 B2 Km. 0-700, 2+400, 4+390, 5-+900, 5+020 ml Km. 14+300, 27+800, 38+600, 39+300, 40+300, 43+200, 44+100, 60+450, 65+660, 73+740. M2 Km. 33+300, 36+660, 46+805, 47+890. M3 Near to 3.5 Km. M4 Km. 0-i-680, 21+400 M5 Km. 0+815, 2+575, 7+260, 7+445, 7+730, 11+960. * M6 Km. 15+275, 16+650 M7 Km. 41+700, 56+880, 61+880 I Ms Km. 5+100, 6+900, 12+545, 29+890, 34+645, 37+520, 388+930, 44+895, 59+500, 73+315, 78+500, 84+150. M9 Km . 0-845, 2+250, 5+530, 5+675, 9+875, 65+320, 67+390, 70+000, 73+900 MIO Km 7+300, 10+320, 11+800, 12+200, 51+050, 63+230, 75-600 Mlt 1 Km. 2+000, 8+200, 28+000, 28+320, 30+600, 31+000 M12 Km. 3+180, 8+000, 9+000, 14+000, 27+000, 37+000 I M113 Km. approximately 11+000,17+000,19+000, 22+000, 26+000, 3 1+000 M14 Km. approximately 7+000, 11+000, 14+000, 19+000, 22+000, 23±000,26+000 Note: AIU to .m14 roads .- i. Based on motor vehicle oedometer Revised by Lea Associates October 2001 (Original Document by ICT. CES, LII) IlH-AhMizoram State RoadS Plroiect Sector'al E1ivilroIllletntaZ ,4ssessmenr Annexure 4.2 Primary Water Quality Standards Designated Best Use Class of Water Criteria 1. Total Coliforms MPN/100ml shall be 50 or less | ~~~Drinkin-, water source i w A 2. pH between 6.5 to 8.5 (with conventional treatment) 3. Dissolved Oxygen 6 mg/I or more 4. Biochemical Oxygen Demand (BOD) 5 days 20 °C 2 mg/l or less 1. Total Coliforms MPN/100 ml shall be 500 or less Outdoor bathing B 2. pH between 6.5 to 8.5 (Organised) 3. Dissolved Oxygen 5 mg/l or more 4. Biochemical Oxygen Demand (BOD) 5 days 20 °C 3 mg/l or less Drinking Water Source 1. Total Coliforms MPN/100 ml shall be 5000 or less I Drinking Water Source C 2 Hbten6t (without conventional 31 treatment) 3. Dissolved Oxygen 4 mg/l or more 4. Biochemical Oxygen Demand (BOD) 5 days 20 °C 3 mg/l or less 1. pH between 6.5 to 8.5 for Fisheries Propagation of D 2. Dissolved Oxygen 4 mg/l or more Wildlife 3. Free Ammonia (as N) 1.2 mg/l or less 5 1. pH between 6.0 or 8.5 Irrigation, Industrial E 2. Electrical Conductivity at 25 'C jtmhos/cm Max Cooling, Controlled Waste 2250 3. Sodium absorption ratio Max. 26 l 1 14. Boron, Max. 2 mg/l Ref: CPCB (I 999). Bio-Mlappinig of rivers. Parivesh News Letter, 5(iv), Central Polliatioji Control Board, Delh i, pp. 20 Revised by Lea Associates October 2001 I (Original Document by ICT, CES, LBII) i/tl:oraln StatC Roads Prjo/ct Secroral Environmental Assessmnent I Annexure 4.3 | National Ambient Air Quality Standards Pollitant Time | Sensitive Industrial Residential, Method of WeiThted I Area Area Rural and Mleasurement Average Other Areas Annual* 15pg/mn' 80lg/m' 60pg/m' Improved West and Sulphur I Gaeke NMethod Dioxide So2 24 hours** 30pgoh1 120ug/nl' 80pg/m11' Ultraviolet l ~~~~~~~~~Fluorescence Annual* 15 ug/m' 80uag/m' 60tig/m' Jacab & Hochheriser Oxide of NModified (Naarseite) S Nitrouen as method No, 24 hours** 30pg/m' 120ptg/m' SOpg/m'i Gas phase Chemilumines cence Annual* 70pigIm' 360pg/m' 140pg/m' High Volume Suspended Sampling I ~~~~~participate __ Matter 24 hours** lOOpg/m' 500lig/ml 200pg/m' (Average flow rate not (SPMI) less than 1.Im3/minute) Carbon 8 hours** 1.0 mg/m' 5.0 mg/mr 2.0 mg/m' Non-dispersive infra Monoxide red (CO) 1 hour 2.0 mg/m' 10.0 mg/mr 4.0 mg/m' Spectroscopy I q I I I I Revised by Lea Associates October 2001 (Original Document by ICT, CES. LBII) Xtizora,i- State Roads Piolect Sectoral Environmewtal Assessmlenit Annexure 4.4 National Ambient Noise Standards Area Code Category of Limit Leq in dB(A) l I Zone Davs Night A Industrial 75 70 B Commercial 65 55 * Residential 55 45 D Silence Zone 50 40 l l l l l l l I l Revised by Lea Associates October 2001 I (Original Document by [CT, CES, LBII) ,A/i0oramtn Staire Roads P,o,w ct Sectoral Envi,-o?znentaIl .4ssessmneao1t Annexure 4.5 Plant Species Having Ethnomedicinal Importance Si. Plant Species Local Name Locality Uses Part Used I Adina Cordifolia Lungkhup Ralvawng Stomach Ulcer |Bark- 2_9 Aeschynanthus Bawltehlantai Bualte Breast Cancer Crushed & Sikkimensi's Boiled 3 Alocasia Fornicata Baibing Lengpui Snake Bite Juice l 4 Alstonia Sclholaris Thuamriat Darlung Typhoid Bark 5 Ampelocissus Latifolia Hruipawl Chawnhu Tooth Ache Whole 6 Aporosa Octandra Chhawntual Chawnhu Stomach Ulcer Bark 7 Artemisia Indica Sai Khawbung Stomach Ulcer Leaf 8 Berginia Ciliata Khamdamdawi Farkwan Diarrhoea & Stem Dysentery 9 Bidens Biternata Chabet Ratu Rheumatism Stem 10 Blunlea Laciniata Khuanglawi Lengpui Snake Bite Root I Bluimea Lancelolaria Buarze Serchhip Stomach Ache Leaf 12 Callicarpa Arborea Hnahkiah Darlawn Cuts & Wounds Bark 13 Cassia Alata Tuihlo Lawngtlai Ring Wonns Leaf 14 Centella Asiatica Lambak Lungdai Heart Disease Whole 15 Chonemorplia Fragrans Theilkelki Suak Ralvawng Stomach Ulcer Root 16 Chromoleana Odorata Tlangsam Khawbung Cuts & Wounds Leaf 17 Chilkrassia Tabularis Zawngtei Bualte Diarrhoea & Bark Gastritis 18 Cinnamomum Thakthingsuak Sihphir Liver Disorder Bark Bej olghota | 19 Cinnamomul'm Verum Thakthing Sihphir Cough & Leaf Vomiting_ 20 ClerodendruLrn Phuihnam Bukpui Hypertension Leaf Colebrookianum 2 1 Costus Specious Sumbul Sihphir Venereal Disease Rhizomes 22 Dendrocnide Sinuata Thakpui Tamdil Retain Placenta Leaf 23 Diospyros Variegata Raisentur Lungrang Diarrhoea & Bark |__ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Dysentery 24 Dysoxylumn Gobara Thingthupui Kawnpui Stomach Leaf Problem 25 Elaeagnus Caudata Sarzuk Chaltlang Retain Placenta Leaf 26 Engelhardtia Spicata Hnum Vangtlang Diarrhoea & Bark Dysentery Revised by Lea Associates October 2(001 * (Ori-iinal Document by [CT, CES, LBII) Alizoiwoan Stitec Roads P7r0j/CL Sectorozl En i7oo zeitrol ,1ssessm ieatr Si. 1 Plant Species Local Name Locality Uses Part Used No. 1 ! 27 Ficus Benjamina Zamanhmawng Lungsen Malarial Fever Bark 9 28 - Garcinia Sopsopia Vawmva Rawpuichhip Snake Bite Bark 29 Gmelina Arborea Thlanvawng Hmnunpui Blood Disease Root 30 Gynocardia Ordorata Saithei Sairep Sore Throat Bark 31 Hedyotis Scandens Kelhnantur Khawbung Urinary Tract Leaf Infection I 32 Ltex Umbellulata j Thinguihahni Ralvawng Tonsilitis Bark Jus3iJusminum Dispen-num | Hrui Damdawi Chawnhu 1 Diarrhoea & Leaf ___________I________ Dysentery __ __ __ _ __ __ _ __ __ _ __ __ __ __ica_ Si phrM alarial Fever Leaf |34 Justicia Zeylanica Kawldal Sihphir i Feve 35 Kaempferia Rotunda Tuktin Par Chaltlang Sore Throat Root 36 Lannea Coromandelica Tawitawsuak Ralvawng Stomach Bark Disorder 37 Lindemia Ruelloides Thasuih Changte Cramp Whole I 38 Lobelia Angulata Choakathi Ratu Fester Whole 39 Mallotus Roxburghianus Zawngtenawhlun Sihphir Diabetes, Leaf U g Hypertension 40 Mangifera Indica Theihai Lungsen Diabetes & Leaf Diarrhoea * 41 Mikania Micrantha Japan Hlo Dungtlang Diarrhoea & Leaf Dysentery 42 Mimosa Pudica Hlonuar Sairang Kidney Problem Root 43 Momordica Charantia Changkhate Phullen Jaundice Leaf 44 Morinda Anguistifolia Lum Lungrang Stomach Ulcer Bark 45 Musseanda Roxburghii Vakeb Zemabawk Snake Bite Leaf 46 Oroxylum Indicum Archangkawm Hmunpui Rheumatism Bark 47 Osberia Rostrata Builukhampa Samthang Genito-Urinary Root Problem I 48 Ostodes Paniculata Beltur Phullen Bad Sore Bark 49 Parabarium Hookeri Thekelki Ralavwng Jaundice Bark 50 Phyllanthus Emblica Sunhlu Phullen Tetanus B ark 51 Phyllanthus Fratemus Mitthi Sunhlu Farkawn Diabetes & Whole Jaundice 52 Picrasma Javanica Thingdamdawi Zotlang Malaria B ark 53 Pramanthes Scandens Kawlhlo Khawbung Urinary Tract Leaf I IInfection | 54 | Psetidodrynaria Awmvel Ralvawng Herpes Zoaster Stem 3 ___| Coronans Revised bv Lea Associates October 2001 I (Original Document by ICT, CES. LBII) Mi-01-rin SrIe Roads Projoect Secroral Enviriontenitazl ,Assessomenit I Si. Plant Species Local Name Locality Uses Part Used No. *55 Psidiim Guajava Kawlthei Lengpui Diarrhoea & Leaf _____ Dysentery |6 jRhus Semialata Khawmhma Darlawn Diarrhoea Fruit 57 Saraca Asoca Mualhawih Hmunpui Stomach Ulcer Bark 3 5| tS Schima Wallichii Khianc Vangtlang Cut & Wounds Bark 59 Scoparia Dulcis Perhpawngchaw Dungtlang Jaundice Whole 60 T Securinega Virosa Saisiak Zemabawk Measles & Leaf L _ _ _ _ _ _ _ _ _ Scabies 61 Solanum Khasianum Rulpak Zemabawk Remove Tooth FrLit _ _ Worms 62 Solanunm Niu,rum Anhling Sairang Stomach Ulcer Leaf 3 163 Stephania Japonica Hnahbial Farkawn Diarrhoea Root 64 StercLulia Villosa Khaupui Hmunpui Throat Problem Bark 65 Stereospernum Colais Zinghal Rualalung Rheumatism & Bark I .__ Scabies 66 Tetrameles Nudiflora Thingdawl Rawpuichhip Cuts & Wounds Bark 67 Vitex PeduncLularis Thingkhawilu Chawnhu Malaria & Black Bark Fever 68 Vitis Peduncularis Pasaltakaza Chawnhu Stomach Bark Problem Source Ph.D. thesis titled "Study of Medicinal Plants in Tropical & Sub- tropical Forest of Mizoram" by Pu. Lalhundanga. I I I U Revised by Lea Associates October 2001 (Original Document by ICT, CES. LB[I) I I I Anneuxre 4.6 Major kinds of trees / plants reported in the state area S No. VERNACULAR NAMES BOTANICAL NAMES LUSHAI NAMES I Sapas, Champas, Sopas Magnolia ptercocarpa Mlagnolia shenocarpa Ngiau Chi reng reng Manglieta insignis, Hookeri caveana, Talauma, Rabaniana and Phellocarpa, Ivfitchelia champaca, Punduana oblon ga. Manii and Montana. 2 Chaulmugra, Lantem Taraktogenos 3 Nahor. Nageswar Mesuaferrea Herhse 4 Sia Nohor, Karal Kauea assainica and floribunda Serpai Kasumoroi (Cachar) Serpoi (Kuki) 5 Gurgra, Nagabhe or Magria Schima wallicchi and schima khasiana Khiang 6 Kurial Dipterocarpos turbinatus 7 Hollong Dipteroxarpos pilosus Lawngthing 8 SalShere robusta Lawngthing tha chi I 9 Makai Shorea assamica 10 Sinmul Salinalia malabaricum Phunchawng 11 Rata Dusoxylum binectarifeumm 12 Amari Rata Amnora rohituka Sahatah Wallichii and Chitaginga 13 Kolia,Hoga,Pona, Hotai Chakrassia tabularis Zawngtei 14 Peema Cederela toona Tei U Febbrifuga and Inicrocarpa 15 Sisso Dalbergia sisso 16 PingCynometra polyandra Kawrhreiha 17 Sonalu, Sanuru Cassiafistula and Nodasa (Banarlathi) Makpazangkang 18 Khair, Khoira Acacis catechu 19 Mio sunbi Albizzia lucida 20 Korei Albizziapreocera Kangtek 21 Hiharu, Koroi Moroi Albizzia odoratissima Thingri 22 Jululi, Duang, Fakiri Altingia excelsa Hriang 23 Hollock, Bhaina Terminalia,Myriocarpa Char 24 Bogi jamuk Eugeniz proaeco Hmuifang 25 Fatijam, Barja, muk Eugeniajanibelana Hmuipui 26 S ida Langerstroemia flosreginae Thado I I I S No. VER-NACULAR NAINAMES BOTANICAL NAMES LUSHAI NAMES 27 Ajhar, Farul Lagerstroemic pa;v flora Thado 28 Khokan Ramadala Duabanga sonnerationiides Zuang 29 Panikadam. Gahorichapa MVyssa sessiliflora banpho-r Chikha 30 Tarakchapa, Haldu. Adina cordifola Haludchaki 1 Kurta Palaquizn polyanthwin 32 Mlohidal. Kawatuh Cordiafragrantissima Muk *3 Ahui Vitex pudzincdlaris Thingkhawilu ' 4 Gomari, Gamarh Gmelina ghoreajlinn Thlanvawng 35 Bonsum. Nikahi Phoebe attenuate and Hai nesiana 36 Gonsoroi, Gondrel Sinnamemrum cecwcodaphne glanduliferwun Khiangzawl 37 Jal Sindhi Alseodaplhne owvendy Bulchi 3 38 Naga Dalchini,Paderai Cinnamonum Thingrai Zeylanicum 39 Agar, Sasi Aqui/aria agallocca Thingrai 40 Kuhir Bridellia resrusa 41 Uriam Dischofin raremica Khuangthli 3 42 Garokhuta, Chhamolia Aporasa roxburghii 43 India Rubber, Bar Ficus elastica Thelret 44 Kathak Artocarpas interglifollia Lamkhuang 45 Sam Artocar-pus chaplasha Tatkawng 46 Dud-Chempa Pseudostrablus indic 47 Bola Morus leavigata Lungli 48 Junari Posocarpus nerrifolia 49 Momailateku (in the district or Nowgong &- Sibsagar) 50 Thutmala in the district of Cachar, Gurunga pinnat. Svhlet and Nowgong 5 1 Ruhimalla Odina wodier 52 Bhelu Tetrarneles nudiflora (in all Forest Division) Thingdawl 53 Kadam Anthocephaalus Banphar cadamba in Syhlet. Cachar, Sibsagar, Lahkhinpur, Kamrup. Haltogoan and Garo Hills Forests Division 54 Kalasam, Kharika Chopa 551 Banjalakia, Bospat and Ainugdalina Thuamriat Satiana I l Annexure 4.7 | Number of Seedlings Planted on the Green Mizoram Day on 1st June 1999 SI. No. Name of District No. Seedlings Remarks Planted I Lun-lei 11,507 40 Govt. Departments, 24 Educational Institution, 17 NGOs / Churches were involved 2 Saiha 12,000 Planting done by Govt. Departments, Schools and Colleges & NGOs 3 Lawngtlai 20,014 -do- t ~~~4 Mamit 1,204 -do- 4 S Kolasib 11,255 29 Govt. Departments, 28 Educational Institutions, 6 NGOs/Churches were involved. 6 Serchhip 26,128 29 Govt. Departmnents, 31 Educational Institutions, 18 NGOs/Churches were involved. 7 Champhai 17,000 15 Govt. Departments, 5 Educational Institutions, 2 ?NGOs/Churches were involved. I Total 99,108 | Altogether 1,50,739 seedlings were planted under Green Mizoram Programme in the whole State on 1 8th June, 1999. The responsibility of the maintenance of Plantation is given to the planting Agencies and today reports on the achievements made by these Agencie are pouring in from X different districts. The Green Mizoram State Programme will be landmark in the history of the state of Mizoram. Note: Issued by the Sub-Cominitee on Green Mizoram, Aizawi. I l l I l AI!mlyuu State Roadi Pt oIje'ct Sector al Lnviwctal Assl.SZlt Annexure 4.8 Mizoram and Its Forests The geographic area of Mizoram is 2.11 million ha. It is located, in the extreme southern part of North-Eastern India between lat. 21°57' and 24030' N and long. 92015' and 930 29' E. bordering NMyanmar in the East & South and Bangladesh in the West. The terrain is hilly and mzostly undulating with average altitude ranging from 500 to 800 m and maximum reaching 5 157 m in Blue Mountains. The Chhimtuipui is the only major river. The land use pattern is showvn in below (see Table) Climate of Mlizoram ranges from moist tropical to moist sub-tropical. Average annual rainfall ranges from 2,160 mim in Aizawl to 3,500 mm in Lunglei. During winter the average temperature varies from 1 1 C to 24° C and in summer from 18° to 290 C. | The total population of the state is 0.69 million of which 54% is rural (1991 census). The Scheduled Tribe population comprises about 94.74% of the total population (1991 Census). The livestock population is 112,000 (1992 livestock census). Land use j Land use hArea in '000 lge | Total geographical area 2,108 I l Reporting area ,2,109 100.0 IForest 1,598 75K77 Not available for cultivation 65 3.08 Permanent pasture and grazing land L0 ||_° __ Land under misc. tree, crops & groves 0 0 I . Culturable wasteland 174 [8.25 Fallow land other than current fallow 163 f773 Current fallow 0 fo I . Net area sown il109 15.17 i Souirce . Land utse statistics At a Glance 1996-9 7, Ministry of Agricuiltuire, GOI, I 2000 Shifting Cultivation Shifting cultivation, also called jhum, is widely prevalent in the state. In a study undertaken by the FSI, it is estimated that during 1987-97, an area of about 0.38 million ha has been affected by shifting cultivation. Revised by Lea Associates October 2001 I (Original Document bv [CT, CES, LBII) Mi:graii Satew Roads Projcct Sectoral Environmental Assessment Forest resources Recorded forest area of the State is 1.59 million ha constituting 75.59% of the total geographic area. The Reserved Forest constitutes 44.7%, Protected Forests 22.4% and Unclassed Forest 32.9%. The three forest types occurring in the state are Tropical Wet Evergreen, Tropical Moist Deciduous and Sub-tropical Pine Forests. Protected areas Mizoram is rich in wild flora & fauna, both in variety and abundance. About 88,400 ha of the forcst area constituting 4.19% of the geographic area of the state is under two National Parks and four Wildlife Sanctuaries. Dampa Tiger Reserve is located in the state. Joint Forest iMvanagement Joint forest management was initiated in 1998. A total of 103 Forest Development Committees are managing an area of 5,870 ha. JFM is to cover the degraded forest areas. The net proceeds shall be shared among the government, beneficiaries and the Village Forest Development Fund in the proportion of 50%, 30% and 20%. Forest Plantations Before 1980, an estimated 7,900 hectares of plantations was done in the State. The average annual plantation peaked to 20,500 hectares during 1985-90 the rate has declined to 6,800 ha during 1998-99. Plan-wise progress of plantations and breakup of species are given in Table(s) below. Forest plantations by all agencies * EVPeriod |IArea in '000 ha 1 ~ ~~~~~~~~I.I -------.. . . ... ...... .. ... ... .. _ *1951-80 {7.91 l 1980-85 . 76.88 I 11985-90 [102.78 1990-91 (1.38 | 1991-92 14.46 l [ 1992-97 , 73.19 l1997-98 1914 1998-99 _6.82 * L Total ] 308.55 Sotirce NAEB, MoEF, 1999 Revised by Lea Associates October 2001 (Original Document by [CT, CES, LBII) ,A ti-orin Stare RoadIs Project Sectodl Ent iromnental -4ssessnwu Species wise Plantations by Forest Department upto 1999 Species ina n Percentage I __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ___ _ _ _ _ _ _ . -_ l [ Tectoac grandis 64.49 j 34.0 Ginelina arborea 153.92 28.4 n I is spp. 32.63 17.2 I |KAfichelia spp. | 11.36 6.0 Fother |27.15 114.3 otal 1189.54 4 100 | Source.:Mizoram Forest Department Forest Cover The forest cover, based on satellite data of Dec. 1998 is estimated as 18,338 sq.km. representing 86.99% of state's total geographic area. The dense forest is 3,786 sq.km. and open forest is 14,552 sq.km. A decrease of 437 sq.km. in forest cover has been observed in the present assessment compared to the previous one. Dense forest registered a decrease of 562 sq.km. while the open forest increased by 125 sq.km. The forest cover is shown in figure 5.10. Thc difference between the data periods of the two assessment is about 4 years. | The change matrix given in the table below reveals that there has been an overall decrease of 562 sq. km. of dense forest. This is the result of degradation of 653 sq.km. to open forest and 453 sq.km to non forest. The decrease is also associated with conversion of 464 sq.km. of * open forest, 56 sq. km. of scrub and 24 sq.km. of non forest to dense forest. The increase of 1 25 sq. km. of open forest is on account of conversion of 653 sq.km of dense forest, 11 sq.km of scrub and 12 sq.km of non-forest to open forest. The increase is also associated with conversion of 87 sq.km of open forest to scrub and improvement of 464 sq.km to dense forest. Forest cover change matrix (sq. km) *..\;,,...,.,,;.\,4.I i -- F. ; . _ _ _ _ [