SOCIALIST REPUBLIC OF VIET NAM ELECTRICITY OF VIET NAM PECC4 POWER ENGIINEERING( CONSULTING COMPANY 4 ISO90012 RP287 Project No.: 13 - 02 VOL. 3 QUY NHON - TUY HOA 220kV TRANSMISSION LINE FEASIBILITY STUDY REPORT RESETTLEMENT ACTION PLAN (RAP) (FIRST REVISION) Khanh Hoa Province - 2005 SOCIALIST REPUBLIC OF VIET NAM ELECTRICITY OF VIET NAM PECC4 POWER ENGINEERING CONSULTING COMPANY 4 ISO 90012000 PROJECT: 13 - 02 QUY NHON - TUY HOA 220kV TRANSMISSION LINE FEASIBILITY STUDY REPORT RESETTLEMENT ACTION PLAN (RAP) (FIRST REVISION) Head of Department Nguyen Kim Dong Head of Project Design: Nguyen Thanh Hai Khanh Hoa Province, 2005 FOR AND ON BEHALF OF POWER ENGINEERING CONSULTING COMPANY 4 PHAM MINH SON DIRECTOR Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study The staffs participating in RAP establishment including of: No. Full name Content prepared Signature In charge of presiding RAP 1 Tran Van Luyen establishlment 2 Mai Thi Hop Establishing RAP Resettlement Action Plan Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CONTENTS ABBREVIATIONS 4 SUMMARY 5 1. Policy framework 5 2. Project impacts 6 3. Resetlement policy 6 4. Public consultation 6 5. Grievance 7 6. Management organization 7 7. Implemetation schedule 7 8. Cost estimate 8 9. Information dissemination 8 CHAPTER 1: GENERAL INTRODUCTION 9 1.1 The basis of the report 9 1.2 Objectives 9 1.3 Validity of RAP implementation 10 1.4 Description of the project 11 1.4.1 Characteristic of the project 11 1.4.2 Project impacts 12 1.5 Project impacts minimizing measures 12 1.6 Implementation cost estimate 13 CHAPTER 2: IMPLEMENTATION ORGANIZATION AND LEGAL 14 FRAMEWORK FOR COMPENSATIONAND RESETTLEMENT 2.1. Institutional arrangements 14 2.2. Organizational responsibility 14 2.3. Staffing organization and responsibilities 19 2.4 Legal framework 20 CHAPTER 3: ENTITLEMENT POLICY 25 Resettlement Action Plan (RAP) 1 Quy Nhon - 2uy Hoa 220kV transmission line Feasibility Study 3.1 Definition of PAP and limitation to eligibility 25 3.2 Resettlement and compensation principles 25 3.3 Eligibility to get compensation entitlements 27 3.4 Entilement policy 27 3.5 Impacted categories 31 CHAPTER 4: SOCIO-ECONOMIC SITUATION OF PROJECT AREA 32 AND THE PROJECT IMPACTS 4.1 Survey work, inventory of project impacts 32 4.2 The socio-economic condition of project area 32 4.2.1 Binh Dinh Province 32 4.2.2 Phu Yen Province 33 4.3 Project impacts 34 CHAPTER 5: PUBLIC PARTICIPA TIONAND CONSULTATION 36 5.1 Objectives of infonnation campaign and consultation program 36 5.2 Consultation and infonn to people 36 5.3 Infonnation dissemination and PAPs'consultation 38 CHAPTER 6: COMPLAINTS AND GRIEVANCE 41 CHAPTER 7:SUPERVISION AND MONITORING 43 7.1 Internal supervision 43 7.2 Independent supervision 43 CHAPTER 8: IMPLEMENTATION ORGANIZATION FOR 45 COMPENSATION AND RESETTLEMENT PLAN 8.1 Measures for the project implementation 45 8.1.1 Announcement to PAPs 45 8.1.2 Compensation and Resettlement deadlines 45 8.2 RAP implementation process 45 8.3 RAP implementation schedule 47 Resettlement Action Plan (RAP) 2 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 9: COSTSAND BUDGET 48 9.1 Budget 48 9.2 Compensation price determination 48 9.2.1 Land 48 9.2.2 Impacted trees and crops 49 9.3 Compensation cost estimate 49 9.3.1 Cost for RAP establishment 49 9.3.2 Compensation cost 50 9.3.3 Management cost 50 9.3.4 Supervision cost 50 9.3.5 Reserved cost 50 9.3.6 Total compensation cost for project 50 CHAPTER 10: CONCLUSIONAND PROPOSALS 51 10.1 Conclusion 51 10.2 Proposals 51 APPENDICES 52 Appendix 1: Entitlement Matrix 53 Appendix 2: Table of compensation quantity for Quy Nhon - Tuy Hoa 220kV T/L 61 Appendix 3: Inventory of Project Affected People 64-65 Appendix 4: Entitlements of Project Affected People 69 Appendix 5: Socio-Economic Household Data Sheet of Project Affected People 73 Appendix 6: Minutes of public consultation 77 Resettlement Action Plan (RAP) 3 I~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study ABREVIATIONS i - RAP Resettlement Plan - PAP Project Affected Person - PAPs Project Affected Persons - WB World Bank - PC People's Committee - EVN Electricity of Vietnam - LC Land clearance - PMB Project Management Board - PECC4 Power Engineering Consulting Company 4 - ER Environmental Resource - VND Viet Nam Dong - SC Safe Corridor - ROW Right-Of-Way - CPPMB Central Power Projects Management Board Plan on compensation and resettlement 4 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study SUMMARY The national industrialization and modernization make contribution to the country development with purposes of rich people, strong country and a equitable, democratic and civilized society. In order to strenthen the capacity of supplying power source, a vitual infrastructure, Electricity of Vietnam (EVN) has established the project "Transmission, distribution and overcoming natural disasters" (3034-VN) financed by World Bank (WB). One of its component is "Quy Nhon - Tuy Hoa 220kV transmission line" project with total route length of 88,704m going through the territory of Quy Nhon City, Binh Dinh Province; Tuy Hoa City, Song Cau, Tuy An and Phu Hoa Districts of Phu Yen Province. The purpose of this project is to increase the transmission capacity on the line and get reliable and continuous power supply for the region as well as have condition to receive energy source from power source of Song Ba Ha hydropower project. In line with Quy Nhon - Tuy Hoa 220kV transmission line, 220kV Tuy Hoa Substation will make 220kV grid connection between the Central region and the Southern region. It makes the capacity distribution to support for electricity supplying ability in the national electricity system safer and more flexible. 1. Policy framework The plan on project compensation and resettlement is established based on Decree 197/2004/ND-CP dated December 3, 2004 of the Government regarding the compensation, resettlement support when the State takes back the land; Decree 1982004/ND-CP dated November 16, 2004 of the Government regarding the method to determine the land price and the price framework of land kinds; Decree 1812004/ND-CP of the Government regarding the implementation of Land Law, etc... and guideline on RAP establishment of WB (the policy framework of unvoluntary resettlement OD 4.30). According to this policy, PAPs are people, households, entities with or without juridical personality for their assets on project impacted land and inventoried before the cut-off-date (June 18th, 2004) are entitled to compensation and resettlement. Plan on compensation and resettlement 5 Quy Nhon - Tuy Hoa 22OkVtransmission line Feasibility Study 2. Project impacts The project causes impacts to the followings: - Perpetual land acquisition at tower foundation positions, ect - Causing damage to trees, crops and other assets at tower foundation positions and within ROW. - Temporary land acquisition under project construction Results of project data collection show that there are 58 impacted households, whereas: + No household loses over 25% area of agricultural land + No affect to cultural relics area, preservation area, pagoda and sensitive areas + No ethnic minority household among impacted households. During public consultation process, impacted households were agreed to select the compensation procedure on land and assets in cash. 3. Compensation policy The cut-off-date is June 18th 2004. The price for making compensation on land, assets and crops is based on the compensation unit price of Binh Dinh and Phu Yen Provinces. All impacted households are entitled according to the policy framework and Vietnam Decrees such as displacement support, support for production stabilization, etc... Up till now, the survey result and damage inventory shows that no remarkable impacts to people, the community and the public assets. As a result, it is unnecessary to have economical recovery measures. 4. Public consultation PAPs consultation to get feedback comments will restrict the contradictions and delay when implementing the project. The resettlement plan will be implemented following to the reference comments from the authorities and people in order to maximize their participation in the resettlement plan and imnplementation as well as socio-economical benefits. The authorities and people are consulted in line route location, the resettlement policy, implementation of resettlement plan, grievance Plan on compensation and resettlement 6 Quy Nhon - TuyHoa 220kV ransmission line Feasibility Study mechanism and the checking, appraisal towards the recovery of life of impected people after project implementation. 5. Grievance During project implementation, grievances of impacted people will be solves based on Vietnam law. All grievances will be solved equitably and the grievances procedures will be guided by related authorities. The griever will pay no cost for this grievance. CPPMB and the local authority are responsible for monitoring the RAP implementation process. In addition, an independent consulting agency will be assigned to supervise independently and appraise the compensation and resettlement implementation process in accordance with the policy stated in this dossier. This agency can be selected and awarded the contract by the PMB after the approved resettlement plan or selected and awarded the contract by WB. The supervising activities are implemented from the beginning of project implementation stage. This independent supervising agency will report to PMB or WB about its results of supervising activities. 6. Management organization CPPMB is the project coordinating unit and cooperates with other agencies such as the Provincial People's Committee, the local authority, Power Company of Binh Dinh and Phu Yen provinces and WB in implementing detailed works of project, especially the RAP implementation plan. 7. Project implementation schedule Contents Time Establishing and approve the technical design Quarter I, 2005 Ask for land acquisition, compensation work and May 2005 .September 2005 land clearance __ _ Establish and submit bidding document July 2005 September 2005 Preparation of construction drawings September 2005 December 2005 Procurement of equipment and materials December 2005 . August 2006 Construction, revising, testing and hand-over January 2006 . November 2006 Commissioning and put the project into service December, 2006 Plan on compensation and resettlement 7 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 8. Cost estimate Total project compensation cost is about VND 2,295,371,139 (or USD 145,277). 9. Information dissemination The draft RAP will be disclosed in Binh Dinh & Phu Yen provinces and the Information Development Center of WB (VDC) at 63 Ly Thai To, Ha Noi. CPPMB will send copies of entitlement statement form to the project district authority. All feedbacks from the local authority and people are considered and supplemented into the RAP. Plan on compensation and resettlement 8 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 1 GENERAL INTRODUCTION 1.1 THE BASIS OF THE REPORT Implementing the Vietnamese Communist Party's policy on the national industrialization and modernization program, EVN decided to use the loan of WB to invest in Quy Nhon - Tuy Hoa 220kV transmission line project. EVN have directed the project implementation step by step. - Pursuant to Official Letter No. 1127 EVN/AMT - KH dated March 25, 2004 issued by CPPMB regarding the FS establishment of power grid projects. - Based on the above instruction, CPPMB has made a contract with PECC4 for preparing Feasibility Study Report, RAP and ETA of the project. Carrying out the contract (with CPPMB), PECC4 has been gathering data, surveying at sites and preparing RAP report for the project. 1.2 PRINCIPLES AND OBJECTIVES This report is set up with the purpose: + Study on policies of compensation, resettlement for households having land acquisition for construction of substation, foundation, tower, temporary road for work execution, etc... according to Viet Nam laws and VB guidelines. + Proposing the alternatives of compensation, resettlement and the most efficient way of implementation to the households affected. + Helping to choose the right design alternative, minimize the degree of damage at the implementation of project and ensure the highest socio-economic interests of the project. During FS stage, carry out to make livelihood-socio- economic damage survey of project area and work with local authorities concerning the compensation and resettlement policy for affected households. The survey and data collecting work focuses mainly on the right of way. Where resettlement is unavoidable, the program will set out provisions to ensure and help affected households improve or at least maintain their pre-project conditions. . Plan on compensation and resettlement 9 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study The principle objective of the Policy Framework is: All PAP's residing, working, doing business or cultivating land in right of way (ROW) of transmission line (T/L), surrounding areas of tower foundation, the substation areas, in the service roads under the Project as of the date of the baseline surveys are entitled to be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-Project living standards, income earning capacity and production level. Lack of legal rights to the assets lost will not bar the PAP from entitlement to such rehabilitation measures. During RAP preparation, Decrees and Circulars of Vietnamese Government such as Decree 197/2004/ND-CP, Decree 181/2004/ND-CP, Decree 188/2004/ND- CP, etc and Decisions about compensation unit price issued by The peoples' committees of provinces are applied. The entitlement policy in this RAP are suggested as follows: + Apply a compensation rate according to the market price or replacement price: Compensation of land and crops (short-day trees) at market price. Compensation of houses and trees (perennial trees) at conversion price. + All affected properties are legible from the cut-off-date (June 18th, 2004). The affected households who have been registered will be compensated. This RAP will be furnished to GOV and WB for concurrence. 1.3 VALIDITY OF RAP IMPLEMENTATION Resettlement and compensation program for PAPs, policy and provisions on resettlement and compensation entitlement in RAP will only be applied after approval of WB and Vietnamese Government. To meet RAP's objectives such as minimizing the resettlement and land acquisition, PAPs will be supplied the information on project, compensation and resettlement, the compensation costs will be paid at replacement cost or market cost. Thus, before implementing resettlement and compensation program, the project owner and local authorities should check and revise the applied compensation costs in this report. If there is any compensation unit price non-conforming at the time of program implementation, the local authorities and Resettlement and Compensation Plan on compensation and resettlement 10 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Board (RCB) need to revise them to ensure sufficient compensation payment for PAPs according to principles stated in RAP. Survey data in this report base on feasibility study of the project. If there are any changes in design, at most the adjustment on affected assets, it is necessary to revise and update them as per the approved alternative. 1.4 DESCRIPTION OF THE PROJECT 1.4.1 The project characteristics Quy Nhon-Tuy Hoa 220kV transmission line is planned to be constructed on the area of Quy Nhon City - Binh Dinh Province; Song Cau, Tuy An Districts - Tuy Hoa City; Phu Hoa District- Phu Yen Province. Main characteristics of the line route: - Voltage level: 220kV. - Number of circuit: 01 circuit - Starting-point: 220kV busbar of 220kV Quy Nhon susbtation (exsting) belonging to Quy Nhon City - Binh Dinh Province. - End-point: 220kV busbar of 220 kV Tuy Hoa substation (design) belonging to Phu Hoa District - Phu Yen Province. - Total length: 88.704km. - Conductor: Aluminum steel reinforced conductor, symbol ACSR-330/43 with neutral grease for anti-erosion. - Ground-wire: Using composite optical fiber overhead ground-wire on line route, for incoming section and outgoing section of 220KV substation suspended another ground-wire TK-70, length of each section is about 2.5km. - Insulator and accessories: using glass insulator or equivalent standard. Electro- mechanical load of suspension string is 7000daN and tension string is 16000 daN. The creepage distance of suspension disc is 295mm and tension disc is 340mm. Accessories for suspending conductors and ground wires comply with their sizes, ensuring the erosion condition and durability reserving coefficient as per norms. - Towers : steel tower with hot dip galvanizing, linked by bolts, manufacture in country - Arms : Manufacture arms with towers all-in one block Plan on compensation and resettlement 11 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Foundation: + Raft foundation for weak soil + Pier foundation for good soil + Pile foundation for crossing spans of Ky Lo river Quy Nhon - Tuy Hoa 220kV transmission line, Tuy Hoa - Nha Trang 220kV transmission line, 220kV Tuy Hoa substation, when being constructed, will make much contribution to the transmission of power system, creating the 220kV grid connection between the Central region and the Southern region, resulting the national electricity system safer and more flexible, contributing to the speed hastening of country industrialization and modenization and supply electricity for people life and economy in the future. 1.4.2 Project impacts Impacts on land and properties: a Permanent impacts: - - - Permanent land acquisition for tower foundations b. Temporary impacts: - Trees, crops in ROW and temporary service road - All trees and crops surrounding the tower foundation areas The safe corridor of the above-mentioned line route is not regulated in Decree th 54/1999/ND-CP dated July 8 , 1999 of the Government regarding the safe protection of high voltage power grid and Decree 118/2004/ND-CP of the Government concerning the amendment of some articles in Decree 54/1999/ND-CP. With the above-mentioned characteristics and scale, land acquired for the project construction as follows: - Number of tower on the whole route : 217 towers - Land acquisition for tower foundations : 21,762m2. -Temporary acquisition land area in safe corridor of power grid: 1,664,363m2. On the whole Quy Nhon - Tuy Hoa 220kV line route, there are 58 households whose houses and architectural works are within the safe corridor of the line route. 1.5 PROJECT IMPACTS MITIGATION MEASURES Selection of logical line route and tower location: For the investigation and design of line route completely avoid passing: Plan on compensation and resettlement 12 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Market areas, densely populated areas. - Airport, military areas. - Near or parallel with communication system - Temple, pagoda - Protection forests, natural preserved areas - Historic and cultural heritage etc. Technical solutions thoroughlv exDloited: Rational design of tower span, foundation structure is designed with different measures in conformity with the chosen site. Design a rational work execution alternative, choose time for work execution at periods of harvest and complete work when next crop is not yet cultivated (land is at rest). If the cultivated period cannot be avoided then manual construction measures are used in order to diminish the surface of land acquired for work execution, road for big trucks are not constructed, organize work according to many shifts at high productivity, reducing the time of lay-out acquisition. During the process of stringing conductor, make scaffold and pull conductor neatly on belt of land about Sm to avoid causing damages of trees and agricultural crops. Make defmetely each item of work, each part of route line to reduce the time of land appropriation. Make full use of the existing roads for transportation of equipments and for other puoses during the time of work execution, limiting the construction of new road. During investigation and work execution process, the workers's camps are set up on vacant lot, on communal office area, not on private land or cultivated land. The result of these minimizing measures is that affected houses on the line route are the least. During the stage of operation management, when making repairs and overcoming incidents, following safety measures must be applied: - Safety measures when making contact with electrical equipments -Safety measures when carrying out operation management works, repairs of electric grid. 1.6 PROJECT COST ESTIMATE Total investment capital (In round) : VND 163,516,043,000 Plan on compensation and resettlement 13 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 2 IMPLEMENTATION ORGANIZATION AND LEGAL FRAMEWORK FOR COMPENSATION AND RESETTLEMENT Project Management Board and Local Authority of all levels will be responsible for imnplementing RAP. It should be on schedule, suitable with approved schedule for the project. The coordination between the project owner and local authorities will be made closely in order to implement RAP smoothly and effectively and to avoid the interruption or delay of RAP implementation. 2.1 INSTITUTIONAL ARRANGEMENTS The following institutions/agencies will be involved in implementing RAP: - PCs of 02 provinces: Binh Dinh and Phu Yen - Electricity of Viet Nam (EVN) - Project Management Board - Central Power Projects Management Board - Consulting Company - Power Engineering Consulting Company No.4. - Departments of Finance and Goods Price of the above project provinces - Land Clearance Boards of the above project provinces - People's Committees of Quy Nhon City, Song Cau, Tuy An Districts - Tuy Hoa City, Phu Hoa District. - Land offices of the above project city and districts. - Land clearance Committees of the above project city and districts - People's Committees of project affected communes such as Tran Quang Dieu, Bui Thi Xuan Wards; Xuan Loc, Xuan Binh, Xuan Phuong Communes; Towns of Song Cau, Xuan Tho 1, Xuan Tho 2, An Dan, Chi Thanh, An Dinh, An Cu, An Hieo, An Hoa, An My, An Chan, An Phu, Binh Kien, Hoa Kien and Hoa Quang Bac. - Project affected persons 2.2 FUNCTIONS, TASKS FORCE AND RESPONSIBILITY * Electricity of Viet Nam (EVN) EVN is the owner of the project and is responsible for managing and organizing of investment policy, investigation, design, construction as well as supervision for RAP implementation. EVN controls the project preparation and implementation via Plan on compensation and resettlement 14 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study professional agencies, approving decisions concerning resettlement work submitted by PMB; assigning Central Power Projects Management Board (CPPMB) to directly manage the whole process of project implementation. * Project Management Board (PMB) Central Power Projects Management Board is assigned by EVN in directing the whole project including the implementation of RAP from impact survey, inventory, making plans for RAP implementation. Main tasks of PMB will be: + Making Master Plan, management and supervision of land clearance implementation to ensure full determination of relating PAPs, set out satisfied entitlements as per land clearance policy. + To ensure that all PAPs are announced of applied policies for RAP preparation. Entitlements of PAPs, project information and site clearance plan are popularized under announcement form. This is considered the proof of their entitlement towards interests of RAP work. + Disseminate project information to PCs of all levels + Send RAP to Resettlement Committees, explaining applied models and entitlements in the project. + Supervision/monitoring for compensation payment, coordinate to implement land acquisition and site clearance. + Independent monitoring for RAP implementation, assigning an experienced and competent agency to do this. + Report the implementation process on land clearance work to EVN and WB. To meet this responsibility, PMB needs to establish a department or a group including experienced officers to monitor RAP and environment implementation. *: Provincial People's Committees (PPCs): Binh Dinh, Phu Yen PPC is the agency approving and directing matters concerning the RAP within the provincial area. The Project PPC are responsible for: * Directing departments, branches and local areas in province related to RAP preparation and implementation such as Land Department, Construction Departnent, Department of Finance and Goods Price and project affected DPCs. * Approving the costs of compensation in provincial area. Plan on compensation and resettlement 15 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study * Approving dossiers of land delivery and recovery in provincial area. * Establishing Provincial Resettlement and Compensation Committee and directly manages the activities of this Board. * Directing and managing the coordination between Branches and local authorities in RAP implementation. D Departments of Finance and Goods Price of Binh Dinh and Phu Yen Provinces To be responsible for issuing detailed compensation unit prices applied in the provincial area. During the implementation process, Department of Finance-Goods Price needs to make cooperation with other departments such as Construction Department, Land Department, Department of Agriculture and Rural Development and People's Committee of District where the project constructed in order to establish the compensation unit price for premises, land, trees and crops. *: Provincial Compensation Committees: Binh Dinh and Phu Yen PCCs are consulting institutions for provinces about RAP approval and RAP implementation management according to the provincial approved plan. Provincial Resettlement Committee will be headed by a Vice Chairnan of Provincial People's Committee. Provincial Resettlement Committee is mainly responsible for: * Assisting owner and compensation committees of districts in preparing detailed plans for compensation and resettlement. * Checking all inventories of project impacts and detailed implementation plans prepared and submitted by Compensation Committees of districts. Approval for implementation plans within 10 days after receiving the plans submitted by District Resettlement Committees. * Checking and submitting RAP implementation plans in provinces to PPCs for approval. * Solving outstanding problems due to the unsatisfied solution at the district level. * Compensation payment for PAPs via District Resettlement Committees. Provincial Compensation Committees will consist the representatives of: - Department of Finance and Goods Price Plan on compensation and resettlement 16 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Construction Department - Industrial Department - Department for Agriculture and Rural Development - Department of Natural Resources and Environment - Chainnen of People's Committee of related districts - Representative of Provincial Project Management Boards. Staffs of Provincial Resettlement Boards will be work concurrently and get allowances according to PPC's decisions. Assistants work during the project implementation and get salary during the work period. *: People's Committees of Quy Nhon City, Song Cau, Tuy An Districts, Tuy Hoa City and Phu Hoa District. Being responsible for guiding compensation and resettlement activities in district and city areas. People's Committees of Districts and Cities are responsible for: + Creating good conditions and coordinate with relating agencies in survey, inventory of project impact; organize community consultation activities, information dissemination on the project implementation policy and land acquisition plan to people of commune (ward) where project constructed. + Establishment of Resettlement Committees of Districts (Cities) + Directing and monitoring RAP implementation in districts (cities) + Solving relating matters during RAP implementation together with Resettlement Committees of district (city). * Resettlement Committees of Quy Nhon City, Song Cau, Tuy An Districts, Tuy Hoa City and Phu Hoa District These are key institutions being mainly responsible for implementing RAP in district (city) area. Resettlement Conunittees of districts consist of experienced officers of the data-gathering inventory. Resettlement Committees of districts (Cities) are mainly responsible for: * Checking all survey documents concerning affected households and assets, making Detailed Measurement Survey (DMS) for each household including of Plan on compensation and resettlement 17 Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study affected assets, total compensation cost based on entitlement policies regulated in RAP. * Checking the unit prices of compensation stated in RAP, suggest adjustment to comply with market prices at the plan implementation period. * Co-ordinating with PMB, consultant agency to organize RAP meetings in local section and organize community consultation together with project owner. * Summarize and submit data affected in local section to Provincial Resettlement Committee. * Based on the policy and approved schedule in RAP, preparing the detailed implementation plan and submit it to Provincial Resettlement Committee. * Directly make payment on compensation and allowances to PAPs in a timely manner. * Settling the complaints and grievances of PAPs, solving any difficulties during the implementation period, and suggest the solutions for the outstanding issues to Provincial Resettlement Committees and Owner. * Making monthly report and send them to PRCs, Owner and Chairmen of DPCs. Resettlement Committees of districts (city) will be headed by Vice Chairmen of districts (cities) and consist of following members: - Representative of Economic Office - Representative of Land Office. - Representative of Agricultural and Rural Development Office - Representative of Statistic Office - Representative of Industrial Office - Representative of affected Commune. - Representative of PAPs Staffs of Resettlement Boards of Districts (cities) will work concurrently and enjoy allowances according to decision of District or City 's decision. Assistants work during the project implementation and get salary during the work period. Plan on compensation and resettlement 18 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study *4 Commune (ward) People's Committees * Contributing to Overall Detailed Measurements Surveys. * Co-ordinate with Resettlement Committees of districts for classifying impacted assets, determine the legality and legibility of assets. * Certify affected assets in general survey for compensation dossier of each household (in the survey note). * Assisting local people in overcoming the difficulties during the process of construction or rehabilitation of damages caused by project implementation. Making public information about the project and disseminating policies in RAP. * Project Affected Persons (PAPs) * Directly participate in the general survey, consider thoroughly their entitlement and responsibility policy. After getting full entitlements, PAPs should transfer the construction surface on time. * Propose expectation, requirement for the above mentioned institutions and monitor their implementation. PMBs of Binh Dinh and Phu Yen provinces will arrange full experienced staffs to ensure that the RAP will be implemented smoothly as the schedule accepted. 2.3 STAFFING ORGANIZATION AND RESPONSIBLES Table 2.1: Responsibilities of RAP implementing Institutions No. Activities Institutions 1 Organizing meetings with PAPs to Compensation Committees disseminate information about RAP Monitoring and certifying Project Management Board and impacted households and their Resettlement Committees of district 2 assets (city) coordinate with Commune People's Committees Project Management Board, Land Clearance Committee coordinate with 3 Detailed measurement survey Commune People's Committees and relevant Units of local authority. Plan on compensation and resettlement 19 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 4 Infonming for PAPs Project Management Board Decision on compensation Compensation Committees problems 6 Compensation payment Compensation Committees and Project Management Board 7 Internal Monitoring Project Management Board Department of Natural Resources and Environment or provincial socio- 8 Independent Monitoring science Units selected by Project Management Board. 2.4 LEGAL FRAMEWORK This is a project with loan from World Bank so the legal grounds applied will be a combination of Vietnam and WB policies. a. The Legal Documents of the Government of Vietnam According to Vietnam Law on land passed by National Assembly Term XI, Session IV on November 26th, 2003 and come into force from July Ist, 2004. Article 5: Land Tenure 1. Land is subject to the ownership of all people and the State is the owner's representative. 2. The State carries out land decision right as follows: a. Deciding the land using purpose via the decision, approval of land using plan (hereinafter called plan, land using plan). b. Regulating land delivery limit and land using period. c. Deciding land delivery, land leasing, land recovery and permit the changing of land using purpose. d. Fixing land price. 3. The Stated carries out the regulating right of income sources from land via financial policies about land as follows: a. Collecting land use charge, land leasing charge. b. Collecting land use tax, income tax from land use right transfer. Plan on compensation and resettlement 20 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study c. Regulating on the value added part from land not due to investments of land user. 4. The State grants LUR for land user via forms of land delivery, land leasing, acknowledging LUR for stable land users; stipulating right and responsibility of land user. Article 7: The State carries out the owner representative right of all people about land and implements common state administration about land. 1. The National Assembly passes law on land, decides the plan and land use plan of the whole country, carrying out the supreme supervision right towards the land administration and use in the whole country. 2. The Government decides the plan and land use plan of provinces, Central cities and the plan, land use plan on the purpose of defense, security; implements common state administration about land in all country. Ministry of Natural Resources and Enviromnent is responsible with GOV concerning the state administration about land. 3. People's Councils of all levels carry out the supervision right on land law implementation in local section. 4. People's Committees of all levels carry out the representative right of land owner and right of state administration about land at local section as per the competence stipulated by law. In addition, other legal documents are also applied such as: * Decree No. 197/2004/ND-CP issued by GOV on December 3rd, 2004 regulates compensation, resettlement support for recovered land by GOV. * Circular No.1 16/2004/TT-BTC issued December 7th, 2004 by the Ministry of Finance provides guidelines to implement Decree No. 197/2004fND-CP issued by GOV on December 3rd, 2004 regulates compensation, resettlement support for recovered land by GOV. * Decree No 188/2004/Nd-CP of November 16th, 2004 on the stipulation of method to determine the land price and the frame for the price of land types. Plan on compensation and resettlement 21 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study * Circular No.1 14/2004/TT-BTC issued November 16t, 2004 by the Ministry of Finance provides guidelines to implement Decree No 188/2004/Nd-CP of November 16th, 2004 on the stipulation of method to determine the land price and the frame for the price of land types. . Decree No. 181/2004/ND-CP issued by the GOV concerning the implementation of Land Law. X ! The Government Decree 54/1999/ND-CP, July 8t, 1999 on the protection of the high voltage networks. * Decree No. 118/2004/ND-CP dated May 10th, 2004 regarding the amendment of some articles in Decree No.54-1999/ND-CP dated July 8i, 1999. . Law on Petition and Accusation approved by National Assembly on December 02, 1998 * Decree No. 67/1999/ND - CP, issued by GOV on 7/81999 regulates in detail the Law on Petition and Accusation. b. World Bank Policy on Involuntary Resettlement (OD 4.30) * The primary objective of this policy is to ensure that PAPs who have lost assets are compensated at replacement cost and are provided with recovery measures to help them improve better or at least maintain their standard of life and their income capacity as in pre-project conditions. * The policy framework is established based on the principles and objectives, selection criteria for PAPs, entitlements, legal framework and institutions, mode of rehabilitation and compensation, the participation of people. Furthennore, procedures of grievance will be guided in the process of compensation, resettlement and rehabilitation for PAPs. c. Comparison between Government of Vietnam and World Bank Approaches * There are a number of ways in which the approaches of the Vietnam Government - both in policy and practice - are compatible with World Bank Plan on compensation and resettlement 22 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study guidelines so that PAPs can have legitimate entitlements. The most important compatibilities are: * Vietnam has a process whereby most people without legal land rights may meet conditions of legalization and receive compensation for losses. * Permanent residents are provided with options that include relocation to an improved site, or cash, or a combination of the two. * Resettlement sites offer not only better-improved infrastructure and services but also represent a higher standard of living. * Allowances are provided to help the PAPs in the transition period and there is an institutional structure through which people are infonned, can negotiate compensation, and can appeal. * Differences between the approaches and measures that need to be addressed within the program also exist. However, in this context, procedures exist within national and City governments that allow the granting of waivers of domestic law on specific projects that may be in conflict with that of the funding agency. d. Required Waivers In order to meet the requirements of the World Ba-nk OD4.30 on Involuntary Resettlement a number of articles in various Vietnamese laws and regulations which do not ensure compensation at replacement cost or set eligibility provisions which do not extend the right to rehabilitation and or assistance to households without proper land paper, will be waived. The articles of law and regulations that will be waived are mentioned below: * Price of Land for Calculation of Compensation According to Vietnam regulations, the calculation of land price for compensation will be based on Decree 188/2004/ND-CP, Decree 181/20041ND-CP, etc and Circulars No. 116/2004/TT-BTC, No. 114/2004/TT-BTC. To ensure that the objectives of the project resettlement policy are met, unit price for land compensation established by the Project Provincial/City People's Committees will be adjusted to meet at replacement costs. Plan on compensation and resettlement 23 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study The Item 4, Article 2 of Decree 17/2001/ND-CP dated May 04, 2001 to guide on the ODA management stipulates that "in the case of the international agreements on ODA have been signed between GOV and sponsor stipulates other contents, then that international agreements will be followed". Plan on compensation and resettlement 24 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 3 ENTITLEMENT POLICY 3.1 DEFINITION OF ELIGIBILITY AND LIMITATION TO ELIGIBILITY Project Affected Persons (PAPs) including people confirmed by data collected from the survey and investigation process as follows: . - PAPs have houses which are partially or totally affected (temporarily or permanently) by the project. - PAPs with partial or total impacted residental land or agriculture land by the project, temporarily or permanently. - PAPs with businesses and related income which are partially or totally affected (temporarily or permanently) by the project. - PAPs have crops (annual and perennial) and trees which are partially or totally affected by the project. - Encroachers who settled into the proposed affected area after the cut-off date (June 18th, 2004) will have no entitlement to compensation and resettlement. They will be required to demolish their structure and cut the trees or harvest their crops for land clearance to the project. In the case necessary, they will be forced to be removed out of the proposed project area. Nevertheless, they do not have to pay any fine or sanction. 3.2 RESETTLEMENT AND COMPENSATION PRINCIPLES The compensation and resettlement plan is established based on fundamental principles, i.e conforming to laws, decrees, policies regulated by Vietnamese Government and WB's guidelines consisting of: 1. Acquisition of land and other assets, and resettlement of people will be minimized as much as possible. 2. All DP's residing, working, doing business or cultivating land in right of way (ROW) of transmission line (T/L), surrounding areas of tower foundation, the substation areas, in the service roads under the project as of the date of the baseline surveys are entitled to be provided with Plan on compensation and resettlement 25 Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income earning capacity and production levels. Lack of legal rights to the assets lost should not bar the DP from entitlement to such rehabilitation measures. 3. The rehabilitation measures to be provided are: (i) compensation at replacement cost, without deduction for depreciation or salvage materials for houses and other structures; (ii) agricultural land for land of equal productive capacity acceptable to the DPs or in cash at replacement cost according to DP's choice ; (iii) replacement of residential/premise land of equal size acceptable to the DP or in cash at replacement cost according to DP's choice; and (iv) transfer and subsistence allowances. 4. Location of resettlement and relocation should be as close as possible to existing residential area of PAPs. 5. The resettlement transition period will be minimized and the rehabilitation means will be provided to the PAPs not over one month prior to the expected start-up date of works in the respective Project site. 6. Plans for acquisition of land and other assets and provision of rehabilitation measures wIll be carried out in consultation with the PAPs, to ensure minimal disturbance. Entitlements will be provided to PAPs not over one month prior to the expected start-up date of works in the respective Project site. 7. The standard of life, the infrastructure of community must be maintained or improved better than their prior place. 8. Financial and physical resources for resettlement and rehabilitation will be made available and as where and when required. 9. Institutional arrangements will ensure effective and timely design, planning, consultation and implementation of RAP. 10. Effective and timely supervision, monitoring and evaluation of the implementation of RAP will be carried out. Plan on compensation and resettlement 26 Quy Nhon - TuyHoa 22OkVtransmission line Feasibility Study 3.3 ELIGIBILITY TO COMPENSATION ENTITLEMENT Legitimate PAPs are all the affected households and institutions included in the inventory with or without legal title included in the RAP inventory or able to demonstrate with other means that prior to RAP cut-off date they owned, rented or used land, and properties associated with land as defined in 3.1 item. 3.4 ENTITLEMENT POLICY DP's will be entitled to the following types of rehabilitation and assistance measures as per the policy framework OD 4.30: * PAP's losing agricultural land and crops (i) The general mechanism for compensation of lost agricultural land will be through provision of "land for land" arrangements of equal productive capacity, satisfactory to the PAP. However, if the PAP prefers to receive cash compensation then the following applies: - if the portion of the land to be lost represents 25% or less than 25% of the total area of the landholding, and the remaining land is still a viable economic holding, cash compensation, at full replacement cost, may be provided to the PAP; or - if more than 25% of a villager's agricultural land is acquired and the remaining holding is not viable then the Project will acquire the entire landholding and provide cash compensation at full replacement cost. (ii) PAP' s will be compensated for the loss of standing crops and fruit or industrial trees at market price. Productive trees will be compensated at replacement cost. Fruit trees will be compensated for the remaining harvests. (iii) PAP's whose land is temporarily taken by the works under the each sub-Project will be compensated for their loss of income, standing crops and for the cost of soil restoration and-damaged Plan on compensation and resettlement 27 I~~~~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study infrastructure. Land will be rehabilitated after the project construction by PMB. * PAP's losing residential land and house/structure (i) The mechanism for compensating loss of residential land and structures will be: (1) the provision of replacement residential land (house site and garden) of equivalent size, satisfactory to the PAP or cash compensation at replacement cost according to PAPs' options; and (2) cash compensation reflecting full replacement cost of the house/structures, without deduction for depreciation or salvage materials or compensate in kind according to PAPs' options. (ii) If residential land is only partially being affected by the Project and the remaining areas are not sufficient for reorganizing PAPs' then at the request of the PAP, the entire residential land will be acquired at full replacement cost. (iii) If house/other structure is only partially being affected by the Project and the remaining areas are not convenient to using, the house/ structure will be acquired at full replacement cost, without depreciation. * PAP's will also be provided compensation at full replacement cost, without deduction for depreciation and salvage materials for any other fixed assets affected in part or in total by the project, such as tombs and water wells, etc. Pursuant to Decree 197/2004/ND-CP issued by the GOV concerning compensation, resettlement support for recovered land by GOV, then PAPs will be supported as follows: - As per Article 27: Transportation allowance Households getting land recovered by GOV must relocate within the province, city are entitled to a maximum of 3 million VND, relocating out of the province are entitled to a maximum of 5 million VND. The level of allowance in details will be regulated by the Provincial People's Committee. Plan on cormpensation and resettlement 28 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Entities getting fully conditions to be compensated on land and assets when being recovered, however they must change the location then they will be supported completely the actual displacement cost, dismantling and installation. People who are recovered the residential land, having no other residential place then within tirme waiting for rehabilitating the new place, will be arranged in the temporary houses or supported with money for house renting; the time and the support level in details are regulated by Provincial PC in accordance with the local reality. - As per Article 28: Restoration allowance Households, people directly make agricultural production, when being recovered more than 30% area of assigned agricultural land, will be supported for stabilizing the life within 3 months without relocation and within 6 months with relocation; in case relocate in areas with difficult or especially difficult socio-economical conditions then the support time is maximum of 12 months. The support level in cash for one person per month equivalent to 30 kg of rice calculated as per the average price in local region. When the GOV recovers land of economical entities, registered business households and causes business pausing, the maximum support level is 30% of an annual income after tax, according to the average income of three subsequent years before confinned by the tax agency. The support level in details are regulated by Provincial PC in accordance with the local reality. - As per Article 29: Support for changing the career and creating employment. - As per Article 30: Support for the hirer not belonging to the state ownership Households, people who are renting houses not belonging to the state ownership, when being recovered the land by GOV and must dismantle the house and relocate then will be supported with the displacement cost equivalent to the level regulated at Item 1 Article 27 of this Decree. Pursuant to the local reality condition, the Provincial PC regulates the support level to stabilize their life and production. Plan on compensation and resettlement 29 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - As per Article 31: Support level when recovering the public land of communes, wards or towns. - Other support such as beside the support regulated in Articles 27, 28, 29, 30 and 31 of Decree 197/2004/ND-CP, pursuant to the local actual situation, the Chairman of Provincial PC decides the other support measures to ensure the life and production stabilization for people who were recovered the land; in special cases, this will be submitted to the Prime Minister for decision. Forms of subsidy and bonus for PAPs Type of subsidy Amount - Monthly subsidy for relocated PAPs 30kg rice/month for each person in 6 months, subsidy granted at one time for each household with total or partial land area that impossible to substitute: - Displacing subsidy 1,000,000 - 3,000,OOOVND for inside province; 3,000,000 - 5,000,OOOVND for outside province. - Displacement subsidy Maximum of VND 3,000,000 for inside province and VND 5,000,000 for outside province. Supporting for the whole cost for dismantling, installation. Supporting the house-renting money (due to the decision of the Chainnan of Provincial PC) - Subsidy for life and production 30 kg of rice/month/person within 3 stabilization months if not displace; within 6 months if displacing the accommodation and within 12 months if displacing to the difficult accommodation. Supporting 30% of the income in one year if affecting to the business. - Subsidy for changing career and The impacted household losing over 30% creating the employment area of the agricultural production land will be supported for changing career. - Other subsidy levels Due to the decision of the Chairman of Provincial PC. Plan on compensation and resettlement 30 T Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 3.5 IMPACTED CATEGORIES By the nature of the project impacts as described above and based on the survey of the PAPs the impacted categories are classified into 7 categories. Category 1: Temporary acquisition of productive land in ROW. Category 2: Temporary acquisition of residential land and garden land in ROW without houses or structures in ROW. Category 3: Temporary impact on residential and garden land. Partial house/building within ROW (the impacted area is less than 25% but not affect to the common structure. Residential and garden land outside of ROW is sufficient for re- organizing (over 60m2 in urban area and 100m2 in rural area). Categorv 4: Temporary impact on residential and garden land. Impact more than 25% or less than 25% of total house/building area and impact to the common structure. Land outside of ROW is sufficient for re-organizing (over 60m2 in urban area and 100m2 in rural area). CateeorV 5: Temporary impact on residential or garden land in ROW. House/structure is partially or totally affected. Land outside of ROW is not sufficient for re-organizing (less than 60m2 in urban area and 100m2 in rural area). CateeorY 6 : Permanent land acquisition for tower foundation. Cate2ory 7: PAP impacted on business or other services Refer to Appendix 1 for details of impacted categories. Plan on compensation and resettlement 31 I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 4 SOCIO-ECONOMIC CONDITION OF PROJECT AREA & PROJECT IMPACTS 4.1. Inventory of project impacts Inventory of project impacts is implemented by PECC4 with coordination and assistance of project local authorities. The content of inventory focuses on: - Overall survey of project affected households - Survey of affected public assets, enterprises, collective farm, afforestration yards,... - Survey of land acquisition area for project construction. The survey is implemented by Survey Group in coordination with project affected local sections. Each survey group consists of 3 or 4 people. General survey votes concerning the socio-economical condition as well as impacts on land, trees, crops, etc... are established for 100% households with houses affected by project. Socio-economic survey was implemented with households for so as to determine characteristics of affected community, evaluating the population condition, premises, main economic activities, income of households,... The data of this socio-economic survey are used to orient the resettlement and compensation policy and to make base for measurement of life rehabilitation level in the process of resettlement implementation later on. 4.2. Socio-economic condition of project area 4.2.1. Binh Dinh Province Binh Dinh is a province on the coastal area of the Southern Central Region, adjacent in the North to Quang Ngai province, in the South to Phu Yen, in the West to Gia Lai province, in the East to the Eastern Sea. The natural land surface of the whole province is 6,076km2. In administrative structure, Binh Dinh has Qui Nhon City and the districts namely An Lao, Hoai Nhon, Hoai An, Vinh Thanh, Phu My, Phu Cat, Tay Son, An Nhon, Tuy Phuoc, Van Canh. Quy Nhon city is the political, economic and cultural Plan on comnpensation and resettlement 32 Quy Nhon - Tuy Hoa 22OkVftransmission line Feasibility Study center of the province, with many ethnic groups and the total population of the province is 1,055,372 inhabitants till 2000. There are many ethnic groups living in Binh Dinh province: The Kinh people occupies 98% of the population, the remaining are some other ethnic minorities such as Ba Na, Hre, Cham etc. Binh Dinh is situated on the important communication lines of the country: National Road IA and national railways along the province, National Road 19 to Gia Lai and highland provinces. The Seacoast has 134km length with many islands, gulfs and bathing seashores. Quy Nhon port has favourable exchanges with Phu Yen province, the Highlands, Lowee Laos, Northeast of Cambodia. These areas have great potentialities of goods, specific forestry products, industrial crops, minerals,etc... The topography of Binh Dinh province is complex, divided into 3 areas. The mountainous area occupies 70% the total surface, situated in the west, belonging to the east side of Truong Son Range, average altitude 500m. The hilly area between the mountains and the plains occupies about 10% the total surface. The plane on seacoast occupies about 20% the total surface. 4.2.2. Phu Yen Province Economy: Phu Yen Province gets low point of departure in economy but in the period 1991 - 1995, GDP has increased in average 9.4% each year, in 1995 - 1998 increased correlatively 1,037 milliards VND, 1,168 milliards VND and 1,355 milliards VND Society: Phu Yen is divided in 8 administrative units: Tuy Hoa City and 07 districts: Tuy An, Song Cau, Dong Xuan, Son Hoa, Song Hinh, Phu Hoa and Tuy Hoa. Tuy Hoa City is the socio-economic and cultural centre of the province. Phu Yen has many ethnic groups among which the Kinh people occupies 95.5% of the total population, the remaining ethnic minorities are Ede, Bana, Cham Hroi and others living mainly in mountainous districts: Song Hinh, Dong Xuan, Son Hoa with irregular distribution. The population living in countryside is 81.1%, city is 18.9%. Socio-economic development objectives in the period 2000 - 2010 - GDP growth rate on average annually 12 -13%. - GDP per capita on average in 2010 reaching 700 -800 USD. Plan on compensation and resettlement 33 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Export turnover striving to reach 30 millions USD in 2010. - Budget revenue striving to reach 12% GDP in 2010. - Population increase rate will be reduced to 1.7% in the period 2001 - 2010. 4.3 PROJECT IMPACTS Categories of Project impacts: Safe corridor for the line route is defined on the Decree No.54-1999/ND-CP dated 8 July 1999 by Gov on security protection for high voltage power network and Decree No.1 18/2004/ND-CP dated May 10h, 2004 regarding the amendment of some articles in No.54-1999/ND-CP dated July 8 , 1999. Project impacts including of: + All houses and public structures in the safe corridor are required to moved. + All high trees over 4 meters high in the safe corridor of T/L will be cut. + All structures out of the safe corridor but it is supposed to impact to the project or be affected by the project such as bomb and mine warehouse, gas station, stone mine, communication centers, etc will be removed. It should avoid these structures during process of investigation; if it is impossible due to difficult topography, removal of these structures must be considered and discussed. + Permanently acquisition land for the project consists of: Land permanently acquired for construction of tower foundation. + Temporary impacted land for the project consists of: - Areas of safe corridor of T/L and land area during the process of pulling conductors, etc... The impacted land area will be expected temporarily acquired from 01 month to 18 months, the affected time depends on weather and project construction schedule. Results of survey Inventory survey work for project impacts was carried out from 2004. Results are as below tables: Plan on compensation and resettlement 34 !~~~~~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study Table 4.1: Inventory ofproject land impacts No. Kind of impacts Unit Binh Dinh Phu Yen Remarks 1 Crops m2 0 522,686 2 Paddy 2 0\ 68,300 3 Eucalyptus tree 21,037 31,664 4 Fruit Trees tree 0 648 5 Cashew tree 32 1,006 6 Natural forest m2 19,101 188,362 Permanent land acquisition for tower foundation 7 Forest land m2 3,048 8,728 Agricultural land m2 9,067 Residential land m2 265 654 8 Affected households household 17 41 On Quy Nhon - Tuy Hoa 220kV line route, there are 58 affected households in which 29 households must be compensated. These households are allowed to be stayed, however the grounding system will be improved to ensure and maintain their lives in the safe corridor of the line route. For the temporary impacts on paddy and crops, only make compensation on the area due to conductor pulling is of 5m (the safe corridor of the line route is of 21.2m). There is no affected ethnic minority household then the impacts on ethnic minorities are not mentioned in this RAP. Categories of affected households Due to the specific characteristic of the T/L development project, affected households are classified as per Appendix 1. Plan on compensation and resettlement 35 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 5 PUBLIC PARTICIPATION AND CONSULTATION 5.1 Objectives of information campaign and consultation program Information dissemination to consultation with and participation of the affected people and involved agencies (i) reduce the potential for conflicts (ii) minimize the risk of project delays and (iii) enable the project to design the resettlement and rehabilitation program as a comprehensive development program to fit the needs and priorities of the affected people thereby maximizing the economic and social benefits of the project investment. The objectives of the Public Information Campaign and PAP Consultation Program are as follows: * To share fully information about the proposed project its components and its activities with the affected people. * To obtain the cooperation and participation of the affected people and communities required to be undertaken for resettlement planning and implementation. * To ensure transparency in all activities related to land recovering, compensation, resettlement and rehabilitation for PAPs. * To obtain information about the needs and priorities of the affected people as well as information about their reaction/feedback to proposed policies and activities. PAPs will be entitled to participate in different stages during the process of investigation, survey, RAP preparation and implementation. They will be invited to participate in meetings organized by the owner and local authorities in order to offer opinions on replacement alternatives, entitlement policies, listening to procedures, process of grievance implementation, responsibility of competent institutions and responsibility of PAPs during the process of RAP implementation. 5.2. Information campaign, PAPs & agency consultation There are two phases of the public infornation campaign and RAP consultation: Plan on comnpensation and resettlement 36 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Phase 1: During RAP planning and survey, make interviews with PAPs for their expectation and selection of compensation measures. During the process of investigation, make coordination with local authorities for agreement on line route selection. Phase 2: After RAP's approval, PMB and local authorities will organize meetings with PAPs to announce information of project, compensation policy and entitlement, replacement solutions, allowances, subsidy mentioned in RAP plan. To ensure that PAPs, their representatives and local governments of the affected areas fully understand on the details of RAP, PMB will also announce to all PAPs the compensation and rehabilitation policy applied in the project before making compensation and resettlement payment for PAPs. The RIB will contain information on the followings: Part I - Project description. - Project objectives - Implementation schedule - Project impacts - Eligibility to compensation and rehabilitation and entitlements policy for the project affected people - Institutions are responsible for resettlement Part 2 - Specific entitlements of PAPs - Description of the detailed impact of the project on the specific household - Compensation rates for each type of impact - Legality and Eligibility to compensation - Resettlement and rehabilitation alternatives. - Implementation schedule for compensation and resettlement Plan on compensation and resettlement 37 m - - m~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 5.3. Information dissemination and PAPs' consultation According to policy applied in this project, all PAPs are entitled to project information, entitlement to compensation. All PAPs have the right to take part in RAP implementation to ensure that they enjoy proper compensation. PAPs will be informed and consulted through the following stages: + Staffs of PMBs and Resettlement Committees of provinces, districts (town) and commune (ward) authority confirm the land acquisition part and make inventory of all structures, land, crops and trees affected by the project with the help of PAPs as well as the public structures affected. + PMP and Resettlement Committees of provinces, districts, commune authority will organize meetings with participants of land recovering process, announce the project information to them, discuss on their suggestion and opinions. All PAPs and people are invited to participate in this meeting. The meetings schedule and participants are expected as follows: The first time: It is expected to organize after the project's approval with the above mentioned content, but the project impacts and resettlement and compensation policy are pressed in order to take advantage of PAP's participation in the inventory and survey work Participants are: - Representative of PMB - Representative of Provincial Resettlement Committee - Representative of District level authority - Representative of Commune level authority - PAPs or representatives of PAPs The second time: It is expected to organize before resettlement and compensation payment, with the same content of the 1st time but compensation policy and schedule are pressed to ensure the fair and give favorable condition for site clearance work. Participants are: - Representative of PMB Plan on compensation and resettlement 38 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Representative of Provincial Resettlement Committee - Representative of District level authority - Representative of Commune level authority - PAPs or representatives of PAPs - Representative of PECC4 The meetings are organized with following content: + Cadres of PECC4 state the project objectives, make detailed description of the project impact on land, agricultural crops, the policies, principles of implementation as well as inform the policies of compensation on properties, land, agricultural crops of the project Compensation Committee. + Reference to opinions during the project execution stage + General infonnation on the project Right after signing credit agreement and preparation for project commencement, the Project Management Board will organize meetings with involved Provincial People's Committees of Binh Dinh, Phu Yen, and Quy Nhon city; District People's Committees of Song Cau, Tuy An, Tuy Hoa, Phu Hoa and PC of affected communes in order to inform local authorities of all levels on project policy, suggesting them to coordinate their activities concerning the site clearance work. + General information on RAP When carrying investigation on project impact, a campaign of information and reference on opinions about RAP must be taken including: socio-economic documents, investigation sheet on statistics of land, properties, agricultural crops being affected; giving instructions on filling all necessary information in the available investigation sheet, organize people meetings to inform the policies of compensation price applying, the progress of project for affected households and local authorities of all levels. + Information spread on local multi-media means The PMB works in combination with the local authorities for information on multi-media means such as local radio system about the project such as the stages of Plan on compensation and resettlement 39 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study project development, information on RAP and project impact on the community in the project area. After obtaining the public comments, summarizing the results collected with the agreement of local inhabitants in the project area and RAP is approved, compensation measures will be carried out, and from then implementing the site clearance work and preparing for work execution. Plan on compensation and resettlement 40 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 6 GRIEVANCE AND APPEALS The main objective of RAP implementation is to ensure the fair and adequacy during compensation payment for PAPs. The resettlement and compensation program should be implemented in such a way that satisfies both partners: the owner and PAPs. Grievance, complaint and solution are the process related to the owner and PAPs during the process of RAP implementation. To solve them timely and effectively, relevant institutions such as PMB, DRC, PRC need to respond to the complaints of the PAPs speedily and sensibly, avoid project delays and difficulty for PAPs. The solution should be agreed by PAPs. During the project implementation, PAP's complaints and grievances will be dealt with according to the regulation of Vietnamese laws. PAPs raising complaints will be treated fairly and guided by related agencies on the order, procedures and complaints of RAP, in addition no charge will be paid for their complaints. Since the entire resettlement and rehabilitation program is being carried out with the participation of the PAPs, to ensure that the PAPs have avenues for redressing their grievances related to any aspect of compensation and resettlement, detailed procedures of redresses of grievances have been established for the project. The mechanism is designed to be easy, transparent and fair. Complaints and grievances related to any aspect of RAP's, including the determined area and price of the lost assets, will be handled as follows: First step: If any person is aggrieved by any aspect of the resettlement and rehabilitation program, he/she can lodge an oral or written grievance with commune authorities. Commune People's Committee will resolve the issue within fifteen days from the date it receive the complaint. Second step: If any aggrieved person is not satisfied with the decision in stage 1, he/she can bring the complaint to the District People's Committee (DPC) or District Plan on compensation and resettlement 41 Quy Nhon - Tuy Hoa 22OkVtransmission line Feasibility Study Resettlement Committee (DRC) within fifteen days from the date of the receipt of the decision in stage 1. The District People's Committee (DRC) or District Resettlement Committee (DRC) will reach a decision on the complaint witiin fifteen days. Third step: If the PAP is still not satisfied with the decisiQn at district level, he/she can appeal to the Provincial People's Committee (PCC) or Provincial Resettlement Committee (PRC) within 15 days of receiving the decision of the DPC or DRC. The Provincia] People's Committee (PRC) or Provincial Resettlement Committee (CRC) will reach a decision on the complaint within fifteen days. Fourth step: If the PAP is not satisfied with the decision of the Provincial level, the case may be submitted for consideration by the District Court within 15 days of receiving the decision of the PPC or PRC. PAP's will be exempted from all administrative and legal fees. Coercion for site clearance can not be applied while PAPs are waiting for solving the complaints. In case an oral compliant is made, it will be written on paper by the commune and processed. Commune People's Committee will resolve the issue within 02 weeks. In case of PAPs are illiterate persons, they can make an oral complaint with the representatives of affected households and their representatives will record all queries to submit to authority levels. Every authority level will resolve the complaints as per the time regulated above. The disputes are organized publicly and implemented in accordance with law. Detailed procedures for redress of grievances and appeal process shown publicized among the PAPs during participation meetings and also in the offices of RBs. Plan on compensation and resettlement 42 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 7 MONITORING & SUPERVISION Implementation of RAPs will be regularly supervised and monitored by the respective PCs/PMB in coordination with the respective District and Communes Peoples' Committees and Communes. The findings will be recorded in quarterly reports to be furnished to EVN or MOI. 7.1. INTERNAL MONITORING & SUPERVISION Internal supervision and monitoring include the following activities: - Verify that the baseline information of all PAP's has been carried out and that the valuation of assets lost or damaged, and the provision of compensation, resettlement and other rehabilitation entitlements has been carried out in accordance with the provisions of this Policy Framework and the respective RAP. - Oversee that the Inventories and RAP's are implemented as designed and approved. - Verify that funds for implementing the Inventories and RAP's are provided to the respective PMBs at local level (provincial/district) in a timely manner and in amounts sufficient for their purposes, and that such funds are used by the respective PMB's in accordance with the provisions of RAP. - Record all grievances and their resolution and ensure that complaints are dealt with in a timely manner. 7.2. Independent monitoring An independent agency or individual consultant will be retained by PMB of the MOI and EVN to periodically carry out external monitoring and evaluation of the implementation of RAP's. The independent agencies will be academic or research institutions, non-Governmental Organizations (NGO) or independent consulting firms, all with qualified and experienced staff and terms of reference acceptable to the World Bank. In addition to verifying the information furnished in the internal supervision and monitoring reports of the respective PMBs, the external monitoring agency will visit a Plan on compensation and resettlement 43 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study sample of 20% of household PAPs in each relevant province six months after each RAP implementation to: - Determine whether the procedures for PAPs participation and delivery of compensation and other rehabilitation entitlements has been done in accordance with this Policy Framework and RAP. - Assess if the Policy Framework objective of enhancement or at least restoration of living standards and income levels of PAPs have been met. - Gather qualitative indications of the social and economic impact of Project implementation on the PAPs. - Suggest modification in the implementation procedures of RAPs, as the case may be, to achieve the principles and objectives of this Policy Framework. Plan on compensation and resettlement 44 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 8 IMPLEMENTATION ORGANIZATION ON COMPENSATION AND RESETTLEMENT PLAN 8.1. MEASURES FOR THE PROJECT IMPLEMENTATION 8.1.1. Announcement to PAPs All PAPs shall be thorough informed about the rights and policies of RAP including entitlement policies, rate of compensation for every type of impact, the active participation right in land acquisition process, complaint and grievance. RAP information will be prepared by PMB and announced to all PAPs or informed at the meetings in province, district and commune levels; on television, radio, newspaper, hung in public places such as administrative quarters of communes and schools. Public announcement tasks shall be implemented immediately after EVN and WB's approval of project is obtained. The information announced consists of: + Schedule of project implementation + Eligibility and non-eligibility to compensation and resettlement + The compensation principle: only make compensation for households using land before inventory making and the official announcement about land acquisition of State. 8.1.2. Compensation deadlines The project impacts conclude households with areas of residential land, agricultural land, forestry land, etc... affected permanently or temporarily. PAPs agreed to receive compensation amount so the RAP is carried out in package to PAPs. Compensation payment for land, assets, paddy and crops; land delivery for resettlement should be done at least 02 months before the project land acquisition. PAPs will receive subsidies at the beginning of months and after their receiving, they will have to transfer land for Site Clearance Board at least one month before construction time. 8.2. RAP implementation process RAP implementation will be included in 3 actions as below: Plan on compensation and resettlement 45 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study + General action: Just at once when beginning the project implementation work + Separately action: at several times, once for each component of the project + Continuously action: Continuously action for the stages of RAP implementation. Basic actions of the proiect Action 1: After RAP approved, PMB hires qualified agency for independent monitoring, this agency must be approved by EVN and WS Action 2: Provincial authorities and PMB are required to supply Resettlement Committees with fully costs and declare the tasks for RAP implementation. Action 3: District Resettlement Committees carry out the Detail Measurement Survey of affected assets and socio-economic conditions, determining the compensation unit price and if necessary, checking and readjusting it in order to make compensation at market price and conversion price. Action 4: Immediately the ends of final inventory survey, Resettlement Committees of Districts will inspect and define the official number of PAPs, impacted properties and total compensation amount for PAPs. Action 5: Resettlement Committees will officially announce the RAP policy, schedule of project implementation and information for RAP to PAPs at public meetings including issues related to compensation, resettlement and land clearance. Action 6: It is suggested to give priority to compensation payment for households with permanent impacts, assisting them in transferring the production mode and mechanism or with land for resettlement and life stabilizing. After that, making compensation payment for PAPs affected on other properties. Action 7: During the project implementation, Independent and Internal Monitoring Institutions will supervise/ monitor all actions of RAP implementation, at the same Plan on compensation and resettlement 46 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study time giving proposals, discussions or report the changes during project implementation as well as suggest solutions. 8.3. RAP implementation schedule RAP will be implemented as per the schedule established to ensure the site clearance work and schedule on project construction. Payment of rehabilitation and furnishing of other restoration/assistance entitlements is made in cash. Organizational arrangement Power companies and all project provinces will arrange full experienced staffs to ensure that RAP will be implemented smoothly as per the accepted schedule. Plan on compensation and resettlement 47 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 9 COST AND BUDGETS 9.1. Budgets Budget for RAP implementation will be from the self-financed capital and loans from WB. EVN entrusted Central Power Projects Management Board (CPPMB) with management and directing project 's activities as well as project finance management. CPPMB has coordinated with the provinces, districts, departments of Finance and Goods Price, Resettlement Committees at all levels to implement compensation payment. 9.2. Determining the compensation price Compensation price for temporary and permanent impacted cultivated land, trees and crops based on: - The Government Decree No 188/2004/ND-CP of November 16th, 2004 on the stipulation of the frame for the price of land types. - Decisions on compensation price of Provincial People's Committee, Departments of Finance and Goods Price of Binh Dinh and Phu Yen Provinces. 9.2.1. Compensation pricefor land Compensation unit price of different types of land as follows: Table 9.2.1. Compensation unit price for land (VND/m2) No. Item Unit Price Remarks I Binh Dinh Province 1 - Forestry land 7,200 2 - Agricultural land 900 3 - Residential land 630,000 II Phu Yen Province 1 - Forestry land 600 2 - Agricultural land 900 . a 3 - Residential land 600,000 Plan on compensation and resettlement 48 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 9.2.2. Compensation unit pricefor trees and crops Compensation for trees and crops on the whole ROW. Provincial Department of Finance and Goods Price in coordination with relevant local authorities will be responsible for offering the rational compensation costs for project impacts. Table 9.2.2. Compensation unit price for trees and crops No. Item Unit price Remarks I Binh Dinh province 1 Crops 2,000 VND/m' 2 Paddy 900 VND/m' 3 Eucalyptus 10,000 VND/tree 4 Fruit trees 150,000 VND/tree 5 Cashew 150,000 VND/tree 6 Coffee 80,000 VND/tree 7 Sugar cane 1,500 VND/tree 8 Forest 2,000 VND/m' II Phu Yen province 1 Crops 700 VND/m' 2 Paddy 900 VND/m' 3 Eucalyptus 10,000 VND/tree 4 Fruit trees 130,000 VND/tree 5 Cashew 100,000 VND/tree 6 Forest 2,000 VND/m2 9.3. Compensation cost estimate 9.3.1. Costfor RAP establishment Cost for RAP establishment consists of: - Preparation work: cost for document study, translation, preparation of forns for socio-economic survey and PAPs 'inventory. - Site survey work: work with local authority for detailed measurement survey (DMS) of PAPs and collecting compensation price list. Plan on compensation and resettlement 49 I~~~~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study - Summarize data for establishment of report and RAP report. - Making Reports at Binh Dinh and Phu Yen provinces, PMB and EVN Survey work is carried out in two stages: Preliminary stage and Detailed Measurement Survey. 9.3.2. Compensation cost Based on the impacted area of land and crops and extent of impacts (described in the previous chapters), compensation costs of the project including of: - Compensation for pernanent land acquisition for construction of tower foundation. - Compensation for structures, houses, paddy and crops affected inside the safe corridor of the line route. - Subsidy for PAPs as stipulated in law. 9.3.3. AManagement cost Management cost consists of cost for activities of PMB and local PRCs including: material base, salary and other allowances for administrative apparatus. For organizational mechanism of these RCs, staffs often work concurrently during project construction period, only several members work permanently by labor contracts. - Cost for meetings, announce with PAPs or their representatives. - This total cost is temporarily calculated 1% of total compensation cost for project impacts stated in item 9.3.2. 9.3.4. Supervision cost - When implementing the project, PMB will sign contract with independent supervision organizations. Total cost for supervision is temporarily calculated as 2% of total compensation cost for project impacts and cost for RAP establishment stated in item 9.3.1 and 9:3.2. 9.3.5. Reserved cost Reserved cost for unpredictable problems is calculated as 10% of total compensation cost for project impacts and cost for RAP establishment stated in item 9.3.1 and 9.3.2. 9.3.6 Total cost for RAP implementation Total compensation cost for projects is of VND 2,869,748,235. Plan on compensation and resettlement 50 I~~~~~~~~~~~~~~~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study CHAPTER 10 CONCLUSION AND PROPOSALS 10.1. Conclusion After investigation, summing up data on damages in the ROW, consulting opinions of the relevant local authorities and community of affected households. Through the making of RAP, we have the following conclusions: * Investment for work construction is necessary in order to receive energy power from Ha Song Ba Hydropower Plant and energy power transmitted on the the route line, meeting the requirements of energy use for the provinces Binh Dinh, Phu Yen, and vicinities. * As the secure corridor of route line and construction site of substation spreading on the area of 02 provinces, at development of compensation and making land clearance works of the project, the relevant local committees and services have to work in combination to ensure favorable results. * Report on determination of land surface, trees and agricultural crops being affected by the project. * Summing up report and calculation on damages due to the project, then bringing up common compensation price. * Study and submission of RAP planning for community of affected inhabitants. 10.2. Proposals * Detailed investigation of affected items must be carried out so as to supply detailed c6mpensation price for each affected household. * Deep and broad propagation of infonnation on the project by multi-media system, etc.. .to the habitants in order to minimize the negative impact of individuals profiting of the standpoint, investment policy of the government. * The Project Management Committee, Resettlement Committee and Compensation Committee have to inspect closely the execution of compensation and land clearance works in preparation of work execution. * Appointment of a standing team to solve in a timely way the complaints and claims of affected households. Plan on compensation and resettlement 51 I Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study APPENDICES Plan on compensation and resettlement 52 I Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study ANNEX 1: ENTITLEMENT MATRIX No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PAPs I Temporary All PAPs PAPs - Cash compensation for affected - Trees have to be cut are regulated by Article 1- acquisition of have trees, with/without trees at the replacement cost plus Item 2 of Decree No.1 18/2004/ND-CP dated May productive land in crops, land cost for cutting trees, crops at 10th, 2004 regarding the amendment of some ROW other certificate market price. Number of crop article in No. 54-1999/ND-CP dated July 8th, 1999. assets in included in patterns to be compensated based on the protection of the high voltage networks. ROW the inventory on the time of temporarily acquired - PMB and local authorities determine and ensure or able to of land. that compensation for trees will be at the prove land - No compensation for land replacement cost and for crops at the market price. occupancy - Rehabilitate land after the project If PAP is requested for cutting affected trees, PIIB pror to cut- construction. will pay money for this work. PAP has right for off date. using salvageable trees. - Full compensation at least 01 month before land clearance. Payment to PAPs will be delivered by PMB and Resettlement Committees (RCs). - Affected land in ROW will be rehabilitated by contractors after the project construction and land could be used with the restricted purposes. - Finance available for compensation and well information disclose/ disseminate 2 Temporary All PAPs -do- - Cash compensation for affected - Trees have to be cut are regulated by Article 1- acquisition of with fruit trees and trees at replacement Item 2 of Decree No. 118/2004/ND-CP dated May residential and orchards cost. 10th, 2004 regarding the amendment of some garden land in or trees in - No compensation for land article in No.54-1999/ND-CP dated July 8th, 1999 ROW without ROW - Rehabilitate land after the project on the protection of the high voltage networks. house or structures *._ ".Tx T construction. Plan on compensation and resettlement 53 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PAPs in ROW construction. - PMB and local authorities determine and ensure that compensation for trees will be at the replacement cost. If PAP is requested for cutting affected trees, PMB will pay money for this work. PAP has right for using salvageable trees. - Full compensation to PAPs at least 01 month before land clearance. Affected land in ROW will be rehabilitated by contractors after the project construction - Payment to PAPs will be delivered by PMB and RCs - Finance available for compensation and well information disclose/ disseminate 3 Temporary impact All PAPs -do- House/ building: - House and building have to be demolished or on residential and have - PAP can opt for i) Remain their could be existed are regulated by Article 1- Item 3 garden land. Partial house/buil houses or building in ROW with the of Decree No.118/2004/ND-CP dated May 10th, house/building ding and conditions regulated by - Trees have 2004 regarding the amendment of some article in within ROW (area trees/fruit to be cut are regulated by Article 1- No.54-1999/ND-CP dated July 8th, 1999 on the in ROW less than trees in Item 3 of Decree No.1 18/2004/ND- protection of the high voltage networks. 25% of total area) ROW CP dated May 10th, 2004 regarding - Consultation for PAP's options on remain their and the demolished the amendment of some article in house in ROW or move out of ROW. area does not No.54-1999/ND-CP dated July 8th, - PMB and local authorities determine and ensure impact to the 1999 on the protection of the high that compensation will be at the replacement cost, remaining voltage networks.Subsidy allowance without deduction for salvageable materials house/building. for fireproof materials and lightning - PAPs will demolish the impacted part/ room and Residential land arrestors for the existing reconstruct/or improve their houses themselves. and garden land house/building; or ii) Cash outside of ROW is compensation for the directly - Full compensation for trees and fiuit trees at least Plan on compensation and resettlement 54 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PAPs sufficient for re- affected rooms at the replacement 01 month before land clearance. If PAP is requested organizing (more cost and cost for demolishing an for cutting affected trees, PMB will pay money for than 60 m2 in the affected room. this work. PAP has right for using salvageable urban area and 100 - No compensation for land. trees. mmintherural - Rehabilitate land after the project - Full entitlement to PAPs impacted on area). construction by contractors. house/building at least 03 months before land Tree and fruit tree clearance. - Compensation for affected trees - Payment to PAPs will be delivered by PMB and and fruit trees at the replacement RCs cost. - land in ROW could be used with restricted Allowances: purposes. - Relocating allowance of 30 kg of - Finance available for compensation and well rice equivalent per person per month information disclose/ disseminate in six months. 4 Temporary impact All PAPs -do- House/ building: - House and building have to be demolished or on residential and have - PAP can opt for: i) Remain their could be existed are regulated by by Article 1- Item or garden land. house/buil houses or building in ROW with the 3 of Decree No.1 18/2004/ND-CP dated May 10th, Impact more than ding and conditions regulated by - Trees have 2004 regarding the amendment of some article in 25% or less than trees/fruit to be cut are regulated by Article 1- No.54-1999/ND-CP dated July 8th, 1999 on the 25% of total trees in Item 3 of Decree No.1 18/2004/ND- protection of the high voltage networks. house/building ROW CP dated May 10th, 2004 regarding - Consultation for PAP's options on remain their area but the the amendment of some article in house in ROW or move out of ROW demolished area No.54-1999/ND-CP dated July 8th, - PMB and local authorities determine and ensure will impact to the 1999 on the protection of the high that compensation will be replacement cost at the remaining of voltage networks. Subsidy time of payment. house/structure. allowance for fireproof materials - PAPs will demolish the impacted areas and Land outside of and lightning arrestors for the reconstruct/or improve their houses themselves. ROW is sufficient eNisting house/building; or ii) Cash P Plan on compensation and resettlement 55 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PA-Ps for reorganizing ( compensation at replacement cost - Full compensation for trees and fruit trees to PAPs more than 60 m2 in . for full areas of impacted at least 01 month before land clearance. If PAP is the urban area and house/building. requested for cutting affected trees, PMB will pay 100 m2 in the rural - No compensation for land. money for this work. PAP has right for using area). - Rehabilitate land after the project salvageable trees. construction by contractors. - Full compensation for impacted house and allowances to PAPs at least 03 months before land Tree and fruit tree clearance. - Compensation for affected trees - Payment to PAPs will be delivered by PMIB and and fruit trees at the replacement RCs cost.RC cllowances: - Cleared residential could be reused with restricted Allowances: purposes. - relocating allowance of 30 kg of - Finance available for compensation/ rice equivalent per person per month rehabilitation and well information disclose/ in six months. disseminate 5 Temporary impact AU PAPs -do- PAPs can opt for one of the - House and building have to be demolished or on residential and have followings: could be existed are regulated by Article 1- Item 3 or garden land in house/build i) Remain their houses or building of Decree No.118/2004/ND-CP dated May 10th, ROW. Full or ing and in ROW with the conditions 2004 regarding the amendment of some article in partial trees, fruit regulated by Article 1- Item 3 of No.54-1999/ND-CP dated July 8th, 1999 on the house/building trees in Decree No.118/2004/ND-CP dated protection of the high voltage networks. impacted and land ROW May 10th, 2004 regarding the - Consultation for PAP's options on remain their outside of is not amendment of some article in house in ROW or move out of ROW sufficient for No.54-1999/ND-CP dated July 8th, - PM]B and local authorities determine and ensure reorganizing (less 1999 on the protection of the high that compensation will be at replacement cost at than voltage networks. Subsidy the time of payment. Plan on compensation and resettlement 56 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PA-Ps 60 m2 in the urban allowance for fireproof materials - Replacement land, and resettlement sites area and 100 m2 in 4 and lightning arrestors for the development. the rural area) existing house/building; or ii) Cash - PAP receive compensation for the whole - PAPs receiving compensation will demolish the residential area which PAP occupied impacted areas and reconstruct/or improve their (not only for the impacted areas) and hmaced areasa r u/ o t properties associated with occupied houses themselves. land at replacement cost. Impacted - Full compensation for trees and fruit trees to land will be obtained by local PAPs at least 01 month before land clearance. If authorities; or ii) "Land for land" PAP is requested for cutting affected trees, PNIB with the same area PAP occupied will pay money for this work. PAP has right for and cash at replacement cost for the using salvageable trees. affected assets associated with land. - Full compensation for land impacted house and Land occupied by PAP will be allowances to PAPs at least 05 months before land obtained by local authorities. clearance. - Compensation for affected trees - Payment to PAPs will be delivered by PMB and and fruit trees at the replacement RCs cost. - Cleared residential could be used with restricted Allowances: purposes. . - Relocating allowance of 30 kg of - Finance/ land available for compensation/ rice equivalent per person per month rehabilitation and well information disclose/ in six months disseminate. - Transportation allowance for - PMB consult with PAP who are eligible to relocating PAP according to the rehabilitation for their options and prepare proposal Compensation Decree 22/1998 CP for rehabilitation programs in the period of RAP dated April 22, 1998 of GOV. implementation. - Rehabilitation assistance if PAPs Plan on compensation and resettlement 57 Quy NAhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PAPs permanently losing business or more than 25% of their incomes. - Incentive for relocating in a timely manner: 5,000,000 VND/HH 6 Permanent All PAPs -do- For PAP losing productive land: - Consultation for PAP's options on land acquisition of land occupied a Land loss less than 25% of their compensation. for tower land and total landholdings - PMB and local authorities determine and ensure foundations, properties - Cash compensation for the lost area that compensation will be at replacement cost at substation and associated if the remaining plot is still the time of payment. access roads etc. with land economically viable. - Replacement land, and resettlement sites permanentl y impacted - Cash compensation for the whole development. by towers impacted plot if the remaining plot - PAPs receiving compensation will demolish the foundations is not economically viable. impacted areas and reconstruct/or improve their , substation - Cash compensation for properties houses themselves. and access associated with land - Full compensation for trees and fruit trees to roads etc. PAPs at least 01 month before land clearance. If 25% of their total lano oldings: PAP is requested for cutting affected trees, PMB will pay money for this work. PAP has right for lPAP can opt for the using salvageable trees. - Full compensation for impacted house and i)"Land for land" with the same area allowances to PAPs at least 05 months before land and productive of impacted area if clearance. the remaining plots are still - No award civil work contract before completion economicviable and for the whole of compensation and reorganizing houses or impacted plots if the remaining rofcaomn plots are not economicviable. relocation. - Payment to PAPs will be delivered by PMB and ii) Cash for land at the replacement RP r Plan on compensation and resettlement 58 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study No Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PAPs cost. RCs - Compensation for trees and affected - Finance/ land available for compensation/ fruit trees at the replacement cost. rehabilitation and well information disclose/ - Rehabilitation assistance. disseminate. . For PAP losing Residential and - PMB consult with PAP who are eligible to garden land: rehabilitation for their options and prepare proposal for rehabilitation programs in the period of RAP - If remaining land is sufficient implementation. for reorganizing (more than 60 m2 _ PAPs will be granted with Land Use Right in the urban area and 100 m2 in the wil an U rural area): Cash compensation for Certificate lost area and assets associated with without payment of administrative fees. land. - If remaining land is not sufficient for reorganizing: PAP can opt for i) cash compensation at replacement cost for land and assets on land, or ii) "land for land" compensation for the whole , residential.area which PAP occupied (not only for the impacted areas) and properties associated with occupied land. For affected house and building, the same entitlement to PAP of categories 3 or 4 or 5. 7 PAP impacted on All PAPs -do- (a) Temporary impact on business or - Full compensation for incomes lost to PAPs at business or other impacted other services. least 0 1 month before land clearance. services on business - PMB consult with PAP who are eligible to _tirl anA r I Compensation for income lost in the I . . r . . Plan on compensation and resettlement 59 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study N0 Type of loss Applicati Definition of Compensation Policy Implementation Issues on entitled PA-Ps and other affected time rehabilitation for their options and prepare proposal services (b) Permanent impact on business or for rehabilitation programs in the period of RAP other services. Rehabilitation assistance. Plan on compensation and resettlement 60 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Annex 2: Table of compensation quantity for Quy Nhon - Tuy Hoa 220kV transmission line TOTAL COST FOR COMPENSATION IN BINII DINII PROVINCE I. Compensation on land, houses, trees and crops: 443,243,556 VND 1. Cost for improving houses in ROW: = 975,956 VND 2. Eucalyptus: 21.037 tree x 10,000 VND/ tree = 210,370,000 VND 3. Cashew: 32 tree x 150,000 VND/ tree = 4,800,000 VND 4. Forest: 19.101 m2 x 2,000 VND/m2 = 38,202,000 VND 5. Cost for LUR transfer at the position of permanent land acquisition tower: 3313.00 m2 - Forestry land: 3.048 m2 x 7,200 VND/ m2= 21,945,600 VND - Agricultural land: 0 m2 x 900 VND/ m2 = 0 VND - Residential land: 654 m2 x 630,000 VND/ m2 = 166,950,000 VND Cost for compensation and resettlement: 0 VND Cost for Compensation II. Board: 1%x (I) - 4,432,436 VND TOTAI. COMPENSATION MElSE (I + H) = 447,675,992 VND Plan on compensation and resettlement 61 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study TOTAL COST FOR COMPENSATION IN PHIU YEN PROVINCE I. Compensation on land, houses, trees and crops: 1,852,127,583 VND 1. Cost for improving houses in ROW: = 140,776,283 VND VND 2. Crops: 522.686 m2 x 700 VND/ m2 = 365,880,200 VND 3. Paddy: 68.300 m2 x 900 VND/ m2 = 61,470,000 VND 4. Eucalyptus: 31.664 tree x 10,000 VND/tree= 316,640,000 VND 5. Fruit trees: 648 tree x 130,000 VND/ tree = 84,240,000 VND 6. Cashew: 1.006 tree x 100,000 VND/ tree = 100,600,000 VND 7. Forest: 188.362 m2 x 2,000 VND/ m2 = 376,724,000 VND 8. Cost for LUS transfer at the position of permanent land acquisition tower: 18449.00 m2 -Forestry land: 8.728 m2 x 600 VND/m2 = 5,236,800 VND -Agricultural land: 9.067 rn2 x 900 VND/m2 = 8,160,300 VND - Residential land: 654 rn2 x 600.000 VND/ m2 = 392,400,000 VND Cost for Compensation II. Board: 1%x (I) 18,521,276 VND TOTAIL COST FOR COMPE.NSATION* (I + ) = 1,870.648,859 VND Plan on compensation and resettlement 62 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Total cost for RAP implementation of Quy Nhon - Tuy Hoa 220kV transmission line No. Item Amount (VND) Remarks Compensation cost for Binh Dinh 1 rovince 443,243,556 Compensation cost for Phu Yen 2 rovince 1,852,127,583 3 Total compensation cost 2,295,371,139 4 Cost for RAP establishment 246,409,686 Total cost for compensation and 5 RAP establishment 2,541,780,825 6 Management cost 22,953,711 7 Supervision cost 50,835,616 8 Reserved cost 254,178,082 9 Total cost for RAP implementation 2,869,748,235 Plan on compensation and resettlement 63 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Annex 3: Inventory of Project Affected People Name of Head of No. of ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Loss of Temporary Name of_Head of No. of Loss of Assets Loss of Crops Other Other Losses Losses Ho-uLsehold persons Tofti Land to be Loss Number and Structures Structures Area of Fruit trees assets Eg., (specify) No. Of Bholding a% type of lost permanent temporary residential lost Type Paddy Other Tombs, Residence Business Income in Of Hhold ~~ol~ in mT by of structures (M2) (MN) land lost and area (Specify) well, etc. (rented) Lost Loss M2 Type total (2) Number (M2) (No. &type Group No11 - Tran Quang Dieu QU~Y Nncity - Binhi Dinh Province Reniar____________s___ TIhese 1 4 1- Hunh Thi By 4 43,86 36 82 households 2 NguyenAn Liem 4 43,86 36 82 _ _ _ are still 3 Nguyen Van ThAo 1 43,86 36 82 _ _ _ allowed to be 4 Dao Thi La Hang 4 43,86 36 82 _ 1 _ stayed so not 5 Doan ThAnh Trung 3 43,86 36 82 = ______make 6 Nguygn Van TA 3 43,86 36 82 compensation 7 Le Dinh Cang 4 43,86 36 82 by house level IV 8 Nguyen Van Dong 5 43,86 36 82 = _ _ _ (only wood 9 Phan Thi 4 80,5 42 52 _ _ house with 10 Ho ic Thang 4 66,1 35 53 _ _ _ tile roof) 11 HuSnh Thic Sinh 3 43,86 36 82 |, 12 Nguyen Thi Nga 5 43,8 36 82 _ _ _ 13 MaiThamhQuin 4 43,86 36 82 | I I L 14 NguyenQuyetTien 3 43,86 36 821 = T I I Bui Thi Xuan Ward -Quy Nhon City - Binh Dinh Province 15 BaNg6 | _ | 1 6 16 100 T Goat-house | I I I T I I T_I _T 16 LamVanOuy Q_ | 24 0 0 Warehouse | 17 Lam Tli Ly _ __ 16 0 0 | Pigsty Xuan Loc Commune - Song Cau District - Phu Yen Province 18 | N yanV6 Hoang 3 24 24 | 100 House | Plan on compensation and resettlement ~4 t65 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 19 Ngo Tin Luc 6 12 12 100 House = = = = House 20 Vo VanEhoa 4 72 0 0 Howe_ __ _ __ __ _ _ _ _ __ _ _ _ _ _ ___ _ _ _ _ _ _ 21 Nguyen CA 8 120 0 0 louse 22 Dug VanThe 7 0 0 Iouse = == _ = = = 23 Nguyen Cong Khanh 8 120 0 0 House 24 NguyenVanCon 3 79 70 88 House = = = = = 25 Pam Van Dang 5 16 0 Pigsty 26 Nguy&e Va-n Phat 60 cowshed Xuan Phuong Commune - Song Ca District - Phu Yen Province _ 27 Nguy&eVanThing 4 68 68 100 Kitchen, _ _ _ __ _ _ Cowshed 28 Vo Vn Chinh 4 24 24 100 House 29 Ong Tien 24 24 100 Uninhabited house So Cau Town - Song Cau District - Phu Yen Province 30 | Pham IA Le. _ | 40 | cowshed 31 | Le Thi Mui _ | 24 | _ cowshed24 Xuan Tho I Cormnune^ - Song Cau District - Phu Yen Province 32 |N Nguyn Giao _ I | 40 |_| cowshed | _ _ _ _ _ _ _ An Dan Commune- Tuy An District- Phi Yen Province _ 33 NguyenC6ngThAnh | 24 | | cowshed | | __| 34 Ho Lieu _20 _| O | |cowshed 35 Do Thi D*c 1 36 36 100 House 36 TrAnLong 5 40 0 0 House I I I _T T _I 37 Truang VanThuky 3 56 36 72 | Cowshed 38 DoVan To 4 45 45 100 adtchen, Cowshed Plan on compensation and resettlement 66 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Chi Thanh Town - Tuy An District- Phu Yen Province 39 Phan Vn Cur 4 76 28 37 Kitchen, Cowshed 40 Phan Dinh Trung 6 98 50 51 Kitchen, Cowshed 41 Ong Dung 36 36 100 Uninhabited house An Dinh Comnae - Tuy An Dish ct- Phu Yen Province 42 Phan Thanh D3ng 3 60 0 0 _ 43 Phan Thoai 3 65 25 38 Kitchen _ = - = 44 Phan Sin 2 42 12 29 Wall 45 Phan Vin HoAng 3 45 15 33 46 Le ThiNgh1a 3 52 52 100 Wall, kitchen cowshed 47 Phan Thinh Long 5 76 76 100 House, cowshed, _ _ _ _ _ _ _ ~~~~~~~~~~ ~~~~~kitchen_ _ 48 NguyenVaaLu I 132 132_ 100 cowshed _ = . | | An Hi Com=me- Tuy An Distrit- Phu Yen Province 49 Nguyen Hoc 9 9 100 cowshed | 50 Hu| I ihVanTim ____12 12 100 | hut___. ____ ___ 51 VoThiThu 4 71 36 51 House, cowshed, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ~~~kitchen_ _ __ _ _ _ _ __ __ _ _ _ 52 LeThiHoi 5 49. 25 51 Ktchen, house 53 Chiu Thi Sum ___ 48 0 | 0 | Kitchen | _ _ _ _ _ i Hoa Kien Coommune- Tuy Hoa Town- Phu Yen Province Plan on compensation and resettlement 67 Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study 54 Cao Kim Thlnh 4 94 0 0 hv class house 55 Dao Van Hfing 6 20 0 0 TV class _ _ _ house _ _ _ 56 Nguy nHIu Huan 6 117 0 0 IV class _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ h ou se _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ __ _ _ _ _ _ IV clas 57 B| Thi Khoa 6 96 0 0 house Hoa Quag Bac Commune - Phu Hoa District- Phu Yen Province IV classT I 58 Nguyen TiPhuang 64 0 0 | I|u 59 V6Thilihng 78 0 0 | class Plan on compensation and resettlement 68 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Annex 4: Entitlements of Project Affected People Compensation for Other Assets Survey Name of Head of Compensation for Land Compensation for Structures Compensation for Crops & Trees (Noi dAt) - ts SNurvey Name of Head of 1ntUi Total in Dong No. Household Unit *1Unit Quantity Price Entitlement in Quantity Unit Pnce Entitlement in Quantity Unit Pnce in Entitlement in Quantity Price in Entitlement in Sq. Meters Sq. Dong Sq. Meters Sq. Dong Unft Dong Dong Unit Dong Dong J M eters ] _ _ _ _ _ _ __ _ __ 1 M eters _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Group No.11- Tran Quang Dieu Ward- Quy Nhon City- Binh Dinh Province I Huynh Thi Bay 36 0 0 0 2 Nguy&n An Liem 36 0 0 0 3 Nguyen Van ThAo 36 0 0 0 4 Dao Thi Le Hang 36 0 0 0 O 5 Doan Thanh Trung 36 0 0 0 6 Nguyen Van TA 36 0 0 0 7 L8 Dinh Cang 36 0 0 0 8 36 0 0 0 8 Nguygn V-an Dilng 3 9 Phan Thi 42 0 0 0 10 Ho Di(c Thang 35 0 0 0 __ Huynh Thic Sinh 36 0 0 0 12 Nguyen Thi Nga 36 0 0 0 13 MaiThanhQuan 36 0 0 0 F14 N~~Q~Ti 36 0 00 P Nguy& Quyet m en an r O6 Plan on compensation and resettlement 69 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Bui Thi Xuan Ward- Quy Nhon City- Binh Dinh Price = = 15 BaNg6 12 57.680 692.157 141.900 834.057 16 Lm VnQuy Qq 24 O 0 0 17 LIm Thi L1 12 0 0 141.900 141.900 Xuan Loc Comnmune - Song Cau District - Phu Yen Province 18 Nguyen V5 Hong 24 446.080 10.705.920 10.705.920 19 Ng8TanLuc 12 446.080 5.352.960 5.352.960 20 V5 Van Khoa 72 0 0 0 21 Nguyen Ca 120 0 0 | 0 22 D#ngVanTh8 66 0 0 141.900 141.900 23 Nguyen Cdng Ksbanh 120 0 0 0 24 Nguy& Vin Con 70 492.160 34.451.200 34.451.200 25 Pham VanDang 16 70.147 1.122.351 1.122.351 26 Nguyen Van Phat 60 3.921.273 3.921.273 Xuan Phuong Commune - Song Cau District - Phu Yen Province 27 Nguyn Van ThAng 32 460.800 14.274.560 | _ _ _ __ | 7.781.917 22.056.477 28 VoVanChinh 1 _ _ _ 24 3.914.617 | _ _ _ 1 | 141.900 4.056.517 29 OngTi&i I _ _ _ 24 4.260.457 | _ _ _ 1 | 141.900 4.402.357 Song Cau Town - Song Cau District - Phu Yen Province _ _ _ _ _ _ _ _ 30 |PhamL. I _ _ _ 24 57.680_| 1.384.313 | _ _ _ I | 141.900 1.526.213 31 |LB ThiMirbi 24 M|___J__ [ 2.969.913 | 1 _ _ 1 | | 2.969.913 Plan on compensation and resettlement 70 Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study Xuan Tho 1 Commune - Song Cau District - Phu Yen Province 32 Nguyn Giao 40 3.099.515 3.099.515 An Dan Commune- Tuy An District - Phu Yen Province 33 Nguy&i C8ng Thinh 18 57.680 1.038.235 1.038.235 34 HoLigu 20 2.119.197 2.119.197 35 Do Thi Duc 36 0 0 283.800 283.800 36 Tran Long 64 0 0 0 37 Truang Van Thuy 20 4.201.290 975.957 5.177.247 38 Dao Vui T 15 103.744 1.156.155 1.156.155 Chi Thanh Town- Tuy An District - Phu Yen Province 39 Phan VaC Cir 12 57.680 692.157 283.800 975.957 40 Phan Dinh Trng 30 4.550.343 975.957 5.526.300 41 (3ngDung = = 12 57.680 692.157 141.900 834.057 An Dinh Commune- Tuy An District - Phu Yen Province 42 Phan Thanh Dong 60 0 0 0 43 PhanThoi 65 -0 0 0 44 PhanSin 121 3.148.711 3.148.711 45 Phan Vgn Hohng 1 5 353.920 5.308.800 5.308.800 46 L6ThjNghia 25 3.659.315 2.539.818 6.199.133 47 Phan ThAnh Long 16 1.960.637 283.800 2.244.437 48 NguyenVanLuu 36 57.680 2.076.470 283.800 2.360.270 Plan on compensation and resettlement 71 I~~~~~ Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study An Eep C e Tuy An Distdrict - Phu Yen Province 49 Nguygn HQc 9 1.643.517 1.643.517 50 Huinh Van 'am 12 223.479 2.681.752 2.681.752 51 Vo Th Thu 36 0 0 283.800 283.800 52 L Th Hoa 25 5.446.429 5.446.429 53 Chau Thi Sum 48 0 0 0 Hoa Kien Commune- Tuy Hoa Town - Phu Yen Province_ 54 CaoKimThinh 94 0 0 0 55 DaoVAnHibng 20 0 0 56 Nguy&n Hfru Huan 117 0 0 0 57 BeziTAiKhoa 96 0 0 0 HoaQa Bac Comnune Phu Hoa District - Phu Yen Province 58 NguyLnThiPhuang 64 0 | 0 | J _ _ _ _ _ _ 0 59 V5Th,Thing 78 0 ol _ j _ ._ _ _ 0 Plan on compensation and resettlement 72 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study Annex 5: Socio-Economic Household Data Sheet of Project Affected People Occupation and Estimated Total Address of Name of Household Member Sources of Employment Income per No. Household Sex Age Ethnic Group Education Income Year N r.oup Kinh High State officer 8.700.000 No.l11- Hu'mh Thi Bay school 2 Dieu Ward- Kin Secondary State officer 10.000.000 QuyNhon Nguyen An Linm school 3 Cainh Kinh Secondary State officer 6.000.000 Dinh Nguyen Van Thao school 4 Kinh High State officer 12.000.000 DAo Thi Le Hang school 5 Kinh High State officer 8.400.000 Doan Thanh Trung school 6 Kinh High State officer 12.000.000 Nguyen Van Ta school 7 Kinh High State officer 12.000.000 Le Dinh Cang school 8 Kinh Secondary State officer 13.200.000 NguynVn Dung school 9 Kinh University, State officer 24.000.000 Phan Thi college . 10 Kinh Unversity, State officer 24.000.000 Ho Dhrc Thang . college. 11 Kinh Secondary State officer 12.000.000 Huynh Thuic Sinh school 12 Kinh Secondary State officer 10.000.000 Nguyen Thi Nga school 13 Kinh Secondary State officer 9.600.000 Mai Thanh QuAn school 14 Kinh Secondaiy State officer 12.000.000 15 _______ Nguyen Quyet Tien school Bui Thi Bi Ng6 16 Xuaa Ward- (-'IV Nhon LAm Via Qu_ Plan on compensation and resettlement 73 Quy Nhon - Tuy Hoa 220kV transmission line Feasibility Study 17 QuY3 Nh- mTh L City - Bnmh Lam Thi Ly Dinh Province _ _ _ _ _ _ _ _ _ _ _ _ _ 18 Nguy& V6 Hoang Kin Secondary Agriculture 8.000.000 school 19 NTaL Kinh Secondary Agriculture 13.500.000 __ __ _ __ _ __ _ __ _ __ _ __ _ __ _ _ _ _ _ _ _ _ _sch o o l_ _ _ _ _ _ _ 20 V5 Van Khoa Kinh Secondary Agriculture 10.800.000 school 21 Nguyen Ca Kinh Secondary Agriculture 28.800.000 _______ ~~school 22 DangVanTh8 Secondary Agriculture 15.000.000 Ding Vin M8 ~~~~~~~~~~~~school 23 Nguy&n Cong Kanh Kinh High Agriculture 18.900.000 school 24 Nguy Va Con Kin Secondaiy Agriculture 7.200.000 school 25 Ph#m Va DaL Kinh Agriculture 30.000.000 26 NguyeVaa Phit Kinh Agriculture 27XuanNn\- 1~n Kinh High Agricultuire 10.000.000 27 Phuong Nguyesn Van Thang school 28 Song Caa Vo Vm hKink High Agriculture 6.000.000 Diict-Pha . Phuschool 29 Yen Khng Ti8n Ki Agriculture Province __ _ __ _ 30 Song Caa Kinh Towyn- song PhozIi Le __ 31 Cau District LZ Thi Muri Kinh - Phua Yen Province Xa Xuan NguyGAo KinG Thg I- H,uy,n Song Clu - Tnh 33 An Dan Nguy&n CBng Thinh Kink 34 Commune- Kinh Plan on compensation and resettlement 74 Quy Nhon - Tuy Hoa 220kVtransmission line Feasibility Study 35 TDY An- Kinh 7.000.000 District - D6TjD" _____ 36 Phu YeV§n on Kinh Secondary Agnculture 15.000.000 Province school Agnciiliiire 10.000.000 37 Trong V9n Thus Kinh Secondary Agnculture 10.000.000 38 TC°6rDislraic-Dio VPhn K8 Kinh Heigh Agncultiure 10.000.000 81 ~~~~~~~~~~~~~~~~~~~~~school 39 Ch Thn hnV- i Kink Secondary Agriculture 15.000.000 Town - Tuy _ __school 40 An District- Kink In-service Agriculture 20.000.000 Phu Yen Phan Dinh Trung Wain. 41 ProViice <3ng Ding Kinh Agriculture 42 An Deinnh Wm Kinh Agricultiure 1.500.000 Provmnce han Tanh Hoang 4 T A e Thoui N Kinh Agriculture 1.500.000 44 District- Phu PhnSnKink Agriculture 45 ron Kinh High Agrculture 1.000.000 Province Phan Tnh Hocng school 46 Ny Th Lw Kinh High Agiculture 1.000.000 school 47 Phan Thnh Long Kink High Agricultuire 1.000.000 ____ _ __ ____ ___ school 48 Nzuv_n Va-n Luu Kink Agriculture 49 An Hiep Nguyen Hgc Kinh Agriculture 50 Co=mune - Kinh Agriculture District Thy HShV- i 51 n - Phuy V5T n Thum Kinh Secondao y Agriculture 10.000.000 yen ~ ~ ~ ~~~~~~~~____school 52 Province Kinh Agriculture 53 Chiu Sum = =__ Kinh Agriculture 54 Kinh High Agriculture 12.000.000 Hoa Kien Cao Kim 'Thhnh school__ _ _ _ _ _ _ _ _ __ _ _ _ _ _ Cominune- -sho 55 Thy Hoa Dao Van Hfig Kinh Secondary Agriculture 30.000.000 Towvn -Phu school______ 56 Yen H Kink Universit, Agriculture 34.000.000 _Province Nguyen EIih Huan . college _t__ Plan on compensation and resettlement 75 ~~~~~~~~~~~~~~ a Quy Nkhon - Tuy Hoa 220kV transmission line Feasibility Study 57 Bfii Thfi Khoa Kinh sHcigh AgIiculture 13.000.000 _________ ~~~~~~~~~~~~~~~~~school 58 Hoa Quag Nguyen TlNi Phuang Kinh Secondary Agriculture 14.000.000 Bac school 59 Coummue- V Thi lbng Kinh Secondary Agriculture 17.000.000 Phu Hoa school Distict - Phu Yen Province Plan on compensation and resettlement 76 CQNG IIOA XA HQ1 CIIU NGH1IA VlJiT NAM DQc Iflip'- Tu (lo - HaInhI pl)hIc -oOo- ,tf. .a . 4, C., nga, 2g. th(ing. .f . n 200 200f BlitN BAN TJ-IAM VAN CQNG D(5NG VE Je&. 2. Nhltrng ngtrfi mlh ilhr&ing: .(L.S........ Nani .. . ; Nrr 3. DE)i di8n Cty TVXD Dieni 4: .............................7...&. CAc valll (le tlianii van cunlg ilulig: 1. Ph( Mtnl Itlilii-lig Ciiiiii sicii li'eii quand.li dACe (ii bil, tati dililb Cll-. - Nlirng kliu vkrc trung hutig dcat cho dir in. - Dur kie.n tlii gian tie&ii IiAnh clho dtr in. - Pho^ bi8n cAc chfiln sAch cua Viet Naim vA WB. - Cac quy diilih phAp uhit Viet Naim vA chinlh s6ch WB c6 Ii8n quaii. - Cic chinhfslAch dcn bCi clio Dtr aln. - CAc kI1U tai djili cu (nieu c6). 2. Y kie"n efia din a pihtuolig VAe Ie lioacli den bii vA tai diiin cur: - nim naug xay ra dihtlh /ul'OIg bit lyi clia dli' dii + lD 'i v6yi jili'a c;ra: .... :(~.... .... :...... A,e ......e OiLk .. ... I. g....{m. t1 v .. A- ..... . . . . ... , ................... . . ................................................................ ...................................................................... + Doi v&i dat dai: ..... ...... Qi, ...... .. .'. . A,. ....................................................................... ":............................................. . .. . . .. . . ..............................................................................................................I........................ + DE)i v6i caiy coi: . ............' . I^t. ;..... L 1 ;..'.2 ...av .................................................................................................................................... ...................................................................................................................................... -D- D)oi vci m6i rt1rrnig lt nhi8in, xa Ft.ii: ........ T.4.& - Cdc Wim'I ph(il) gidin: 1tie'II: 11111 11111_~~~~~~~~~~~~~~~1 I~~~~~~~~~~~~~~~~~~~~~~~~~~~I + Trong giai doaf] tiliei ke& : ...... .... F.L ....... . ...................................................................................................................................... ...................................................................................................................................... 1- Trong giai doai liii cOng:......................................................................................... ...................................................................................................................................... ................................................................................. . ..... . . . . .. . . . . .. . . . . .. . . . . + rrong giai dooani van liciIi:......................................................................................... ...................................................................................................................................... ...................................................................................................................................... - Cdc ph,tI o'tg on digit bit, quty irlith c/ti ird deln bit: + Gia den biT,, hinh (li[rc d- C- g~o :n1diyj mlY)~ d4)iJd mj?1'I !)J - 1 7 . 1I 1 ...................................................................................................................................... Z ................. I............. ....... .......................................................................... ................... ,. jr *.*741?-7. 7-:P0P 41333 !MA !,C1 - .............. ...................... .............I............................... .................................................... .. . ......................................................... .. . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . ...... . . .... ... ............... ~ .......... - --l. . . . .. r:113.n !P T !QA 10( + ....................................................................................................................................... ....~ ~~~~. ip Ltt LOA lo up .hp inp 0.1 ~pqgai~n~qm p alii fpx,ux ii'p')j- ljlllp!t-,)V.A iqtial^) q3*01 O'll 3A1, 2110.1( 1-}V Ji f)v 1-11vl "')"I A-Z :.i13 qutip !1,' I'A lIys "a?~ tlet aj aA St.o.ltiq1:> t'4!) '1!w Z~IA. -(go nall).110 Itill?l IL] ''1p1 -),'D *tlB, i lCl(o' nq tiop I!1s Ilulilp v, - wnlb tLiil 9o3 fIPA 113yS IlUIljO LA tlueN 161A Alnl ciVtIcI tjlull Xnbu o, - *fJp 1iA 1H13N 1t!A 'nP 1PV,E t11lt143,B tl'P ! H wOt9 - * *tBU, ilp 01j3 1tIlEt1 upTl UB2T TL.tp} 1w3P1 'i - 'tie Alp ot4o Wi) SH1p unl.lq 3AA Illp &I.1l1N - *.na) tgtl,p qIy ilq uiap iiap munb llail qlaus tItiila 2unq tt. iilqla o°ldc 't :2tlQp 21163 tIUA ItUIq ?lap IUVA 31c ......................................... \.. >g% <: laGax. 1 3! c ,M~~~~yjy7 ~~~~~:v 111j C1XAI, XID "16P PkI ' ..............IlN--- - --7- - ...... ........ ............ -:2u.0jll lit{sE !Q lBtl 2tl.11tlq -Z ............................q ! . ~ ~ 4*~~~Jitfr') ~~~~~j7V~~~1//A1~~ .... U....:NiIfl IrM 11c. :.np iuuqj 1piu(ld ilinll .n lD HNia lylj VA flit Ntl(J l C-13VOI I 3X IA ONQOG fN()D NYA WVIlVL Ny£U NL31H -ooz -000 -------7 3N11V(4 1 1111-N - i1) I6I - (1 you 1N6 WVN.LtIIA VII-I:9N MU 1611 b- vx VOI- ONOO3 -I.~~~~~~~~ Sllo..lilud uip p aXiqb quip U ba tiqpju upX :lI - * p Sll(t S1!.hp SUX !IA!1 X1IO 21103 211.0*1111 i0ll BLI93 PPBIg1 U lflO l) ]II3 Ulla 116111O1 + v~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ ...................................................................................................................................... ...................... .......................... .------------------I--..................................................... ....... .............. ................. -' tZ) S ss M>7t7 nt; rml :n~~~~~~~~~~~~~W q tla s.l Y,l u'1l? uOuitl qtpeO Xn6. + ......................... .................................................................. ................................................................................... ; vs aga jWS lstS nL S IX ; f 2 ----v-7---w7 - :n1q liop !ttlo titx I witiq l? 11,Iw + ...................................................... ............................................................................ ..................................................................................... ........................ .~~~~~~~~~~~~~~.....l ---- 'jtl -i ' - -- '- 0'-*' IVDSiq tlop SeSwt,)I + ..................................................................,;.., . . . ^ . . . . .. . . . . . . . . . . .. . . . . . . . . . . ........................................................IEL ft~- I O !'V 2 1 .j ,... ............ ..... t 2 (01 ,+ ...:]IFL. ikkJI.S1 ,LNes lKiJiwSt. i .oc_ _- .. I